Views: 213 Author: Saijia Acoustic Publish Time: 2026-11-19 Origin: Site
In Qujing, Yunnan Province, a long-serving television studio was transformed into an XR integrated media studio in less than six months. Within its 1,500 m² space, the project brought together acoustic fit-out, television lighting, line-array sound reinforcement and an integrated three-screen LED system. Commissioned by Qujing Radio and Television Station and delivered on site by Guangzhou Saijia Acoustics & Lighting Engineering Co., Ltd., the project received its Letter of Award on November 8, 2023, and completed installation and commissioning within 87 days. Integrated system commissioning was completed in April 2024, when the studio entered live operation. Following the timeline from design and pre-construction preparation through key construction stages, completion and acceptance, this case study reviews the transformation using records of the original studio, construction photographs and completed-site images. It offers a reference for organizations planning to build or renovate studios and integrated media centres.
Project Item | Details |
Project Name | Qujing Radio and Television Station “Clean Qujing” TV Channel Studio Renovation and Upgrade Project |
Project Location | Qujing, Yunnan Province, China |
Purchaser | Qujing Radio and Television Station |
User Organization | Qujing Radio and Television Station (Qujing Integrated Media Centre, QJTV) |
Contract Period | Equipment installation, commissioning, construction and handover to be completed within 87 days after contract signing |
Project Scale | 1,500 m² integrated media centre, including a large multipurpose studio |
Scope of Work | Room-acoustic design, acoustic fit-out, lighting system, sound system, video system and LED display integration, furniture installation, system commissioning and maintenance |
Technical Features | XR studio design; EASE acoustic simulation; coordinated main LED screen, movable portrait screens and LED floor screen; one-touch scene recall |
Construction / Contractor | Guangzhou Saijia Acoustics & Lighting Engineering Co., Ltd. |
Three details in this project profile are particularly important. First, the procurement method: an open tender, through which Qujing Radio and Television Station selected the contractor in accordance with government procurement procedures. Second, the contract schedule: installation, commissioning, construction and handover were required to be completed within 87 days after contract signing, making this a time-critical renovation project. Third, the scope of work: from room-acoustic design and acoustic fit-out to lighting, audio, video and LED display integration, as well as furniture installation, system commissioning and maintenance, all systems were coordinated under one contractor. This is the essence of integrated audio, lighting and video delivery.
The project was driven by the programme-production needs of Qujing Radio and Television Station’s “Clean Qujing” television channel. After renovation, the studio needed to support the channel’s regular news broadcasts and feature-programme recordings, as well as variety shows, press conferences, knowledge competitions and other programme formats. For a broadcaster, the studio is a core space for integrated media production: acoustics determine pickup and sound reinforcement quality, lighting shapes the image, and LED displays define the visual presentation. All three are essential. This is why the tender combined sound, lighting, visuals and space into one integrated project.
On November 13, 2023, the first day the project team entered the site, photographs documented the studio’s original condition. The stage still had an old movable backdrop and traditional seating; the worn carpet and tangled cables reflected years of use; and the overhead lighting bars and outdated fixtures were awaiting removal. For a renovation project, this record of existing conditions is almost as important as the design drawings: it identifies what must be removed, retained or reinforced.

Figure 2. Existing conditions (November 13, 2023): the old studio before renovation, showing the stage, seating and facilities that had been in service for many years.
The design was developed around four priorities: sound, lighting, visuals and space. For acoustics, EASE software was used to build a three-dimensional room model and simulate speech intelligibility (STI), sound-field distribution and reverberation time. The results informed the placement of sound-absorbing materials: high-absorption treatment was specified for the side walls beside the audience seating; the ceiling combined absorption and diffusion while accommodating lighting suspension; and openings in the building envelope were sealed for sound insulation. For lighting, high-CRI (Ra ≥ 90) LED television panel lights with consistent colour temperature formed the basic key-lighting system in the performance area, with all fixtures grouped by zone under the DMX512 digital dimming protocol. For sound reinforcement, line-array loudspeakers were suspended on both sides of the stage opening, and their positions were included in the sound-field calculations during acoustic simulation. For visuals, the large LED display formed the hardware foundation of the XR system. These four priorities converged in one coordinated detailed-design package, rather than being designed independently by four separate subcontractors.
The design renderings clearly show two operating modes for the studio. In performance mode, the main screen and side portrait screens display coordinated dynamic visuals, while effects lighting and a star-cloth backdrop create the stage atmosphere. Three camera positions cover dance and variety-show recording. In conference mode, the main screen switches to press-conference content, four portrait screens are arranged symmetrically, and the key lighting is even and practical to ensure clear speech. The overall audience-view rendering also established the intended appearance of the tiered seating with red-and-black chairs and blue acoustic wall panels. These design concepts were subsequently realized during construction and integrated commissioning.

Figure 3. Design rendering: panoramic view from the audience towards the stage, showing tiered seating, blue acoustic wall panels and LED screen positions.

Figure 4. Design rendering: view from the stage towards the audience, showing the multi-level seating, key-lighting bridge and lighting suspension layout.

Figure 5. Design rendering — performance mode: coordinated dynamic visuals on the main and portrait screens, with effects lighting creating the stage atmosphere.

Figure 6. Design rendering — conference mode: press-conference visuals and a symmetrical portrait-screen layout.
Unlike traditional green-screen chroma-key production, this project uses a wraparound visual system comprising a main LED screen, movable portrait screens on both sides and an LED floor screen. The portrait screens can be repositioned to suit different programme formats, while the floor screen extends towards the front edge of the stage, carrying the visuals from the background onto the floor. During system design, the relationship among screen resolution, viewing distance and camera parameters was coordinated to prevent moiré patterns and scan lines during filming. The LED screens’ switching power supplies and drivers were powered in separate groups in strict accordance with electrical distribution requirements. The effect of screen illumination on the stage lighting environment was also addressed through coordinated lighting design.
No. | Key Challenge | Challenge Analysis | Solution |
1 | High installation-accuracy requirements for movable side screens | Movable side screens require highly level and smooth-running tracks. Installation deviations can cause the screens to stick or become misaligned, affecting operation. | Use a specialist installation team; accurately set out track positions and strictly control levelness and parallelism. Repeatedly test and adjust operation after installation to ensure smooth movement and precise positioning. |
2 | Difficult installation of manually operated flip-up aluminium panels above the stage | This is work at height. The flip mechanism requires accurate installation and smooth operation, making construction control demanding. | Implement appropriate work-at-height safety measures. Install the flip mechanisms and aluminium panels in accordance with the design. Test each group after installation for smooth movement and reliable locking to ensure safe operation. |
3 | Safety risks when modifying and reinforcing the existing studio equipment level | The existing equipment level requires structural reinforcement. Construction must preserve the safety of the existing structure while accommodating additional loads, creating both technical challenges and safety risks. | Carry out the work strictly in accordance with the reinforcement plan to ensure the equipment level meets structural safety requirements. Securely connect suspended components to the building structure and perform individual anti-fall checks. |
4 | Audience-seat positioning must preserve sightlines | Seat layout must strictly comply with sightline design requirements. Positioning deviations may obstruct audience views and affect the viewing experience. | Set out positions in accordance with the design drawings and verify sightlines through simulation before construction. Check seat elevations and positions row by row during installation to ensure unobstructed views from every seat. |
This list of major challenges formed the construction roadmap for the entire project. The four principal risks were the installation accuracy of the movable side-screen tracks, the installation of manually operated flip-up aluminium panels at height, reinforcement of the existing equipment level, and precise audience-seat positioning to preserve sightlines. The corresponding countermeasures were accurate setting-out and repeated commissioning; safety protection and staged adjustment; reinforcement in accordance with an approved plan; and setting-out supported by sightline simulation and verification. Notably, none of these challenges could be solved simply by “buying better equipment.” They all depended on workmanship and project management — the essential difference between a renovation project and equipment procurement alone.
The project retained three technical briefing records covering LED display acceptance and operation, installation of lighting fixtures, switches and sockets, and installation of electrical cables. These briefings covered the work teams responsible for the various audio, lighting and video trades. They translated requirements in standards such as GB 50303, Code for Acceptance of Construction Quality of Building Electrical Works, into practical procedures. Cable bending radii and fixing intervals, installation tolerances for lighting fixtures, switches and sockets, and LED display acceptance criteria and operating precautions were all explained before work began. For a project delivered by a team working away from its home province, briefings that reach every crew are essential to consistent workmanship.
The contract required installation, commissioning, construction and handover to be completed within 87 days after signing. The project team travelled from Guangzhou to Qujing, Yunnan Province, to work on site. Detailed design was used to manage the risks of working at a remote location. Before construction, the team completed and cross-reviewed the acoustic construction drawings, lighting suspension drawings, loudspeaker suspension-point drawings, LED screen steelwork drawings and power-distribution layouts, resolving potential site changes at the drawing stage. Components such as acoustic panels and lighting brackets were prefabricated in the factory wherever possible and assembled on site to reduce delays caused by sourcing additional materials across provinces. Materials were shipped in batches according to the construction sequence to control on-site storage and secondary handling.
The first major task in the renovation was demolition. From late November to early December 2023, the old lighting bars, outdated fixtures and abandoned cable trays were dismantled, and old cables were sorted and removed. Demolition was not simply a matter of taking everything down. The existing overhead equipment level had to be modified and reinforced so that it could continue to support the new lighting suspension system and LED screen steelwork. All suspended components were securely connected to the building’s structural layer, with individual anti-fall checks and load verifications. Site photographs from April 2024 show technicians inspecting the winches and wire-rope system on the existing equipment level one by one, providing a safety basis for the subsequent operation of the lighting bars.

Figure 7. Construction in progress (November 30, 2023): removal of the old lighting bars and traditional lighting fixtures.

Figure 8. Construction in progress (December 2, 2023): transportation and zoned installation of new cables.

Figure 9. Construction in progress (April 12, 2024): individual inspection of the winches and wire-rope system on the existing equipment level.
In late December 2023, construction of the steel structure for the tiered audience seating got fully underway. Steel platforms were installed section by section according to the setting-out marks, creating the foundation for the seats, sightlines and evacuation aisles. At the same time, the new overhead lighting bars and track system were positioned and numbered. Suspension points for key, top, side and back lighting were coordinated with the acoustic ceiling elevations as part of the integrated services layout. Power and fire-protection services were installed first, followed by the lighting suspension system and signal cable trays, preventing clashes between different trades.

Figure 10. Construction in progress (December 27, 2023): steel structure for the tiered audience seating and installation of the new lighting-bar tracks.
The acoustic walls use a perforated sound-absorbing panel construction. Site photographs from February 2024 document the colour-spray test: workers applied a trial coat of blue finish to the perforated panels, and large-scale application began only after the colour and width of the colour bands had been approved. The principle was to approve a sample first and proceed with the full area only afterwards; work would not be expanded if the colour failed to meet the requirements. In March 2024, installation of the blue acoustic walls progressed alongside the audience seating. Both the sealing of the acoustic construction and the appearance of the absorptive finish were checked. Behind the panels is a broadband sound-absorption assembly; the visible surface gives the studio its distinctive appearance. Here, acoustic performance and interior design come together.

Figure 11. Construction in progress (February 2024): blue paint sample test on the perforated acoustic wall panels.

Figure 12. Construction in progress (March 24, 2024): installation of the blue acoustic walls alongside the audience seating.
The first item on the project’s challenge list — the installation accuracy of the movable side-screen tracks — was put to the test during equipment installation. The tracks were accurately set out, and their levelness and parallelism were checked section by section. After the screens were lifted into position, their movement was repeatedly tested and adjusted. At the same time, power-amplifier racks and other sound reinforcement equipment were installed in designated positions, with clear responsibility labels on each unit and identification for every cable termination. By this stage, the hardware for the three major systems — lighting, audio and video — had all arrived in the studio. The remaining task was to make them work together as one system.

Figure 13. Construction in progress (March 24, 2024): power-amplifier racks installed, with clearly identified responsibility labels.
Before handover, commissioning was carried out at three levels: individual equipment, subsystem and multi-discipline integration. Acoustic construction was checked for airtightness and sound leakage. Each lighting fixture was inspected for colour temperature, colour rendering and flicker. The sound reinforcement system was adjusted for sound-pressure-level distribution and feedback suppression. The LED screens and video signal chain were tested for signal integrity, image stitching and camera compatibility. After commissioning, lighting scenes, sound reinforcement settings and LED screen content were grouped and preset by programme type. News mode provides natural-looking lighting on presenters and clear speech; gala mode activates effects lighting and dynamic visuals on the floor screen; and press-conference mode switches to symmetrical lighting and conference visuals. Directors and duty technicians can recall these configurations with one touch, enabling programme changes without changing operators.
The completion photographs taken on April 17, 2024 show the new studio taking shape: the blue acoustic walls have neat finished edges, new seats are ready on the tiered platforms, and the overhead LED television lighting array, line-array loudspeakers and three-screen system are all in place. Four days later, on April 21, the main LED screen was illuminated with the words “Qujing Integrated Media Centre.” From the worn carpet and movable backdrop documented on November 13, 2023, to the integrated three-screen system in April 2024, the 1,500 m² studio had been transformed in less than six months.

Figure 14. Completed studio (April 17, 2024): the main LED screen and two side portrait screens operating as a three-screen system, with the star-cloth backdrop and new seating in place.

Figure 15. Completed studio (April 17, 2024): view of the stage from the audience seating, showing the tiered platforms, acoustic walls and completed three-screen system.

Figure 16. System testing (April 22, 2024): the main LED screen illuminated with “Qujing Integrated Media Centre.”
A separate scanned copy of the final completion acceptance report was not retained for this project. The handover record is therefore based on integrated system commissioning and actual operation, as documented. Following joint preliminary inspections by the different trades, integrated system commissioning was completed in April 2024. The studio’s functions entered live operation, and the facility was successfully handed over for use. For broadcasters, the ultimate test of a studio is its picture and sound: natural skin-tone reproduction during news broadcasts, the lighting atmosphere of a gala, and speech intelligibility at a press conference were all evaluated in actual operation.
Acceptance of an integrated audio, lighting and video studio involves more than checking whether the equipment can be switched on. For acoustics, inspect the construction details and sealing. For sound reinforcement, measure four parameters in accordance with the applicable standards: maximum sound pressure level, transmission frequency response, sound-field non-uniformity and transmission gain. For lighting, check illuminance, colour-temperature consistency and suspension safety. For LED screens, inspect image-stitching flatness, dead pixels and camera compatibility. For mechanical suspension systems, review load capacity and anti-fall inspection records. Without measurement data, it is impossible to determine whether the performance meets the required targets. This is why acoustic performance indicators and testing requirements should be clearly specified in the tender documents.
Since entering service, the studio has quickly become a core venue for integrated media production at Qujing Radio and Television. News broadcasts, feature programmes, variety shows, press conferences and knowledge competitions are produced here in turn. The XR three-screen system has elevated the channel’s visual presentation. Operating photographs dated June 24, 2024 show the stage machinery, curtains and lighting-bar system running smoothly. The 87-day schedule, the out-of-province site team and the four major construction challenges ultimately translated into clean images on camera and clear voices through the loudspeakers. The project demonstrates that upgrading a broadcast studio depends on the integrated coordination of acoustics, lighting, visuals and space — not on the specifications of any single piece of equipment.

Figure 17. In operation (June 24, 2024): the stage curtains, flip-up aluminium panels and lighting-bar system operating smoothly.
Q: How does acoustic fit-out for an integrated media studio differ from ordinary interior decoration?
A: Ordinary interior decoration focuses on appearance and convenience. Acoustic fit-out for a studio is governed by measurable targets such as reverberation time, sound absorption, sound insulation and background noise. Acoustic calculations and construction detailing should be completed before materials are selected and installed. Muffled or “sticky” voices, unclear words and humming coloration in a studio are often caused by ordinary decoration that overlooks acoustic performance. Such problems are difficult to correct later with equipment alone.
Q: What makes renovating an old studio more difficult than building a new one?
A: The challenge is working within existing constraints. The old building structure, equipment level and service routes are already fixed. In this project, modifying and reinforcing the existing equipment level was one of the greatest risks: construction had to preserve the safety of the existing structure while accommodating the additional loads from new lighting suspension and LED screens. Removing old lighting bars, fixtures and cable trays also had to be done without damaging acoustic and structural elements that were to remain. A renovation must begin with a site survey, proceed through detailed design, and only then move into construction; it cannot simply follow the approach used for a new-build project.
Q: How does an XR studio differ from a traditional green-screen or blue-screen studio?
A: Traditional green-screen and blue-screen studios rely on post-production chroma keying to composite backgrounds. This can produce visible edge artifacts around people and less realistic lighting. An XR studio uses LED screens directly as the filming background. The main screen, movable portrait screens and floor screen display coordinated visuals, placing presenters and performers in a real illuminated environment with greater depth and realism while eliminating the chroma-keying step. XR requires more careful coordination of screen specifications, lighting ratios and camera-to-screen distances, so an integrated team should manage the design.
Q: Why choose LED television lighting fixtures for a studio?
A: Recorded images need to reproduce natural skin tones. A colour rendering index (Ra) of at least 90 is recommended, together with consistent colour temperature across scenes and flicker-free operation. LED television panel lights generate less heat, have a long service life, and offer dimming and colour-temperature adjustment. They are suitable for extended recording sessions and XR production with LED screens. Ordinary office lighting cannot meet skin-tone reproduction requirements; images may look grey or flicker, and the colour temperature may visibly mismatch the LED display.
Q: Why is installation accuracy so important for movable side screens?
A: Movable side screens require very high track-levelness and parallelism. Track deviations can cause the screen to move jerkily, become misaligned or even derail, directly affecting transitions between programme formats. This project used a specialist installation team to set out the tracks accurately, control their levelness and repeatedly test screen movement after installation. The result was smooth movement and precise positioning. This kind of work, hidden in the track installation, is one of the factors that distinguishes a professional studio project from ordinary interior decoration.
Q: How should organizations in Yunnan and Southwest China choose a studio audio and lighting contractor?
A: Look for an integrator with relevant integrated media studio experience and the ability to deliver sound, lighting, visuals and control as one coordinated system. Key criteria include experience with out-of-province site work; whether the company completes detailed sound-field and lighting design, such as EASE simulation, before quoting; whether it uses established brands and standard protocols such as DMX512; and whether it provides commissioning, training and long-term maintenance. This project is a representative example of Guangzhou Saijia’s work for a broadcaster in Yunnan.
Q: How should an integrated media studio be maintained after handover?
A: A recommended approach is quarterly inspections combined with an annual specialist assessment. The lighting team should check fixture cooling, dimming circuits and suspension points to prevent flicker and colour shifts. The sound reinforcement system should have its loudspeakers, microphones and peripheral equipment calibrated to control background noise and feedback. LED screens should be checked for power supply issues, image-stitching flatness and dead pixels. Acoustic construction should be inspected regularly for seal integrity and the condition of sound-absorbing surfaces. Keep inspection records and repair any deterioration promptly.
Pitfall: Tendering a studio renovation as ordinary interior decoration.
Solution: Ordinary decoration is judged by appearance, while studio acoustic fit-out is judged by reverberation time, sound insulation and background-noise targets. A specialist team should complete acoustic calculations and construction detailing before work begins, and acceptance should be based on acoustic test data. Acoustic performance indicators and testing requirements should be included in the tender documents; otherwise, the result may look attractive but perform poorly during recording.
Pitfall: Assuming that a large space only needs loud enough speakers and no acoustic design.
Solution: Large spaces tend to have long reverberation times and are prone to echoes and sound focusing. Simply increasing amplifier power makes the sound louder but less clear. Acoustic construction and EASE sound-field simulation should come first, followed by appropriate loudspeaker and amplifier selection. This is the way to achieve speech clarity at the rear of the room and even coverage throughout the venue.
Pitfall: Assuming that more and larger LED screens are always better.
Solution: Screen size and quantity should be determined by programme formats and filming requirements. Screen reflections, brightness and colour temperature directly affect presenter lighting and image quality, so the LED system must be designed in coordination with the lighting system. Adding screens without a clear purpose also increases electrical and heat loads. In this project, the sizes of the main screen, portrait screens and floor screen were determined by programme requirements, not by the maximum available budget.
Pitfall: Assuming that ordinary lighting fixtures are sufficient for a studio.
Solution: Studio lighting fixtures should have Ra ≥ 90, consistent colour temperature and flicker-free operation, with separate lighting zones for key, top, side and back lighting. Ordinary lighting cannot meet skin-tone reproduction and filming requirements when used with LED screens; images may look grey or flicker, and people may appear visually disconnected from the screen content.
Pitfall: Installing new equipment on the existing equipment level without a structural safety assessment.
Solution: The equipment level in an old studio was designed for the loads of the original lighting system. Suspending additional equipment such as LED screens and new lighting bars without checking the structure creates safety risks. Before renovation, inspect the existing equipment-level structure and suspension points. Reinforce them where necessary, recalculate the loads and carry out individual anti-fall checks. This was one of the first items on this project’s list of major challenges.
Pitfall: Allowing the acoustic, lighting, audio and video trades to work independently as separate packages.
Solution: Disconnected work by different trades can lead to service clashes, sound leakage through penetrations, interference between screens and lights, and repeated rework. Use coordinated detailed design, integrated services planning and a unified commissioning checklist so that acoustic, lighting, sound reinforcement and video requirements are all met in one coordinated construction process.
Integrated media studio projects span building acoustics, television lighting, sound reinforcement, video displays, fire protection and electrical engineering. Design and acceptance should therefore reference the relevant national standards and radio, film and television industry standards:
Standard No. | Standard Title |
GY/T 5086-2012 | Acoustic Design Code for Radio and Television Recording (Broadcast) Rooms and Studios |
GY 5022-2007 | Measurement Specification for Reverberation Time in Radio and Television Announcer / Studio Rooms |
GY 5045-2006 | Design Code for Lighting Systems in Television Studios (including mandatory provisions) |
GB/T 50356-2005 | Code for Architectural Acoustics Design of Theatres, Cinemas and Multipurpose Auditoriums |
GB 50118-2010 | Code for Design of Sound Insulation of Civil Buildings |
GB 50371-2006 | Code for Design of Sound Reinforcement Systems in Auditoriums |
GB/T 4959-2011 | Methods of Measurement for Sound Reinforcement Characteristics in Auditoriums |
WH/T 97-2022 | Acceptance and Testing Specification for Stage Lighting Systems |
WH/T 60-2013 | General Technical Requirements for LED Stage Lighting Fixtures |
GB/T 14218-2018 | Performance Parameters and Test Methods for Electronic Dimming Equipment |
SJ/T 11141-2017 | General Specification for LED Displays |
GB 50303-2015 | Code for Acceptance of Construction Quality of Building Electrical Works |
GB 55024-2022 | General Code for Building Electrical and Intelligent Systems |
GB 50116-2013 | Code for Design of Automatic Fire Alarm Systems |
GB 50222-2017 | Code for Fire Protection Design of Interior Decoration of Buildings |
Guangzhou Saijia Acoustics & Lighting Engineering Co., Ltd. specializes in acoustic and lighting engineering. Its projects include acoustic fit-out and integrated audio, lighting and video systems for television studios, integrated media centres, theatres, concert halls, auditoriums, lecture halls, sports venues and recording studios. The company undertakes projects in China and overseas, with a focus on South China, East China, Central China and Southwest China. This project is a representative example of its service to a broadcaster in Yunnan, covering out-of-province on-site delivery, detailed design, integrated system commissioning and operator training through a one-stop service.