24 Recording Studios in One Fit-Out: GZ Radio & TV

Views: 213     Author: Saijia Acoustic     Publish Time: 2026-11-18      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
Reddit sharing button
Threads sharing button
sharethis sharing button

Case Study: Acoustic Fit-Out of Simple Recording Studios at the New Headquarters of Guangzhou Broadcasting and Television Station — The Story Behind 24 Recording Studios


At the new headquarters building of Guangzhou Broadcasting and Television Station, an acoustic fit-out project covering only 167 square meters but requiring the one-time delivery of 24 simple recording studios was completed in just 40 days, from bid award on October 24, 2016 to completion on January 15, 2017—five days ahead of the 45-day tender requirement. These studios were designed for voice-over production of news and other spoken-word programs. Reverberation time was controlled at 0.25±0.1 s, background noise at the NR-25 curve, and the speech intelligibility index RASTI above 0.65. All were accepted against the substantive requirements marked with ★. Following the timeline of design, pre-construction preparation, key construction stages, completion, and acceptance, this case study breaks down the full development of the broadcasting station's recording-studio acoustic fit-out project and provides a reference for broadcasting organizations and integrated media centers planning voice-over rooms, recording studios, and podcast rooms.


1. Project Overview

Project Element

Details

Project Name

Acoustic Fit-Out and Equipment Procurement Project for Simple Recording Studios at the New Headquarters of Guangzhou Broadcasting and Television Station (Package 1)

Purchaser

Guangzhou Broadcasting and Television Station (New Headquarters, No. 231 Huanshi Middle Road, Yuexiu District, Guangzhou)

Contractor

Guangzhou Saijia Acoustics & Lighting Engineering Co., Ltd.

Start/Completion Dates

December 6, 2016 – January 15, 2017

Project Scale

24 simple recording studios on the 2nd and 7th floors; total acoustic fit-out area approximately 167 m²

Scope of Work

Recording-studio acoustic fit-out, noise control, electrical and lighting works, fire-protection modification, HVAC modification, and procurement/installation of recording equipment

Core Acoustic Targets

Reverberation time 0.25±0.1 s; background noise NR-25; speech transmission index RASTI >0.65; sound-insulating door >35 dB (implementation plan ≥40 dB); sound-insulating observation window >50 dB; wall sound insulation >50 dB


2. Before Construction: Design Stage (October 2016) — The Acoustic Challenge of 24 Small Rooms

For any recording studio that performs well, much of the work is done before construction begins. The early stage of this project was captured in a design presentation prepared in October 2016. From functional positioning and room layout to sound-insulation construction and acoustic simulation, it addressed one major challenge step by step: how to build a large number of recording rooms inside an office building.


2.1 Functional Positioning: Voice Recording Studios Designed for News Production

The simple recording studios at the new headquarters were primarily intended for voice-over production of news and other spoken-word programs. Their design positioning was therefore clear: the studios served news production, with an emphasis on clear, full and highly intelligible sound, while recording equipment was selected with cost-effectiveness as a priority. Speech recording has very different acoustic requirements from music recording—speech calls for a clean, controlled “dry” sound, short reverberation decay, a flat frequency response, and background noise low enough to be imperceptible to the microphone. This determined the three core design priorities: strong sound absorption, strong sound insulation, and low noise. The design directly referenced broadcasting-industry standards: sound-insulating doors and windows followed the GY/T 5043-2013 framework, “Indoor Environmental Requirements for Technical Rooms in Radio and Television Centers”; noise control followed GY/T 5086-2012, “Acoustic Design Specifications for Radio and Television Recording (Broadcasting) Studios and Production Studios”; and reverberation time followed GY 5022-2007, “Measurement Specifications for Reverberation Time in Radio and Television Broadcasting (Production) Studios”—using standards rather than relying on subjective judgment.


2.2 Overall Layout: 18 Studios on the 2nd Floor and 6 on the 7th Floor

The acoustic fit-out area was divided into two zones: the news production network on the 2nd floor and the integrated production network on the 7th floor, with a combined area of approximately 167 square meters. On the 2nd floor, 18 simple recording studios were separated from the original planned Area #202, covering about 92 square meters. On the floor plan, Voice-over Areas A, B and C were arranged in bands around the news editing area, keeping editing workstations just steps away from the recording rooms. The 7th floor contained 6 recording studios, each measuring approximately 5.3–6.1 square meters, together with a machine room, lounge and corridor. Another easily overlooked detail on the 7th-floor plan was the use of 180 mm multi-damping lightweight composite sound-insulating walls and acoustic corner treatments. Breaking up parallel wall surfaces in a small room is a low-cost, high-return way to suppress flutter echoes and standing waves.


1

7th-Floor Recording Studio Floor Plan (Design Stage): Layout of 6 recording studios (5.3–6.1 m² each), machine room, lounge and corridor; 180 mm multi-damping lightweight composite sound-insulating walls with acoustic corner treatments.


2

2nd-Floor News Production Network Voice-over Area Floor Plan (Design Stage): 18 simple recording studios arranged in Voice-over Areas A, B and C around the original planned Area #202.


2.3 Acoustic Calculation: Calculate the Performance Targets Rather Than Guessing Them

For small-room acoustics, “good enough” is the biggest taboo. During the design stage, separate reverberation-time calculation sheets were prepared for the 2nd and 7th floors. Taking one 2nd-floor studio as an example, its clear dimensions were 2.82 m × 1.65 m × 3.2 m, with a floor area of 4.65 m² and a volume of 13.96 m³. The sound absorption of the flame-retardant acoustic carpet, polyester-fiber acoustic ceiling panels, two wall absorption constructions, 120 mm skirting, and Grade III sound-insulating door was accumulated by frequency band from 125 Hz to 4000 Hz, resulting in a full-band T60 of approximately 0.25 s and an NR-25 background-noise target. EASE 4.3/4.4 acoustic simulation software was then used to model the studios on both floors, producing consonant loss, reverberation curves, and speech intelligibility (STI) distributions. Simulated values ranged from 0.69 to 0.90, supporting the design target of RASTI > 0.65. Calculate first, simulate first, then build: this was the basis for bringing all 24 rooms to the required acoustic performance at completion.


3

2nd-Floor Recording Studio Reverberation-Time Calculation Sheet (Design Stage): Single-room dimensions 2.82 m × 1.65 m × 3.2 m; T60 = 0.25 s calculated by frequency band; background noise NR-25.


4

EASE 4.3 Speech Intelligibility (STI) Simulation (Design Stage): Simulated values of 0.69–0.90, corroborating the design target of RASTI > 0.65.


2.4 Walls and Ceiling: Zoned Absorption for Mid-to-High and Mid-to-Low Frequencies

Speech recording is particularly sensitive to harsh high-frequency flutter echoes and muddy low-frequency hum. The wall treatment was therefore divided into two types. One half used a light-gauge steel framing system filled with 50 mm bagged superfine glass wool, a 5 mm rear air cavity, and a finished acoustic material surface, primarily handling mid-to-high frequencies. The other half used light-gauge steel framing with a 5 mm plywood face, a 100 mm rear cavity filled with glass wool, and a polyester-fiber acoustic panel finish, reducing panel resonance and primarily handling mid-to-low frequencies. The two constructions were arranged alternately. Together with a full ceiling layer of 600 × 600 × 50 mm high-performance acoustic wool with a density of 32 kg/m³ and an absorption coefficient α > 0.6, protected in double bags against dust, this allowed the reverberation time to remain at 0.25±0.1 s with a flat frequency response. Ceiling colors also differed by floor: dark-gray polyester-fiber panels on the 2nd floor created a modern appearance, while white polyester-fiber ceiling panels on the 7th floor were paired with soft indirect lighting, balancing acoustic performance with spatial atmosphere.


2.5 Sound-Insulation System: A Complete Chain Integrating Walls, Doors, Windows and Floor Slab

With many rooms packed into an office building, sound insulation was the first critical line of defense. The walls used 240 mm/180 mm multi-damping lightweight sound-insulating construction: double 9 + 12 mm gypsum boards with a 0.6 mm steel plate between them increased surface mass and damping; UC75 light-gauge steel studs were flexibly connected to prevent rigid sound transmission; 50 mm sound-insulation wool was placed inside the cavity to suppress cavity resonance; and 3 mm vibration-isolation rubber pads further broke sound bridges. The wall sound-insulation requirement was above 50 dB, achieving professional-grade isolation at a much lower thickness than a brick wall. Sound-insulating doors followed Grade III broadcasting-industry requirements. The tender required more than 35 dB, while the implementation plan achieved ≥40 dB, using a 100 × 60 mm flame-retardant environmental-friendly timber frame, 32 kg/m³ polyester-fiber acoustic wool inside the door, industrial felt sealing along the door gaps, a custom 1 mm stainless-steel threshold, and imported emergency-release hardware. All wood products received fire-, moisture-, and termite-resistant treatment. Sound-insulating observation windows used 12 mm + 10 mm double panes of unequal-thickness tempered glass, sized and adjusted on site at an 85° inclination. The inclined installation reduced coupled resonance between the panes and prevented reflected light from creating double images. The cavity between the glass panes was dried, while the glass-to-frame interface was sealed with industrial felt and finished with clear silicone sealant, achieving more than 50 dB sound insulation. The floating floor used a zigzag plywood support base, 18 mm formwork, 5 mm moisture-resistant vibration-isolation rubber pads, and flame-retardant acoustic carpet, separating each layer to keep footfall and furniture-impact noise out of the floor slab. Walls, doors, windows and floor slab therefore formed a complete sound-insulation chain; if any link failed, the overall isolation would be compromised.


2.6 Design Highlights: Enhanced Sound Insulation with a Double-Layer Gypsum-Board Ceiling

The tender proposal went beyond the basic requirements in four ways. First, to enhance sound insulation, a 12 mm gypsum-board acoustic ceiling was added beneath the original structure. The detail drawing shows Φ8 fully threaded suspension rods with anti-corrosion treatment, followed by a 12 mm gypsum board, U75 light-gauge steel framing, 32 kg/m³ double-bagged superfine glass wool (50 × 600 × 600 mm) inside the framing, and polyester-fiber panels as the finish. The cavity between the two assemblies created a composite “panel–cavity–panel” sound-insulation system, further reducing sound transmitted through the floor slab. Second, because HVAC ducts could cause cross-room sound transmission, acoustic ducts and sound-attenuating outlets were specified. Third, the sound-insulating door performance was upgraded from the tender requirement of 35 dB to 40 dB. Fourth, the construction period was committed at 42 days, better than the tender requirement of 45 days. These four enhancements were written into the bid proposal and became the quality baseline for construction.


5

Ceiling Sound-Insulation Detail (Design Stage): A 12 mm gypsum-board acoustic ceiling added beneath the original structure, forming a composite assembly with U75 light-gauge steel framing, double-bagged superfine glass wool and polyester-fiber panels.


2.7 HVAC Noise Control, Fire-Protection Modification and Technical Power Distribution

HVAC is one of the most common sources of background noise in recording studios. The design required every studio to have an air-conditioning outlet connected to the building's central HVAC system. Supply and return ducts were fitted with sufficiently long silencers, while airflow velocity inside ducts and silencers was controlled to prevent regenerated airflow noise. Ceiling return grilles were also used to control airflow velocity and treated for vibration isolation. Fire-protection modifications followed GB 50016-2014, the Code for Fire Protection Design of Buildings, while studio fire-protection requirements followed GY 5067-2003, the Code for Fire Protection Design of Radio and Television Buildings. Finishes mainly used B1-grade or higher flame-retardant materials; concealed wood structures, including wood studs and base boards on both sides, were coated with two layers of fire-retardant paint; superfine glass wool was film-wrapped to prevent dust; and fabrics used permanently flame-retardant, acoustically transparent textiles. Environmental requirements met the E1 level of GB 18580-2001. Technical power distribution covered lighting and professional equipment for the studios on both floors. Studio illumination was 350 lx and public areas/machine rooms 200 lx. Emergency and evacuation lighting was treated as a Class II load with automatic transfer at the terminal ends of two power supplies. Each studio was equipped with a “RECORDING IN PROGRESS” indicator so the recording status was immediately visible and accidental entry could be avoided.


2.8 Recording Equipment: Two Parallel Procurement Routes

The recording equipment for the 24 studios was divided into two technical routes according to existing room conditions. Route 1: 12 studios used the station's existing voice-over workstations, with dedicated professional audio interfaces and voice-over software; only voice-over microphones, a vocal channel processor (microphone preamp) and monitor-volume processor were required, ensuring vocal recording quality and convenient level adjustment and monitoring. Route 2: the other 12 studios used non-linear editing workstations with USB external professional audio interfaces. The core specifications were broadcast-grade: 24-bit/192 kHz conversion, signal-to-noise ratio of at least 110 dB, integrated high-quality microphone preamps, at least 2 inputs/4 outputs, latency no greater than 2 ms, independent headphone output, and 48 V phantom power. Twenty-six voice-over microphones were specified, featuring supercardioid pickup, 1-inch large diaphragms, maximum SPL ≥125 dB and S/N >76 dB, together with desktop universal shock mounts and windscreens. Acoustic construction and equipment were linked as one system from the design stage: once the room was clean and controlled, the signal chain could make the voice clean and full, providing dual assurance for the final quality of spoken-word programs.


3. Pre-Construction: Award, Contracting and Detailed Design (October–November 2016)

3.1 From Notice of Award to Contract Signing

On October 24, 2016, Guangdong Guangzhao Tendering & Procurement Co., Ltd. issued the notice of award. Guangzhou Saijia Acoustics & Lighting Engineering Co., Ltd. won Package 1 of the “Acoustic Fit-Out and Equipment Procurement Project for Simple Recording Studios at the New Headquarters of Guangzhou Broadcasting and Television Station” (Project No. 0877-16GZTP01A362). The awarded scope covered the acoustic fit-out of the simple recording studios, with a contract award price of RMB 958,095.65 and a completion period of no more than 42 days—three days shorter than the tender requirement of 45 days.


3.2 Detailed Design and Confirmation of Additional Works

November after the award was the detailed-design window. The integrated drawings were finalized and issued on November 7, 2016, and the estimate for additional works was confirmed on the same day. On the 2nd floor, the additions included 37.2 m² of 120 mm multi-damping lightweight composite sound-insulating wall, finished decorative doors and locks, ordinary electrical work and wall latex paint, and fire-protection column cladding. On the 7th floor, 172.29 m² of 180 mm sound-insulating wall was upgraded to 240 mm—a typical “small additional cost for a major improvement” decision, with a price difference of RMB 19.68/m²—along with additional 120 mm sound-insulating walls, tempered-glass partitions, cement self-leveling and plastic flooring, emergency lighting and exit signs. The total value of the additional works was approximately RMB 114,700. These additions may appear minor, but they were closely connected: the wall upgrade directly supported the 7th-floor sound-insulation targets; self-leveling and plastic flooring provided the flat base for the floating floor; and emergency lighting supported fire-protection acceptance. Resolving interfaces and construction assemblies at the drawing stage prevented the 40-day schedule from being lost to rework and waiting.


3.3 Pre-Construction Preparation: Interface Definition and Sequence Planning

Another key task before mobilization was defining the construction interfaces. Room 202 on the 2nd floor had completed basic finishes, with power and lighting routed to the distribution box, but technical power still required modification. Some rooms on the 7th floor remained unfinished; the basic HVAC system was complete but had not been commissioned, and fire-protection work was only at the basic stage. Based on the site survey, the contractor and purchaser defined each interface one by one: after technical power modifications, the contractor would complete subsequent cabling and technical grounding; studio air outlets would connect to the building's central HVAC system; smoke control and exhaust, fire alarms, sprinklers and smoke detectors would be integrated with the building systems, with the contractor responsible for fire-protection filing, inspection and HVAC modification acceptance. The workflows for five lines—acoustic fit-out, HVAC modification, fire-protection modification, electrical/lighting, and recording-equipment installation and commissioning—were planned in advance. Concealed works were to be inspected before closure, and incoming materials were checked for B1 flame retardancy and E1 environmental performance.


4. Key Construction Priorities and Challenges: Three Essential Questions Within 40 Days

The project team officially mobilized on December 6, 2016. The main challenges were summarized into three essential questions: acoustic consistency across many small rooms, identification and correction of acoustic defects, and efficient testing during trial operation. The team addressed each through standardized process control.


4.1 Challenge One: Acoustic Consistency Across Multiple Small Rooms

Challenge analysis: there were many rooms and each was small—18 on the 2nd floor and 6 on the 7th floor, with the smallest room measuring only 4.65 m². Differences in acoustic construction between rooms could easily occur, making it difficult to ensure that every room met the targets and delivered balanced acoustic performance.


Solution: establish a unified construction standard for acoustic assemblies and provide dedicated technical briefings to the construction crews. Each room underwent process-by-process inspection during construction to ensure consistent acoustic construction and compliant quality. The distribution of the two wall absorption systems, stud spacing, fastening of the acoustic wool and sealing procedures all followed the same standard, keeping all 24 rooms consistent like a production line.


4.2 Challenge Two: Identifying and Correcting Acoustic Defects in Small Spaces

Challenge analysis: small spaces are prone to acoustic defects such as standing waves and echoes. Construction deviations—including uneven finished surfaces, insufficiently sealed gaps and misaligned assemblies—can all cause acoustic problems, and defects are often more pronounced in small rooms. Each room therefore required individual inspection and correction.


Solution: before construction, acoustic software was used to simulate each room and avoid common acoustic defects in advance; the reverberation calculations and EASE simulations in the design stage served this purpose. During construction, subjective acoustic evaluations were carried out in stages so problem areas could be identified and adjusted promptly. Acoustic corner treatments, the double-layer ceiling and floating floor were each checked before closure, eliminating defects before they became concealed.


4.3 Challenge Three: Efficient Acoustic Testing During Trial Operation

Challenge analysis: acoustic testing had to be completed for every room during trial operation, with problem rooms corrected promptly. Managing the testing and rectification cycle across 24 rooms was difficult because repeated corrections in even one room could affect overall delivery within the 40-day schedule.


Solution: conduct acoustic-performance testing room by room during trial operation and correct issues immediately to achieve efficient testing and rectification. At the same time, quantitative acceptance criteria were moved forward into the contract and technical briefing, with test items, methods and acceptance values agreed in advance to avoid disputes at handover.


4.4 Material and Workmanship Details: The Acoustic Outcome Is Hidden in the Details

The tender documents specified numerous workmanship details. Each package of polyester-fiber acoustic wool had to be stitched to the fabric at the four corners and center to prevent the wool from gathering and reducing absorption. Light-gauge steel framing had to be at least 0.63 mm thick (0.8 mm for wall studs), and the frame had to be rigid and secure to prevent harmful resonance. Finished acoustic surfaces had to be flat and smooth; the allowable deviation from floor to ceiling was no more than 4 mm, while ceiling and floor flatness had to be below 2 mm. Sound-insulating door gaps had to be tightly sealed, and the threshold had to fit closely against the floor. Multi-disciplinary coordination was also routine within the 40-day schedule: detailed design came first, concealed works were inspected before closure, fire-protection filing and acceptance proceeded alongside integration with building systems, and five specialist workstreams were coordinated across two floors without waiting for one another.


5. Completion: 24 Recording Studios Delivered in 40 Days (January 15, 2017)

The project was completed on January 15, 2017. From mobilization on December 6, this took only 40 days—two days earlier than the committed 42-day schedule and five days earlier than the tender requirement of 45 days. All 24 simple recording studios were completed according to the drawings. The 18 studios on the 2nd floor and 6 on the 7th floor incorporated alternating mid-to-high and mid-to-low frequency wall absorption systems, 240/180 mm multi-damping sound-insulating walls, Grade III sound-insulating doors (≥40 dB), 12 + 10 mm inclined double-pane observation windows, floating floors and double-layer gypsum-board acoustic ceilings, forming a complete sound-insulation chain. HVAC noise control, fire-protection modifications, technical power distribution and “RECORDING IN PROGRESS” indicators were completed at the same time, and recording equipment was installed and commissioned according to the two technical routes. For accuracy, the project handover files did not retain on-site photographs taken after final acceptance. The images below therefore show the intended completed design using design-stage renderings, and every caption is explicitly marked “Design Stage Rendering”; they are not presented as actual post-completion photographs.


6

Simple Recording Studio Design Rendering 1: Polyester-Fiber Acoustic Panel Finish, Recording Workstation and Sound-Insulating Observation Window (Design Stage Rendering)


7

Simple Recording Studio Design Rendering 2: Sound-Insulating Door, Sound-Insulating Observation Window and Two-Position Recording Workstation (Design Stage Rendering)


8

Simple Recording Studio Design Rendering: Blue-Gray Polyester-Fiber Acoustic Panel Walls and Acoustic Ceiling (Design Stage Rendering)


9

7th-Floor Recording Studio Design Rendering: Sound-Insulating Observation Window, Sound-Insulating Door and Acoustic Floor Details (Design Stage Rendering)


6. Acceptance: Third-Party Testing and Performance-Based Verification

The acceptance rules were quantified as early as the tender stage. After completion of the fit-out, the awarded contractor was required to invite a qualified third-party testing organization to issue a standard test report for the acoustic performance indicators, with testing costs included in the quotation. Four core indicators were covered: reverberation time (targeting 0.25±0.1 s and the required frequency response), noise rating curve (NR-25), speech transmission index RASTI (>0.65), and sound insulation of doors and windows (door >35 dB, window >50 dB). All were accepted against the specified criteria, with unconditional rectification required if standards were not met. Reverberation-time measurement followed GY 5022-2007, “Measurement Specifications for Reverberation Time in Radio and Television Broadcasting (Production) Studios.” The process turned “sounds acceptable” into “meets the measured target”—a key distinction between professional broadcast recording-studio construction and ordinary decoration.


Within the acceptance chain, concealed works—including sound-insulation assemblies, cable routing and the floating-floor base—were submitted for inspection and documented before concealment. Sub-items followed a handover inspection system in which the previous process had to pass before the next process could begin. Electrical work was inspected under GB 50303-2015 for conductor termination and grounding, while finish quality was checked item by item under GB 50210-2018. Equipment after-sales service was also written into the contract: at least three years of warranty, a service point within the province, a four-hour response and arrival within 24 hours. Broadcast-grade equipment specifications were therefore paired with broadcast-grade service response. It should be noted that the original third-party test report was not retained in the project handover files; actual measured values should be verified against the final acceptance documentation and are not fabricated here.


7. FAQ: Frequently Asked Questions About Acoustic Fit-Out for Simple Recording Studios

Q: What is the difference between a simple recording studio and an ordinary office fit-out?

A: The difference is “architectural acoustics.” Ordinary decoration focuses on appearance and durability, while recording-studio fit-out focuses on sound. Reverberation time must be controlled at 0.25±0.1 s with a flat frequency response; background noise must meet NR-25; RASTI must be >0.65; and the sound-insulating doors, windows and walls must form a complete sound-insulation chain. In this project, these acoustic targets were all substantive requirements marked with ★ and also required a report from a qualified third-party testing organization. This is a professional threshold that ordinary fit-out contractors may struggle to meet.


Q: What does a 0.25-second reverberation time mean? Why is it so short for speech recording?

A: 0.25 seconds represents a strongly absorptive, “dry” acoustic environment. Speech recording prioritizes clarity and intelligibility. The longer the reverberation tail, the more words blur together, increasing the burden on post-production noise reduction and equalization. A standard approach for broadcast voice-over is to record a dry signal and add reverberation later. Therefore, simple studios for news voice-over and documentary narration commonly keep T60 around 0.25 seconds while balancing absorption by frequency so low frequencies do not become boomy and high frequencies do not become harsh. The result is a clean, controlled voice.


Q: How are the >35 dB sound-insulating door and >50 dB sound-insulating observation window achieved?

A: The sound-insulating door relies on “mass + airtightness + vibration isolation”: a 100 × 60 mm flame-retardant timber frame, 32 kg/m³ acoustic wool inside the door, full industrial-felt sealing along the door gaps, and a stainless-steel threshold. Only when the door leaf is airtight can the sound insulation exceed 35 dB; this project's implementation plan achieved ≥40 dB, exceeding the tender requirement. The observation window relies on “unequal thickness + inclination + sealing”: 12 mm and 10 mm tempered-glass panes shift their resonance frequencies, are installed at an 85° angle, have a dried cavity between them, and are sealed to the frame with industrial felt and clear glass sealant, achieving >50 dB sound insulation.


Q: What is the purpose of a floating floor? Can't we simply install carpet?

A: A floating floor is a key construction for breaking solid-borne sound transmission. Footsteps and furniture impacts can travel a long distance through the floor slab. Ordinary carpet mainly absorbs high-frequency airborne sound and cannot stop structure-borne transmission. In this project, the floating floor used zigzag plywood supports, 18 mm formwork, 5 mm moisture-resistant vibration-isolation rubber pads and flame-retardant acoustic carpet, separating the layers so impact energy was significantly attenuated by the isolation layer. This protected the studio's quiet environment and reduced disturbance to the floor below. In a dense office-building layout where offices may be directly adjacent, this construction should not be omitted.


Q: Will the air conditioner introduce fan noise into the recording? How is it avoided?

A: It will if the HVAC system is not acoustically treated. This project used three measures: sufficiently long silencers on the supply and return ducts; strict airflow-velocity control inside ducts and silencers to prevent regenerated airflow noise, which can be more troublesome than the fan itself; and ceiling return grilles with airflow control and vibration isolation to prevent grille vibration from radiating noise. Combined with the NR-25 background-noise requirement, the result was that the air conditioner could operate normally during recording without audible airflow noise being captured by the microphone.


Q: Why were two recording-equipment routes used—voice-over workstations and USB external audio interfaces?

A: Because the existing conditions differed among the 24 studios. Twelve already had voice-over workstations with professional audio interfaces and voice-over software, so they only needed voice-over microphones, vocal channel processors and monitor-volume processors. The other 12 had only non-linear editing workstations. After evaluating and testing multiple options, the project team selected non-linear editing workstations with USB external audio interfaces: 24-bit/192 kHz, S/N ≥110 dB, 2-in/4-out, latency ≤2 ms, and supercardioid large-diaphragm condenser microphones. Adapting the system to each room rather than using a one-size-fits-all approach saved cost without lowering the performance targets.


Q: How can quality and schedule both be controlled when the project must be completed in 40 days and include third-party testing?

A: By completing detailed design first and using quantified acceptance as the safety net. Before construction, professional construction drawings and renderings were prepared and confirmed by the purchaser, with interfaces and work sequencing resolved at the drawing stage. Incoming materials were checked for B1 flame retardancy and E1 environmental performance. During construction, each room underwent process inspection and concealed works were inspected before closure. After completion, a qualified third-party testing organization measured reverberation time, noise rating curve, RASTI and door/window sound insulation against the agreed criteria, with unconditional rectification for failures. The contract also locked in the schedule, warranty of at least three years, and response times of four hours/24 hours, keeping project risks with the contractor rather than the end user.


8. Avoidance Guide: Six Common Pitfalls in Simple Recording-Studio Construction

Pitfall 1: Doing absorption without sound insulation—the room sounds good, but conversations next door are recorded.

A: Sound absorption and sound insulation are two different things. Meeting the reverberation target does not mean there will be no sound leakage. Sound-insulating walls, doors (>35 dB), observation windows (>50 dB) and floating floors must be designed together so that walls, doors, windows and floor slab form a complete sound-insulation chain, with compatible performance at every link. Do not let one weak door undermine an otherwise strong wall.


Pitfall 2: Covering every wall with the same acoustic material, causing high frequencies to collapse and low frequencies to boom.

A: A single absorption construction has a limited effective frequency range. Follow the approach used in this project: use bagged superfine glass wool on half the wall area for mid-to-high frequencies, and plywood + a 100 mm cavity + polyester-fiber acoustic panels on the other half for mid-to-low frequencies. With the ceiling and floor working together, the reverberation-time frequency response can remain flat, producing speech that is both clean and natural.


Pitfall 3: Connecting the HVAC directly to a simple outlet—once the air starts, the recording is full of whooshing noise.

A: HVAC in a recording studio must include acoustic noise control: sufficiently long silencers on supply and return ducts, strict airflow-velocity control to prevent regenerated airflow noise, and vibration isolation at return grilles. This project made an HVAC outlet with acoustic treatment in every studio a ★ requirement for exactly this reason—HVAC noise is one of the most common sources of rework in simple recording studios.


Pitfall 4: Looking only at sound-absorption coefficients while ignoring fire safety and environmental performance.

A: Fire-safety requirements in broadcasting buildings are stringent. Fit-out materials must achieve B1-grade or higher flame retardancy and meet environmental requirements (GB 18580-2001 E1 level). Concealed wood structures must be coated with fire-retardant paint on both sides; fabrics must be permanently flame-retardant and acoustically transparent; and glass wool must be film-wrapped to prevent dust. Fire-protection filing and inspection, smoke control and exhaust, sprinklers and smoke-detector integration must all be included in the contractual scope, otherwise acceptance may fail.


Pitfall 5: Cutting corners on concealed works—loose framing and unsecured acoustic wool eventually cause resonance and abnormal noise.

A: Put workmanship details into the construction requirements and perform concealed-work inspections. Light-gauge steel framing should be at least 0.63 mm thick and securely fixed; each package of acoustic wool should be stitched to the fabric at the four corners and center to prevent accumulation; finished-surface flatness should be controlled within 4 mm/2 mm limits; and fire-, moisture- and termite-resistance for wood structures and anti-corrosion treatment for steel structures should not be omitted.


Pitfall 6: Buying an ordinary desktop conference microphone—no matter how good the room is, the voice will sound hollow.

A: Voice-over work should use a supercardioid large-diaphragm condenser microphone (1-inch diaphragm, maximum SPL ≥125 dB, S/N >76 dB), together with a desktop universal shock mount and windscreen to isolate page-turning noise and desk vibration at the source. The signal chain should also include a broadcast-grade external audio interface or vocal channel processor; compression/limiting, de-essing and parametric EQ can then shape the voice into a clean, full sound.


9. Applicable Standards

The main standards related to design, fire performance of materials, construction and acceptance for this project are listed below. They also serve as general references for similar recording-studio projects in the broadcasting industry.


Category

Standard No.

Standard Title

Recording-studio acoustic design

GY/T 5086-2012

Acoustic Design Specifications for Radio and Television Recording (Broadcasting) Studios and Production Studios

Reverberation-time measurement

GY 5022-2007

Measurement Specifications for Reverberation Time in Radio and Television Broadcasting (Production) Studios

Technical-room environment

GY/T 5043-2013

Indoor Environmental Requirements for Technical Rooms in Radio and Television Centers

Acoustic construction acceptance

GY/T 5087-2012

Specifications for Construction and Acceptance of Acoustic Fit-Out Works in Radio and Television Centers

Fire protection for broadcasting buildings

GY 5067-2003

Code for Fire Protection Design of Radio and Television Buildings

Hall acoustics

GB/T 50356-2005

Acoustic Design Code for Theaters, Cinemas and Multipurpose Halls

Building sound insulation

GB 50118-2010

Code for Sound Insulation Design of Civil Buildings

Fire protection design

GB 50016-2014 (2018 Edition)

Code for Fire Protection Design of Buildings

Environmental requirements for fit-out materials

GB 18580-2001

Limit of Formaldehyde Emission of Interior Decoration and Refurbishment Materials — Artificial Boards and Their Products

Fit-out acceptance

GB 50210-2018

Standard for Acceptance of Quality of Building Decoration and Fit-Out Works

Electrical installation

GB 50303-2015

Code for Acceptance of Construction Quality of Building Electrical Engineering

Grounding systems

GB 50169-2016

Code for Construction and Acceptance of Grounding Devices in Electrical Installation Engineering


10. Service Areas

Guangzhou Saijia Acoustics & Lighting Engineering Co., Ltd. undertakes acoustic fit-out and audio, lighting and electrical system integration for recording studios, voice-over rooms, recording booths, livestream rooms, podcast rooms, production studios, integrated media centers, theaters and multipurpose halls in China and overseas. The company primarily serves South, East, Central and Southwest China, with particular expertise in projects in the Greater Bay Area and Pearl River Delta. Services cover the full delivery chain from acoustic design, sound insulation and vibration isolation, and sound-quality design through acoustic fit-out construction and acceptance, with localized rapid response.


Guangzhou Saijia Acoustics & Lighting Engineering Co., Ltd. | Tel: 020-86299208 | Address: Room 615, Building 3, No. 135 Huangyuan Road, Baiyun District, Guangzhou, China

Content Menu
CONTACT
Add: Room 615, Building 3, No. 135 Huangyuan Road, Baiyun District, Guangzhou City, Guangdong Province
E-mail: saijia.avl@gmail.com
Mobile: +86-13802436547,  +86-18600228211
INFORMATION
Sign up to receive our weekly newsletter
Contact us
Copyright © 2026 Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. (SJAVL)