Dolby Atmos Lab Conversion: Xinghai Conservatory

Views: 209     Author: Saijia Acoustic     Publish Time: 2026-11-18      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
Reddit sharing button
Threads sharing button
sharethis sharing button

From a 110㎡ Classroom to a Dolby Atmos Laboratory — Xinghai Conservatory of Music: The Story Behind the Acoustic Renovation of the Music Technology Laboratory


On the campus of Xinghai Conservatory of Music in Guangzhou University Town, Xuehai Building G02 was once an ordinary teaching space. In July 2025, after the project award notice was issued, this approximately 110㎡ classroom began an extensive renovation centered on sound. It was planned as four functional zones: the Metaverse Sound Laboratory, Recording Studio (Music AI & Brain Science Laboratory), Digital Music Intelligent Education Laboratory (Conference Room), and Metaverse Mixing Studio (Control Room), with the goal of creating an immersive acoustic environment meeting high standards benchmarked against Dolby Atmos certification. Based on project records, design renderings, construction images, and the completion acceptance report, this article reconstructs the full story of the music laboratory renovation and provides a real-world reference for readers interested in recording studio acoustic fit-out, acoustic engineering design, and construction.


I. Project Overview

Let us start with the project records: this was a RMB 948,000 renovation project with a tight schedule, multiple disciplines, and demanding acoustic standards. From award and commencement to completion and acceptance, the entire process is documented.


Project Item

Details

Project Name

Guangdong-Hong Kong-Macao Music Technology Center Laboratory Site Renovation Project

Purchaser (Owner)

Xinghai Conservatory of Music (No. 398 Waihuan West Road, Xiaoguwei Street, Panyu District, Guangzhou)

Project Location

Xuehai Building G02, University Town Campus, Xinghai Conservatory of Music

Contract Duration

Completion within 48 calendar days after contract effectiveness; acceptance within 8 calendar days

Contractor

Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. (fit-out and equipment installation)

Scope of Works

Laboratory acoustic fit-out, steel structures, electrical and lighting, HVAC and fresh air, fire protection, intelligent systems, and supporting works

Core Acoustic Strategy

Tailored strategy for each room + room-within-a-room construction + custom 46 dB sound-insulating doors + low-frequency traps and floating floor


II. Before the Renovation: The “Sound Mission” of an Ordinary Classroom

2.1 Award Notice: Competitive Consultation and a RMB 948,000 Contract

On July 2, 2025, Gongcheng Management Consulting Co., Ltd., commissioned by Xinghai Conservatory of Music, organized procurement for the Guangdong-Hong Kong-Macao Music Technology Center Laboratory Site Renovation Project (Project No. ZB-15-04F-2025-D-F-E13968) through competitive consultation. Following evaluation and confirmation by the purchaser, Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. was selected as the successful bidder, with a total contract price of RMB 948,000, including tax. The contract required completion within 48 calendar days after effectiveness and acceptance within 8 calendar days. The project manager was Yu Xiaoshan, a Level-2 Registered Constructor.


2.2 Xuehai Building G02 Before Renovation: The “Sound Shortcomings” of an Ordinary Space

Before renovation, this was simply an ordinary campus space: its layout was designed for teaching, with no professional sound-insulating enclosure, sound absorption, diffusion, or low-frequency treatment, let alone the low background-noise environment required for multichannel monitoring. A Dolby Atmos laboratory has much stricter requirements for background noise, reverberation time, and left-right symmetry than an ordinary classroom. The gap between a “usable room” and a laboratory that can pass acoustic acceptance is not merely decoration—it is a complete acoustic system. The approximately 110㎡ floor area was ultimately divided into four functional zones, launching a “small space, multiple disciplines” renovation.


III. Design: Putting Acoustic Targets into the Renderings

3.1 Overall Layout: Four Functional Zones in Approximately 110㎡, with a Tailored Strategy for Each Room

The approximately 110㎡ floor area is a typical “small space, multiple disciplines” project. The design divides it into four zones with different functions and complementary acoustic requirements: the Metaverse Sound Laboratory is designed for immersive-sound creation and experience, using movable tables and chairs and a multichannel monitoring layout for flexibility; the Recording Studio (Music AI & Brain Science Laboratory) is designed for high-fidelity recording and neuroscience experiments, requiring low background noise and accurate room response; the Digital Music Intelligent Education Laboratory (Conference Room) supports teaching, seminars, and listening, with speech intelligibility as the priority; and the Metaverse Mixing Studio (Control Room) is the core space for immersive-sound mixing and calibration, pursuing short reverberation and high clarity. Because the acoustic requirements differ, each room receives a tailored strategy, with individual targets established and verified.


Space

Core Acoustic Target

Design Focus

Metaverse Sound Laboratory

Background noise ≤ NR-20

Immersive-sound creation and experience; low noise prioritized

Recording Studio (Music AI & Brain Science Laboratory)

Background noise ≤ NR-25

High-fidelity recording; accurate room response

Digital Music Intelligent Education Laboratory (Conference Room)

Background noise ≤ NR-40

Teaching and seminars; speech intelligibility prioritized

Metaverse Mixing Studio (Control Room)

Design target RT60 approx. 0.26 s; NR-20

Short reverberation; high-clarity mixing environment


3.2 Three Main Acoustic Design Lines: Sound Isolation, Sound Absorption, and Low-Frequency Control

Sound isolation — three golden rules: decoupling, sealing, and matching. Resilient materials are installed between light-gauge steel studs and boards to break sound bridges; all holes, gaps, and wall penetrations are sealed; and the sound-insulation performance of doors and windows is matched to the walls to prevent one weak link from compromising the entire assembly. The project uses three custom 46 dB sound-insulating doors and three concealed wooden doors, with a room-within-a-room construction for immersive-sound spaces.


Sound absorption — controlling reverberation with data. Approximately 300㎡ of light-gauge steel stud cement-board partitions and 137㎡ of lightweight brick partitions were constructed, together with approximately 28㎡ of mid/high-frequency wall absorption, 170㎡ of low-frequency absorption, 97㎡ of 18 mm-thick perforated wood acoustic panels, 59㎡ of integrated shaped acoustic ceiling in the recording studio, and 227㎡ of flame-retardant acoustic wall felt. These were combined with approximately 23㎡ of low-frequency trap structures and angled ceiling low-frequency traps. Every material quantity corresponds to the design targets for reverberation time and background noise.

Low-frequency control — the biggest challenge in a small room. Curved low-frequency traps filled with glass wool at densities of 24/48/96 kg/m³ are installed at corners and along walls. The mixing studio uses a raised floating floor consisting of rubber isolation blocks, flame-retardant timber joists, staggered cement fire-resistant boards, and an acoustic isolation felt layer. This reduces both airborne and structure-borne sound, suppresses room coloration, and improves low-frequency clarity.


3.3 Renderings: From a Gray Shell to a “Concert Hall for Sound”

The design team first “staged” the future laboratory through renderings: the reception area combines a fair-faced concrete aesthetic with lighting features; the recording studio uses perforated wood panels and blue upholstered acoustic treatment to create a warm recording environment; and the control room uses a dark palette and symmetrical acoustic construction to provide accurate imaging for multichannel monitoring.


1

Reception Area Design Rendering: Fair-Faced Concrete Texture and Lighting Features


2

Recording Studio Design Rendering: Perforated Wood Panels and Blue Upholstered Acoustic Treatment


3

Metaverse Mixing Studio (Control Room) Design Rendering: Symmetrical Acoustic Construction and Low-Frequency Traps


IV. Before Construction: Detailed Design, Technical Briefings, and Material Sample Approval First

4.1 Advance Detailed Design to Work Backward from the Contract Schedule

With a tight schedule and multiple disciplines, success is often determined before construction starts. The project advanced detailed design work, including plans, nodes, system diagrams, and acoustic simulation, to establish the zoning and three-dimensional overlapping workflow. Progress was broken down by week and day, with daily coordination meetings used to resolve obstacles. Equipment was procured separately, so the team coordinated with suppliers in advance to confirm system and point-layout drawings and clarify wiring standards and interface requirements, avoiding discrepancies between wiring, equipment supply, and installation.


4.2 Four Technical Briefings, Four Quality Gates

For an acoustic engineering project, the construction precision of architectural finishes and MEP systems directly determines the final acoustic performance. Before construction, the project team prepared and implemented technical and quality briefing records for key processes—including composite wood flooring, wooden door installation, lighting/switch/socket installation, and distribution box installation—in accordance with the Code for Acceptance of Construction Quality of Building Electrical Engineering (GB 50303) and other applicable national and industry standards. The principle was “brief first, build second.” The execution standards and key control points for the four briefings are listed below.


Technical Briefing Document

Applicable Standard / Specification

Key Quality Control Points

Composite Wood Flooring Installation Technical & Quality Briefing

Construction Process Standard for Building Floor Engineering

Process: moisture barrier → setting-out → timber battens → flooring → trial installation → adhesive → final installation → post-installation treatment; verify substrate flatness, control relative humidity, complete floor service installation/testing, and ensure no standing water on site

Wooden Door Installation Technical Briefing

Quality Acceptance Standard for Building Decoration and Fit-Out

Apply anti-corrosion coating to the wall/floor-facing side of the frame and one clear-oil coat to surfaces and door leaves; install frames before plastering and door leaves after plastering; securely nail timber blocks, flatten nail heads into the blocks, and ensure the frame is firmly installed

Lighting, Switch & Socket Installation Technical Briefing

Code for Acceptance of Construction Quality of Building Electrical Engineering (GB 50303)

Model/specifications must comply with the design; tin conductor ends; no exposed wiring; dedicated marked screws for PE or neutral connections; provide fire protection and thermal insulation near combustible materials and wood structures, use cool-light sources, and secure each luminaire with at least two screws or bolts

Distribution Box Installation Technical Briefing

Code for Acceptance of Construction Quality of Building Electrical Engineering (GB 50303)

Setting-out → surface-mounted distribution box → fixing → electrical device installation → panel wiring → box/panel fixing → insulation resistance test; reliably ground metal enclosures without using the box for series connection; distribute neutral conductors through terminal blocks; repeat-ground PE conductors; meet panel verticality and insulation-test requirements


4.3 Approve and Seal Material Samples First

Acoustic engineering must ensure that “what is designed is what is built,” and material sample approval is essential. Before major acoustic materials entered the site, samples were reviewed and sealed for approval. Key materials such as acoustic panels, sound-insulation boards, and glass wool were checked against the approved samples one by one, ensuring from the source that construction assemblies matched the design details. This was the second source-level safeguard, alongside “brief first, build second.”


4

July 11, 2025: Site Preparation — Material Sample and Construction Method Confirmation (Photo taken with the project’s timestamp camera)


5

July 15, 2025: Materials Arrive Progressively and Renovation Work Officially Begins (Photo taken with the project’s timestamp camera)


V. Construction Focus: A Multi-Disciplinary Symphony within 110㎡

The project’s major challenges can be summarized in four areas: high acoustic and noise-control standards (professional acoustic requirements and Dolby certification, with HVAC and fresh-air noise posing potential interference); difficult control of basic construction quality (wet masonry work, mesh reinforcement and roughening, and steel-structure elevation control); coordination risks between equipment wiring and supply (separate equipment procurement can create discrepancies between wiring and delivery); and fire-safety acceptance compliance risks (limited detailed fire-protection drawings and a relatively brief bill of quantities). The corresponding measures were implemented throughout the key construction processes below.


5.1 Basic Works: Protective Demolition and Standardized Masonry

Xuehai Building G02 is an existing campus building. The renovation involved relocating existing air ducts, electrical modifications, and cable installation. All work had to preserve the original structural safety and connect with the building’s power distribution, fire protection, and HVAC systems. The project used protective demolition and zoned construction to avoid affecting normal use of other areas. Brickwork strictly followed the bidding specifications, while mesh reinforcement and surface roughening were controlled throughout, with curing periods and measures implemented according to the standards. The quality of the early wet works determined the “foundation” for the subsequent acoustic construction.


6

July 20, 2025: Protective Demolition and Site Cleaning (Photo taken with the project’s timestamp camera)


7

July 17, 2025: Lightweight Brick Masonry with Full-Process Control of Mesh Reinforcement and Surface Roughening (Photo taken with the project’s timestamp camera)


5.2 Steel-Structure Mezzanine and Spiral Staircase: Creating New Space on the Existing Floor Slab

Due to the existing building height and functional zoning requirements, the project added an approximately 38㎡ steel-structure mezzanine (I-beams + corrugated steel deck + concrete leveling) and one steel spiral staircase (steel channels + checkered steel plate), together with five new 150×150×5×5 mm columns. Before construction, the site height was precisely rechecked and the second-floor elevation confirmed. During construction, welding quality, fire prevention, and lifting safety were closely controlled, with acceptance carried out in accordance with the relevant requirements of the Standard for Acceptance of Construction Quality of Steel Structures.


8

July 23, 2025: Lifting and Welding of the Steel Spiral Staircase (Photo taken with the project’s timestamp camera)


5.3 Acoustic Construction: Studs, Glass Wool, and Sound-Insulating Doors—No Step Can Be Skipped

Acoustic fit-out is the core of this project. Light-gauge steel stud partitions were fully filled with glass wool, and boards were installed with staggered joints. During installation of the custom 46 dB sound-insulating doors, the door-frame verticality was corrected and resilient seals were compressed to ensure that door and wall sound-insulation performance matched. The ceiling acoustic layers and floating floor were advanced in parallel. Construction strictly followed the acoustic details in the detailed drawings, while acoustic testing and comparative certification were carried out in stages, making compliance part of the process rather than a final remedial test.


9

August 3, 2025: Glass Wool Fully Filled inside the Light-Gauge Steel Stud Partitions (Photo taken with the project’s timestamp camera)


10

August 17, 2025: Installation of Sound-Insulation Boards and Sound-Insulating Door Frames (Photo taken with the project’s timestamp camera)


11

September 4, 2025: Ceiling Acoustic Layer Construction (Photo taken with the project’s timestamp camera)


5.4 MEP Noise Reduction: The “Quiet Revolution” of HVAC, Fresh Air, and Fire Protection

In enclosed acoustic rooms, the biggest noise sources are often HVAC and fresh-air systems. The project selected a Daikin DC inverter VRV system (20 kW outdoor unit, with indoor-unit operating noise as low as approximately 23 dB) together with Green Island Wind fresh-air equipment. Acoustic wrapping was applied to fresh-air, HVAC, and fire-protection piping, while penetrations through floors and walls received sealed sound-isolation treatment. For fire protection, all nine sprinkler heads in the space were modified and connected to the building’s smoke-detection and temperature-sensing alarm systems.


Power, low-voltage, and intelligent systems were coordinated to provide the “skeleton” for the immersive-audio system: distribution-box connection adjustments, power wiring, galvanized cable trays for strong and weak currents, HDMI cables, 8-core armored multimode OM4 fiber (80–100 m), and approximately 310 m of CAT6A network cable provide low-latency, low-loss transmission paths for multiple audio and video signals.


5.5 Four Major Challenges, Four Sets of Countermeasures

High acoustic and noise-control standards: use professional sound-insulating doors meeting national standards; develop dedicated noise-reduction measures for HVAC equipment and discipline-specific piping; seal and isolate wall penetrations; and conduct staged acoustic testing with comparative certification.


Difficult basic construction quality control: strictly follow standards for wet works, accurately recheck elevations before steel-structure construction, and implement the required curing periods.


Equipment wiring coordination risk: confirm system and point-layout drawings in advance, track supply progress together with on-site wiring, and ensure accurate equipment points.


Fire-safety acceptance compliance risk: work with the fire-protection specialist in advance to develop detailed drawings, clarify the construction scope and acceptance criteria, and identify key acceptance requirements.


5.6 Finishing and Trim: Details Determine Acoustic Success or Failure

From September onward, the project entered the finishing stage: woodwork features, acoustic-panel finishes, lighting features, and resilient trims were completed one by one. Once acoustic assemblies are covered by decorative finishes, they are difficult to change, so embedded services, access panels, and hole sealing were completed before finishing work. Beauty is the final step, but it is built on every step that comes before it.


12

September 19, 2025: Wall Lighting Features Begin to Take Shape (Photo taken with the project’s timestamp camera)


13

September 28, 2025: Finishing Installation and Trim-Out Stage (Photo taken with the project’s timestamp camera)


VI. Completion: From a Bare Classroom to a “Concert Hall for Sound”

The project was completed on November 20, 2025. Entering the renovated laboratory group, the main monitors and surround channels in the Metaverse Mixing Studio (Control Room) are symmetrically arranged around the mixing position, with acoustic absorption modules and diffusion features carefully distributed. The recording studio uses perforated wood panels and upholstered treatment to create a quiet recording environment. The Metaverse Sound Laboratory has movable tables and chairs and a multichannel system, allowing flexible changes between creative scenarios. The conference room is bright and open, with speech intelligibility prioritized to support focused discussion. The following are on-site photos taken after completion and during use.


14

Metaverse Mixing Studio (Control Room) — Completed: Short-Reverberation, Low-Noise Environment for Immersive-Sound Mixing


15

Control Room — Completed: Main Monitors and Surround Channels Symmetrically Arranged around the Mixing Position for Accurate Imaging


16

Metaverse Sound Laboratory — Completed: Movable Tables and Chairs with a Multichannel System


17

Recording Studio (Music AI & Brain Science Laboratory) — Completed


VII. Acceptance: Three Parties Sign Off, Project Quality Qualified

7.1 Acceptance Conclusion: Compliant with Design and Construction Requirements

On December 8, 2025, Xinghai Conservatory of Music, as the project owner, organized representatives of the design and construction parties to form an acceptance team for the project completion inspection. The acceptance opinion stated: “Completed in accordance with the contract and bill of quantities; after inspection and acceptance, the project quality complies with the design and construction requirements, and acceptance is approved.” Overall project quality rating: Qualified.


7.2 Key Information in the Acceptance Records

Commencement date: July 15, 2025; completion date: November 20, 2025; acceptance date: December 8, 2025; contract price: RMB 948,000; overall quality rating: Qualified. Owner: Xinghai Conservatory of Music; design company: Beijing North Anheli Digital Technology Co., Ltd.; contractor: Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. (fit-out and equipment installation).


Acceptance organization: The owner chaired the acceptance meeting and reviewed the performance and project documentation of the owner, design, and construction parties. The acceptance team then inspected the completed works on site, formed the completion acceptance opinion, and signed it. Compliance: the entire construction process followed the Code for Acceptance of Construction Quality of Building Electrical Engineering (GB 50303), the Standard for Acceptance of Construction Quality of Steel Structures, and the relevant standards for building decoration and flooring works. The four technical quality briefings were also implemented, maintaining the principle of briefing before construction.


VIII. FAQ: Frequently Asked Questions about Acoustic Laboratory Renovation

Q1: What is the difference between a Dolby Atmos laboratory and an ordinary recording studio?

A: Dolby Atmos is an object-based immersive-audio technology. In addition to horizontal channels, it includes overhead channels and low-frequency effects channels, with stricter requirements for background noise, reverberation time, and left-right symmetry than an ordinary recording studio. This project established background-noise targets by functional zone (NR-20/NR-25/NR-40), while the mixing studio has a design target of approximately RT60 0.26 s, reserving the acoustic conditions for a future Dolby Atmos (HE + Music Studio) qualification application.


Q2: How can three laboratories in 110㎡ avoid sound leakage between rooms?

A: The solution follows three golden rules: decoupling, sealing, and matching. The room-within-a-room construction and resilient layers under the light-gauge steel studs break sound bridges; holes, gaps, and wall penetrations are sealed with non-combustible materials and acoustically wrapped; and 46 dB custom sound-insulating doors are used, with their performance matched to the walls so one weak link does not compromise the entire assembly. Acoustic targets are also differentiated according to the functions of adjacent zones, reducing interference from the design stage.


Q3: What does “a tailored strategy for each room” mean, and why are the targets different?

A: It means setting acoustic targets according to each room’s specific use rather than applying one design uniformly. The four zones have different functions: the Metaverse Sound Laboratory focuses on immersive-sound experience and requires background noise ≤ NR-20; the Recording Studio supports high-fidelity recording and brain-science experiments and requires ≤ NR-25; the Conference Room prioritizes speech intelligibility and allows NR-40; and the Mixing Studio (Control Room) requires short reverberation, with a design target of approximately RT60 0.26 s. Differentiated targets ensure performance while avoiding unnecessary expenditure.


Q4: What are low-frequency traps, and why is low-frequency treatment necessary in small rooms?

A: The length, width, and height of a small room can be close to low-frequency wavelengths, easily exciting standing waves. Some frequencies may sound “boomy” while others may disappear, which is a major source of room coloration. Low-frequency traps are absorptive structures installed at room corners and walls. This project uses curved low-frequency traps filled with glass wool of different densities—24/48/96 kg/m³—to cover different frequency ranges. The mixing studio also uses a raised floating floor, reducing both airborne and impact sound and improving low-frequency clarity.


Q5: How was the 48-calendar-day contract schedule achieved?

A: Three measures were critical. First, detailed design was advanced, with plans, nodes, system diagrams, and acoustic simulation completed before construction to resolve problems in advance. Second, zoned layouts and three-dimensional overlapping workflows were used, with progress broken down by week and day and daily coordination meetings used to remove obstacles. Third, because equipment was procured separately, the team coordinated with suppliers in advance to confirm system and point-layout drawings and clarify wiring standards and interfaces, preventing discrepancies between wiring, supply, and installation.


Q6: Which construction standards must an acoustic laboratory renovation follow?

A: This project followed the Code for Acceptance of Construction Quality of Building Electrical Engineering (GB 50303), the Standard for Acceptance of Construction Quality of Steel Structures, and the relevant standards for building decoration and flooring works throughout construction. Before work began, four technical quality briefings were completed for composite wood flooring, wooden doors, lighting/switches/sockets, and distribution boxes. The project followed “brief first, build second” and approved material samples first, translating standards into every construction process.


Q7: What is the acceptance process for an acoustic laboratory renovation?

A: The owner—in this case, Xinghai Conservatory of Music—chairs the acceptance meeting and organizes the design and construction parties into an acceptance team. The team first reviews the performance and project documentation of the owner, designer, and contractor, then inspects the completed works on site, forms and signs the completion acceptance opinion. The acceptance also verifies completion against the contract and bill of quantities and checks architectural and MEP quality according to the four technical briefings, ultimately assigning an overall project quality rating.


IX. Pitfall Guide: Six Common Misconceptions in Acoustic Laboratory Renovation

Misconception 1: Acoustic fit-out means simply “adding acoustic panels.”

A: Sound absorption is only one part of an acoustic system. A professional acoustic space must address sound isolation, absorption, diffusion, and vibration control separately: first use room-within-a-room construction and sound-insulating doors and windows to keep noise out; then use absorptive materials to control reverberation; use diffusers to break up flutter echoes; and finally address low frequencies. Simply adding acoustic panels may shorten reverberation, but it does not solve sound isolation or low-frequency problems.


Misconception 2: Only treat absorption and ignore sound isolation.

A: Absorption determines how the room sounds inside; sound isolation determines whether outside noise enters and whether your sound disturbs the outside. They are different issues. This is especially important for a group of laboratories. In this project, the three rules of decoupling, sealing, and matching, combined with 46 dB custom sound-insulating doors and room-within-a-room construction, allowed the three laboratories on the same floor to operate without sound leakage between them.


Misconception 3: Ignore HVAC and fresh-air noise.

A: In an enclosed acoustic room, HVAC and fresh-air systems are often the biggest noise sources. Low-noise equipment should be selected (this project used a Daikin DC inverter VRV system, with indoor-unit operating noise as low as approximately 23 dB). Pipes should be acoustically wrapped, and penetrations through floors and walls should receive sealed sound-isolation treatment. One unwrapped air duct can undermine the performance of an entire sound-insulating wall.


Misconception 4: The monitoring position and acoustic construction are not left-right symmetrical.

A: The acoustic construction of a mixing studio or control room must be symmetrical around the monitoring position. Otherwise, stereo imaging becomes skewed and a mix may sound different on other monitoring systems. Symmetry should be established at the rendering stage, construction should follow the acoustic details, and the relationship should be checked on site during acceptance.


Misconception 5: Decorate first and add acoustic design later.

A: Acoustic design must be brought forward to the planning stage. Room proportions, functional zoning, construction methods, and target values should all be determined before construction. Arbitrary room proportions can make low-frequency standing waves almost impossible to solve. Once embedded services, access panels, and hole sealing are missed and the decorative finishes are installed, they are difficult to change. Design first and build second is the sequence that minimizes rework.


Misconception 6: Buy a sound-insulating door like an ordinary door.

A: Sound-insulating doors are one of the weakest links in the sound-isolation chain. They should be custom-made according to the required sound-insulation rating (this project used three custom 46 dB sound-insulating doors). During installation, the door-frame verticality must be corrected, resilient seals properly compressed, and the door/window performance matched to the wall. Concealed wooden doors also require sound-isolation treatment. Ordinary off-the-shelf doors, combined with sound leakage through gaps, may provide only single-digit decibel isolation.


X. Service Areas

Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. undertakes acoustic fit-out and lighting engineering projects for recording studios, mixing rooms, broadcasting studios, music technology laboratories, Dolby Atmos laboratories, lecture halls, and other spaces in China and overseas. The company primarily serves South, East, Central, and Southwest China, with particular expertise in projects in the Greater Bay Area and Pearl River Delta. From acoustic design, acoustic simulation, sound isolation and vibration isolation construction to acoustic fit-out, construction, and acceptance, it provides end-to-end delivery and rapid localized response.


Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. | Tel: 020-86299208 | Address: Room 615, Building 3, No. 135 Huangyuan Road, Baiyun District, Guangzhou

Content Menu
CONTACT
Add: Room 615, Building 3, No. 135 Huangyuan Road, Baiyun District, Guangzhou City, Guangdong Province
E-mail: saijia.avl@gmail.com
Mobile: +86-13802436547,  +86-18600228211
INFORMATION
Sign up to receive our weekly newsletter
Contact us
Copyright © 2026 Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. (SJAVL)