A professional recording studio converted from a double-height commercial space was officially completed in August 2025 at a commercial complex in Huangshi Subdistrict, Baiyun District, Guangzhou. Commissioned by Guangzhou Yiji Commercial Operations Management Co., Ltd. and built by Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd., the project created approximately 67 m² of professional acoustic space within an operating commercial building in about 50 days. The facility includes a recording studio, mixing room, sound lock, music production studio and storage room. Drawing on design drawings, acoustic simulation reports, work-specific technical briefing records and construction photos documenting the entire process, this case study traces the project from planning to completion and offers a practical reference for readers interested in recording studio fit-out costs, acoustic design and construction methods.
Project Item | Details |
Project Name | Acoustic Fit-Out Project for Guangzhou Yiji Commercial Operations Management Co., Ltd. Recording Studio |
Project Location | Huangshi Subdistrict, Baiyun District, Guangzhou, Guangdong, China (inside a commercial complex) |
Client | Guangzhou Yiji Commercial Operations Management Co., Ltd. |
Contractor | Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. |
Scope of Work | Acoustic fit-out and supporting electrical works for the recording studio (live room), mixing room (control room), sound lock, music production studio and storage room |
Area by Function | Recording studio: approx. 31 m²; mixing room: approx. 21 m²; sound lock: approx. 4.8 m²; music production studio: approx. 7.6 m²; storage room: approx. 3 m² (approx. 67 m² in total) |
Building Conditions | Commercial space with an approximate double-height of 5.8 m (approx. 5.25 m to the underside of the main beams); a second-floor slab is located above the recording studio area (approx. 2.5 m to slab soffit) |
Project Schedule | Site work began in early July 2025 and was completed in late August 2025, taking approximately 50 days |
Core Acoustic Strategy | Room-in-Room construction + acoustic simulation using ODEON-type software before construction + tailored design for each room + reuse of existing acoustic components |
Before renovation, the site was a double-height commercial space with an approximate floor-to-ceiling height of 5.8 m (about 5.25 m to the underside of the main beams). A second-floor slab was located above the recording studio area, with an underside height of approximately 2.5 m. The site was within an operating commercial complex, where pedestrian traffic and equipment noise from neighboring businesses created a complex acoustic environment. Turning a usable commercial space into a professional recording environment required far more than ordinary decoration: sound insulation, sound absorption, diffusion and vibration isolation were all essential.

Existing site before renovation: a commercial space with an approximately 5.8 m double-height ceiling and a steel staircase (on-site survey, March 2025)
Entertainment businesses operated around the project floor, and noticeable external noise interference was present on site. If not properly controlled, external noise can compromise the indoor acoustic environment and prevent a recording studio from meeting professional requirements. This was one of the project's three major challenges: controlling sound transmission from surrounding noise sources.

Neighboring businesses on the project floor: lighting and audio equipment in an entertainment venue, one of the external noise sources (on-site photo, July 2025)
Rather than relying on a superficial treatment such as simply covering surfaces with acoustic foam, the design rebuilt the acoustic inner shell using a Room-in-Room approach. The floor incorporated a raised vibration-isolation base; independent wall framing was filled with sound-absorbing material and clad with sound-insulation boards; and the ceiling was decoupled from the main structure through a suspended transition layer. Both airborne and impact sound transmission paths were addressed. This is a high-standard solution for building recording studios inside urban buildings.
During the design stage, the team used ODEON-type acoustic simulation software to create separate models for the recording studio and mixing room. The simulations generated grid maps for T30 (reverberation time), G (sound strength distribution), D50 (speech definition), C80 (music clarity), RASTI (Rapid Speech Transmission Index) and low-frequency ratios. These results informed material data and construction selections. Simulating before construction moved the risk of discovering unsuitable reverberation only after completion back to the drawing stage, where it could be addressed earlier.

Acoustic simulation for the recording studio: G (sound strength distribution) grid map at 250 Hz, generated during the design stage
This recording studio complex is not a single room, but a group of spaces with different acoustic objectives. The design therefore specified the construction, materials and performance targets separately for each area:
Space | Area | Main Acoustic Construction | Acoustic Objective |
Recording Studio (Live Room) | Approx. 31 m² | Ceiling transition layer + custom-shaped sound-absorbing ceiling made of Eterpan boards; approx. 61.4 m² of integrated sound-absorbing walls combining upholstered panels and wooden acoustic panels; five reused 600 × 1,200 mm diffusers; raised vibration-isolation base + vinyl flooring; reused Grade III lightweight acoustic door | Clean, dry recordings with reduced reverberation |
Mixing Room (Control Room) | Approx. 21 m² | Custom-shaped Eterpan sound-absorbing ceiling; approx. 40 m² of integrated sound-absorbing walls; one 600 × 1,200 mm diffuser + four 600 × 600 mm diffusers; approx. 3 m² acoustic observation window; Grade III acoustic door + professional acoustic lock | Accurate monitoring: short reverberation time, flat frequency response and symmetrical stereo imaging |
Sound Lock | Approx. 4.8 m² | Vestibule formed by two acoustic doors; custom F1-board sound-absorbing ceiling; approx. 13.86 m² of polyester-fiber sound-absorbing wall panels | A vestibule transition that increases combined sound insulation |
Music Production Studio | Approx. 7.6 m² | Aluminum ceiling panels, inorganic-paint wall finish and vinyl flooring | Standard interior finish suitable for music production and office work |
Storage Room | Approx. 3 m² | Standard interior finish | Auxiliary space |
The success of sound insulation in a compact, multi-room recording studio depends on three principles:
Decoupling — Use resilient construction to break rigid connections between the floor platform, walls and ceiling, preventing structure-borne sound from bypassing the sound-insulation layer.
Sealing — Carefully seal every weak point, including acoustic doors, observation windows and service penetrations through walls.
Matching — Match the sound-insulation ratings of doors and windows to those of the walls, so that a single door does not undermine the performance of the entire wall.
The project used Grade III lightweight acoustic doors in accordance with the applicable national standard. A professional acoustic lock was added to the mixing room to ensure even compression along the door seals, while a sound-lock vestibule layout further increased the combined sound-insulation performance.
When the budget is limited, spending must be prioritized. The project reused five existing 600 × 1,200 mm wall diffusers and some Grade III acoustic doors, paying only for dismantling, reinstallation and transportation. The saved material costs were redirected to essential components that could not be replaced, such as the raised vibration-isolation floor and ceiling transition layer. This approach helped preserve the essential sound-insulation and acoustic-quality requirements within a contract value of approximately RMB 160,000.
The design renderings provided a preview of the planned acoustic spaces. Wooden diffusers and upholstered wall treatments created a warm recording environment, while the mixing room combined a console and monitoring workstation with integrated sound-absorbing walls to create an accurate listening environment.

Recording studio design rendering: recording area and sound-absorption/diffusion layout (design-stage rendering)

Recording studio design rendering: ceiling features and wall diffusers (design-stage rendering)
Before construction, the project team prepared work-specific technical briefing records to document quality requirements and construction procedures:
Vinyl flooring installation briefing: specified the three key requirements for primer treatment, application of bonding agent and self-leveling compound — substrate moisture content, floor hardness and flatness — as well as installation procedures. Materials were to be acclimatized before installation and laid in production-sequence order. Seams had to be tight enough that a sheet of copy paper could not fit through them. Air was to be expelled and the flooring firmly rolled after installation to prevent curled edges, bubbles and blisters.
Door and window installation briefing: acoustic doors and windows were to be installed in pre-formed openings. Gaps between frames and walls were to be filled with resilient materials such as polyurethane foam and properly sealed. The selection and fixing of hardware, reinforcement steel and sealing strips were specified in detail. Powder-actuated fasteners were prohibited on brick masonry.
Lighting, switches and socket installation briefing: work was to comply with the Code for Acceptance of Construction Quality of Building Electrical Engineering (GB 50303). Switches and sockets had to match the design specifications, wiring had to comply with applicable requirements, and the live conductor had to be controlled by the switch. Fire-resistant and thermal-insulation measures were required when installing lights near combustible structures.
At the early construction stage, dedicated coordination meetings were held with the fire-protection and air-conditioning contractors. The teams jointly established site setting-out positions, clarified the work boundaries and sequence for each trade, and appointed a coordinator to prevent conflicts between overlapping operations. This was the first measure taken to address the project's key construction challenges.
The commercial complex remained open throughout construction. Material deliveries were scheduled to avoid peak pedestrian traffic, work areas were enclosed with protective barriers, construction waste was removed daily, and noisy operations were scheduled for times that would cause the least disruption to neighboring businesses.

July 2, 2025: Material delivery and protection of access routes (construction photo taken with a timestamp camera)

July 3, 2025: Inspection and preparation of the floor substrate (construction photo taken with a timestamp camera)
The project's acoustic design, fire safety, electrical work and sound-insulation construction were carried out with reference to applicable national and industry standards, including the following:
Standard / Code | Reference No. | Application in This Project |
Acoustic Design Code for Radio and Television Recording (Broadcast) Studios | GY/T 5086 | Acoustic design basis for reverberation time, background noise, sound insulation and room-acoustic targets in the recording studio and mixing room |
Code for Design of Sound Insulation of Civil Buildings | GB 50118 | Design of Room-in-Room sound-insulation construction and airborne sound insulation of the enclosure |
Code for Fire Prevention in Interior Decoration of Buildings | GB 50222 | Fire-performance requirements and fire-protection construction for acoustic panels, upholstered finishes and polyester-fiber panels |
Code for Acceptance of Construction Quality of Building Electrical Engineering | GB 50303 | Installation and wiring of lighting, switches and sockets, including grounding |
Code for Fire Protection Design of Buildings | GB 50016 | Fire-safety provisions such as emergency lighting and exit signs |
The project had three main challenges: coordinating the positions and work sequences of multiple trades, particularly fire protection and air conditioning; controlling external noise from nearby entertainment businesses; and safely dismantling and reinstalling existing acoustic components, since acoustic doors and diffusers could be damaged during handling or allow sound leakage if not properly resealed. The corresponding solutions were incorporated into the six key construction stages below.
The owner's existing acoustic doors and diffusers had to be reused. These components could be damaged during removal and reinstallation, and inadequate sealing could cause sound leakage. A specialist team carefully dismantled the existing acoustic doors and diffusers. During reinstallation, joints, door frames and other potential leakage points were treated strictly in accordance with the required procedures. Sealing performance was checked item by item after installation to ensure that the acoustic components remained fully functional.

July 7, 2025: Dismantling of existing studio diffusers and the observation-window substrate (careful removal of components for reuse)
The recording studio was located beneath a large-span, double-height space. If the ceiling had been rigidly connected to the existing structure, impact noise from upper floors and surrounding areas could have travelled directly into the room through the framing. The team first installed a ceiling transition layer. The suspension rods were connected to the main structure using vibration-isolation hangers, after which the light-gauge steel framing and sound-absorbing ceiling panels were installed. This resiliently decoupled the ceiling system. Scaffolding was also provided to ensure safe work at height in the double-height area.

Ceiling transition layer installation: vibration-isolation hangers and light-gauge steel framing — a key detail for resiliently decoupling the acoustic ceiling (site photo)
The walls used independent framing filled with sound-absorbing material and clad with sound-insulation boards. The recording studio had approximately 61.4 m² of integrated sound-absorbing wall treatment combining upholstered panels and wooden acoustic panels; the mixing room had approximately 40 m²; and the sound-lock walls were covered with approximately 13.86 m² of polyester-fiber sound-absorbing panels. Absorption and diffusion were balanced according to each room's purpose. The recording area relied on sound absorption to reduce reverberation and produce clean, dry recordings. The mixing room combined strong absorption with multiple QRD-type diffusers to break up flutter echoes and low-frequency standing waves commonly found in small rooms.

On-site installation of wall-mounted sound-absorbing panels
Acoustic doors and observation windows are often the weakest links in a sound-insulation system. During installation, the team followed the door and window technical briefing to control opening dimensions and level the frames. Gaps between frames and walls were filled with resilient materials and sealed. After the observation-window glass was installed, the compression and sealing conditions were checked. The mixing room's acoustic door was fitted with a professional acoustic lock to ensure even pressure along the door seals when closed.

July 13, 2025: Installation of the recording studio's acoustic observation window between the mixing room and recording area (approximately 3 m²)
An approximately 31 m² raised vibration-isolation floor was installed in the recording studio to interrupt impact-sound transmission. The vinyl flooring was installed in accordance with the technical briefing: the substrate's moisture content, hardness and flatness were inspected; bonding agent and self-leveling compound were applied; the flooring was acclimatized for 24 hours and installed in sequence-number order; and the seams and perimeter edges were firmly rolled and pressed.
A main power supply and distribution panel were provided for the project, with wiring, switches, sockets and lighting arranged according to the needs of each room. The recording studio, mixing room and sound lock were each equipped with an “Recording in Progress” indicator, an “Exit” sign and emergency lighting. Every wall penetration for services was acoustically sealed during construction. Electrical work was not allowed to compromise the sound-insulation continuity of the enclosure. Fire-retardant plywood was used for the ceiling substrate, and upholstered finishes and polyester-fiber acoustic panels were selected in accordance with fire-safety requirements for interior finishes.
Construction took place during Guangzhou's hot July–August season, with on-site temperatures repeatedly reaching 34–36°C. Work progressed according to the technical briefings for each trade: wall framing and the ceiling transition layer were completed in early July; sound-insulating walls and ceiling framing were completed in mid-to-late July; the observation window and finish layers were installed from late July to early August; and flooring, skirting, lighting and final cleaning were completed in mid-to-late August.

July 4, 2025: Wall framing in the double-height space (temperature: 34°C; photo taken with a timestamp camera)
From the arrival of materials on July 2 to final cleaning in late August, all project work was completed in approximately 50 days. The following photos show the site during the finishing stage.

August 21, 2025: Recording studio nearing completion — diffusers installed on the walls and ceiling features completed

Completed sound-absorbing and diffusing wall in the recording studio: a combination of upholstered panels, wooden acoustic panels and architectural lighting (site photo, August 21, 2025)

Completed mixing room (control room): diffusers, air conditioning and furniture in place (site photo, August 21, 2025)

Reinstallation of reused QRD diffusers completed: each unit checked for sealing and appearance (site photo, August 21, 2025)

Final work on acoustic doors and sound lock: room-by-room inspection before cleaning and handover (site photo, August 21, 2025)
During construction and before handover, the project team used a sound level meter to measure sound pressure levels by frequency band and verify the indoor background-noise level and the effectiveness of the sound-insulation construction. The acoustic simulation indicators used at the design stage — T30, G, D50, C80 and RASTI — could be measured again after completion and compared against the design results. This is the most direct way to verify performance.

On-site acoustic testing: sound pressure level measurements by frequency band using a sound level meter (background-noise verification during construction)
Sound insulation: airborne sound insulation and indoor background-noise levels, with particular attention to the sealing of acoustic doors and windows, service penetrations through walls and the integrity of the Room-in-Room construction.
Room acoustics: reverberation time T30 and its frequency characteristics; D50 and RASTI as references for speech recording; and C80 as a reference for music recording.
Sound-field uniformity: G (sound strength distribution) and the symmetry of the monitoring environment, compared with the acoustic simulation results from the design stage.
Acceptance also covered the work packages corresponding to the three technical briefings: vinyl flooring quality (flatness, seams, and absence of curled edges or bubbles); acoustic door and window installation (frame-to-wall sealing, hardware and smooth operation); and electrical installation (wiring, grounding and switch control inspected in accordance with GB 50303). For accuracy, this article does not insert specific measured values; the final figures should be taken from the project completion and acceptance records.
The project began on site in early July 2025 and all work was completed in late August, taking approximately 50 days. Neighboring businesses continued normal operations throughout the overlapping construction work, and no complaints were reported.
Q1: Is it really possible to build a professional recording studio inside a commercial complex? What are the challenges?
A: Yes, but the space must be designed as a complete Room-in-Room system. The challenges in a commercial complex include complex noise from neighboring businesses and significant sound transmission through slabs and the building structure. Surface sound absorption alone cannot solve these problems. This project used a raised vibration-isolation floor, independent sound-insulating walls, a ceiling transition layer with vibration-isolation hangers, a sound lock and acoustic doors and windows to acoustically separate the studio from the commercial space, creating a quiet recording environment inside an operating commercial building.
Q2: How much does recording studio acoustic fit-out cost? What can a budget of RMB 160,000 achieve?
A: The cost mainly depends on the floor area, required sound-insulation rating and number of rooms. This project covered approximately 67 m² across a recording studio, mixing room, sound lock, music production studio and storage room, with a contract value of approximately RMB 160,000. By prioritizing investment in the core rooms and using standard finishes in auxiliary rooms, while reusing existing diffusers and acoustic doors, the project maintained professional standards in the two key spaces for recording and mixing.
Q3: What is the difference between the acoustic requirements of a recording studio and a mixing room?
A: The primary goal of the recording studio (live recording area) is to capture clean, dry sound, so it relies mainly on strong sound absorption. The mixing room (control room) must provide accurate monitoring, requiring a short reverberation time, a flat frequency response and a symmetrical left-right listening environment. Diffusers are also used to eliminate flutter echoes and low-frequency standing waves. Although the construction approaches are similar, the acoustic objectives differ, so each room must be designed individually.
Q4: What is a sound lock? Is it necessary in a small recording studio?
A: A sound lock is a small transitional space between two acoustic doors. The outer and inner doors are not opened at the same time, preventing a direct path for sound to pass through. It is a cost-effective sound-insulation measure. The sound lock in this project was only approximately 4.8 m², and its interior walls were fully lined with polyester-fiber sound-absorbing panels to absorb residual sound energy. It is recommended wherever space allows. A sound lock of just a few square metres can improve the combined sound-insulation performance far more effectively than simply making the walls thicker.
Q5: Does reusing existing acoustic doors and diffusers affect acoustic performance?
A: Reuse does not compromise performance if the components are in good condition and meet the required rating; it can also reduce costs. Before construction, the project team inspected the existing Grade III acoustic doors and five 600 × 1,200 mm diffusers individually. After confirming that they were in good condition, the team reused them and paid only for dismantling, reinstallation and transportation. Seals and hardware were also inspected and replaced as necessary during reinstallation. The key principle is: inspect first, then reuse.
Q6: Which indicators should be checked during final acceptance of a recording studio?
A: Three groups of indicators are essential: sound insulation (airborne sound insulation and background noise); room acoustics (T30 and its frequency characteristics, with D50 and RASTI as references for speech and C80 for music); and sound-field uniformity (G sound strength distribution and monitoring symmetry). If acoustic simulation was conducted during design, the same indicators should be measured again after completion and compared with the design results.
Q7: How can construction be carried out in an operating commercial building without disturbing neighboring businesses?
A: Four measures are essential: schedule material deliveries outside peak pedestrian hours and protect access routes; enclose work areas and remove construction waste daily; schedule noisy demolition and cutting operations for times that cause the least disruption; and communicate the construction plan to property management and neighboring businesses in advance. During this project's overlapping construction work, surrounding businesses remained open and no complaints were reported.
Mistake 1: Converting a commercial space into a recording studio by simply adding a layer of acoustic foam.
A: Sound absorption is only one part of an acoustic system. A studio inside a commercial complex must be designed as a complete Room-in-Room structure. The raised vibration-isolation floor, independent sound-insulating walls, resiliently decoupled ceiling and acoustic doors and windows are all essential. Sound insulation, absorption, diffusion and vibration isolation must work together. The sound-insulating enclosure should be completed first, followed by interior absorption and diffusion; these functions should not be confused.
Mistake 2: Sound insulation simply means making the walls thicker and choosing any doors and windows.
A: Doors and windows are often the weakest links in the sound-insulation system. Their sound-insulation ratings must match those of the walls; otherwise, a single door can undermine the entire wall. Gaps between frames and walls must be filled with resilient material and sealed. Where space allows, a sound lock should be provided. A vestibule of just a few square metres can improve combined sound insulation far more than simply increasing wall thickness.
Mistake 3: When the budget is tight, cut the acoustic construction scope in half.
A: This project demonstrates how to prioritize spending. Invest more in the core rooms — the recording studio and mixing room — and use standard finishes in auxiliary spaces such as the music production studio and storage room. Inspect existing components before reusing them, and redirect the material savings to essential construction such as the raised vibration-isolation floor and ceiling transition layer. A budget of approximately RMB 160,000 can still preserve the essential professional requirements.
Mistake 4: Treat sound absorption and diffusion as the same thing and cover every wall with the same material.
A: The recording area needs clean, dry sound and therefore relies mainly on strong absorption. The mixing room needs accurate monitoring and must combine strong absorption with QRD-type diffusers to break up flutter echoes and low-frequency standing waves in a small room. Absorption controls reverberation, while diffusion helps prevent acoustic coloration. An incorrect balance can make a room sound either lifeless or excessively reflective.
Mistake 5: Leave electrical, air-conditioning and other services until the end, and drill holes wherever needed.
A: Electrical, air-conditioning and fire-protection systems must be coordinated with the acoustic construction from the design stage. A dedicated coordination meeting should establish setting-out positions and work boundaries before construction. Every service penetration through a wall must be acoustically sealed. Lighting, switches and sockets must be installed in accordance with GB 50303 without compromising the sound-insulation continuity of the enclosure. One unsealed opening can undermine the performance of an entire sound-insulating wall.
Mistake 6: Wait until completion to find out whether the acoustic performance is acceptable.
A: Acoustic design should be completed at the proposal stage. The design team should provide acoustic simulations or calculation evidence, such as grid maps for T30, G, D50, C80 and RASTI. Simulate first and build second, resolving risks at the drawing stage. After completion, measure the same indicators again and compare the results. Performance should be demonstrated by data, not guesswork.
Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. undertakes acoustic fit-out and supporting engineering projects in China and internationally, including recording studios, mixing rooms, audio recording rooms, livestreaming rooms, podcast studios, broadcast studios, converged media centers and music technology laboratories. The company focuses on South China, East China, Central China and Southwest China, with particular experience in projects across the Greater Bay Area and Pearl River Delta. From acoustic design and simulation to sound insulation, vibration isolation, acoustic construction and acceptance, the company provides end-to-end delivery and responsive local support.