Views: 168 Author: Saijia Acoustic Publish Time: 2026-11-18 Origin: Site
In Baiyun Xincheng, Baiyun District, Guangzhou, the 95-mu educational facilities project for Phases 5–8 of Baiyun Xincheng delivered an 11-meter-clear-height gymnasium for the Baiyun Campus of Peiying Middle School. The venue includes a basketball competition area, badminton courts, a fitness room and table tennis rooms. China Construction Eighth Engineering Division Corp., Ltd. served as the general contractor, while Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. undertook the specialist fit-out subcontract covering three spaces: the auditorium, gymnasium and tiered classroom. The project passed completion acceptance on September 8, 2022. Following the timeline from design and pre-construction preparation through key construction activities, completion and acceptance, this case study reviews the development of the school gymnasium's acoustic fit-out, supported by 16 project images. It is intended as a reference for schools and educational institutions planning gymnasiums, basketball courts and covered sports grounds.
Project Element | Details |
Project name | Baiyun Xincheng Phases 5–8, 95-Mu Educational Facilities Project (Specialist Secondary Fit-Out Works) |
Project location | Baiyun Xincheng, Baiyun District, Guangzhou, China (Peiying Middle School, Baiyun Campus) |
General contractor | China Construction Eighth Engineering Division Corp., Ltd. |
Specialist subcontractor | Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. |
Scope of work | Secondary fit-out of the auditorium, gymnasium and tiered classroom |
Completion acceptance | September 8, 2022; conclusion: “Complies with the design requirements; acceptance passed” (signed and sealed by both the general contractor and specialist subcontractor) |
Two details in the project record are particularly informative. First, the scope covered three types of space—the auditorium, gymnasium and tiered classroom—under one specialist subcontract. This was a coordinated upgrade of the school's shared facilities rather than a series of isolated room renovations. Second, the acceptance conclusion, “Complies with the design requirements; acceptance passed,” was confirmed with the signatures and seals of both the general contractor, China Construction Eighth Engineering Division, and the specialist subcontractor, Saijia. The report was dated September 2022, just after the start of the autumn semester, and the new facilities were then put into campus use.
For a secondary school, a gymnasium is much more than a place to play ball. Physical education classes, basketball games, badminton training, fitness activities and school gatherings all take place there. This facility is comprehensive: the basketball competition area is equipped with a full-size competition-grade mobile basketball system; the main hall also accommodates badminton courts; and the building includes a fitness room, two table tennis rooms and administrative offices. Its most important technical value, however, lies in what cannot be seen. Without acoustic treatment, reverberation in an 11-meter-high space can make whistles and public-address announcements merge into an indistinct wash of sound. The client therefore awarded the gymnasium acoustic fit-out together with the auditorium and tiered-classroom fit-out to a specialist contractor, recognizing that acoustic spaces need to be designed and built correctly by an experienced team from the outset.

Figure 1. Design rendering: basketball competition area, featuring perforated sound-absorbing walls and ceiling, protective steel mesh and maple sports flooring (approved in July 2021).
The space was handed over as an unfinished shell in a newly built school building. The steel roof trusses and purlins were exposed, and the surrounding walls were bare and awaiting fit-out. Large windows provided abundant daylight but also created extensive hard, reflective surfaces. Site photographs from June 2021 show full-height scaffolding already erected inside the hall, with construction and site investigation taking place in parallel to provide first-hand spatial data for detailed design. The space had two natural advantages: generous headroom and an open layout. Its major weakness was the absence of acoustic treatment. The steel roof structure, walls and floor were all reflective surfaces, causing sound waves to bounce around the hall. Reverberation time could reach five or six seconds or more, making a systematic acoustic fit-out essential to rebuild the indoor acoustic environment.

Figure 2. Existing condition: unfinished hall beneath the steel roof structure, with materials being brought onto site (June 2021).

Figure 3. Existing condition: full-height scaffolding completed, establishing the vertical work area beneath the 11-meter clear height.
The core design principle was to treat each zone according to its function. The basketball competition area, with an 11-meter clear height, received a comprehensive high-performance sound-absorbing ceiling and wall system to control reverberation and low-frequency resonance. The main hall, which also accommodates badminton, continued the same acoustic system and added dedicated badminton flooring mats. In the fitness room, dark acoustic wall panels and linear lighting create an energetic sports atmosphere. The two table tennis rooms have a clear height of 4.5 meters and use a mid-range specification comprising aluminum acoustic wall panels and custom F1-board acoustic ceilings. In the design renderings, the perforation ratios of the sound-absorbing aluminum panels are customized to the drawings and varied by zone. Acoustic performance is integrated into the architectural appearance: the modern look seen by athletes and the sound clarity they experience come from the same construction system.

Figure 4. Design rendering: badminton area, featuring perforated aluminum acoustic wall panels and solid-wood sports flooring.

Figure 5. Design rendering: fitness room, featuring dark acoustic wall panels and linear lighting.

Figure 6. Design rendering: table tennis room, featuring aluminum acoustic wall panels and a custom acoustic ceiling.
The bill of quantities for the basketball hall acoustic fit-out at Peiying Middle School's Baiyun Campus, prepared during the design stage, specified construction methods down to the level of process parameters. The steel ceiling transfer framework required Sa 2.5 surface preparation, two coats of red-lead primer and two coats of topcoat, followed by 4.5 mm of sprayed fireproof coating. High-performance ceiling absorption used 32K-density, double-bagged fire-resistant glass-wool insulation (600 × 600 × 25 mm), with an inner film layer and an outer fiberglass-cloth layer to prevent fiber leakage; the specified sound absorption coefficient was α > 0.6. Ceiling and wall finishes used the OSL-A aluminum honeycomb corrugated system, with perforation ratios customized to the drawings. The floor build-up began with a 100 mm-high raised vibration-isolation base incorporating two layers of 3.7 mm damping acoustic underlay, providing a sound insulation rating of more than 30 dB, followed by 18 mm-thick, MFMA-certified Grade 1 maple sports flooring. The value of this schedule is that every cost item is tied to measurable construction parameters, providing a firm basis for subsequent tendering and acceptance.
Area | Main scope and specifications |
Basketball hall (competition area) | 803 m² steel ceiling transfer framework; 803 m² high-performance ceiling absorption; 803 m² aluminum acoustic ceiling; 1,184.7 m² aluminum acoustic wall panels; vibration-isolation base and maple sports flooring; two basketball systems |
Basketball hall (main hall) | 302 m² of the same acoustic construction system; 82 m² of dedicated badminton mats; protective steel mesh and standard electrical works |
Fitness room | 106.5 m² acoustic ceiling; 143.6 m² aluminum acoustic wall panels; sports flooring |
Two table tennis rooms | Acoustic ceilings including F1-board acoustic ceiling panels; 183.3 m² aluminum acoustic wall panels (4.5 m clear height) |
Administrative rooms | Acoustic ceilings, inorganic-paint wall finishes and polished-tile flooring |
The preliminary estimate also disclosed one important figure: the planned ceiling height of the basketball hall was 11 meters. This height contributes to the quality of the space, but it also makes work-at-height safety management one of the project's major challenges—a point repeatedly demonstrated during construction.
No. | Key challenge | Challenge analysis | Countermeasure |
1 | Strict environmental requirements for educational interiors | Interior fit-out materials are subject to stringent environmental requirements and must comply with the standards applicable to school premises. | Select fit-out materials that meet the environmental standards for educational facilities. Conduct indoor air-quality testing after construction and hand over the space only after the results pass. |
2 | Difficult coordination among multiple trades | The project involves several construction disciplines with closely overlapping work sequences. Coordination efficiency directly affects the overall schedule. | Review the work sequences of all trades in advance, prepare an integrated master schedule, and hold regular coordination meetings to ensure smooth interfaces between activities. |
3 | Strict campus construction safety requirements | The work site is located within a school campus, requiring rigorous safety controls to protect everyone on campus. | Enforce restricted-site management and appropriate safety-protection measures to maintain a safe construction environment on campus. |
4 | Complex safety management for work at height | The project includes work at height, making control of related safety risks a major construction-management priority. | Assign a dedicated safety officer to supervise work-at-height activities on site and ensure that all such work is carried out in accordance with safety procedures. |
This list of major challenges formed the management framework for the entire project. The four principal risks were environmental compliance, coordination among trades, campus safety and work at height. They were addressed through compliant material selection and indoor air-quality testing, an integrated master schedule and coordination meetings, restricted-site management, and on-site supervision by a dedicated safety officer. Unlike a typical commercial project in the city, a school project has an additional non-negotiable constraint: teaching and learning must not be disrupted. This requires more detailed and punctual construction planning.
The project retained a systematic set of technical and safety briefing records. The construction-organization briefing assigned responsibility for four areas of preparation: technical work, materials and equipment, workforce organization, and site arrangements. A dedicated safety briefing covered the operation of aerial work platforms. New workers had to follow the general contractor's formal site-entry procedure, including three-level safety induction, employment-contract signing and registration, truthful completion of health information, and signatures and fingerprints at designated locations; entry was prohibited if any step was missing. Electrical works followed a separate in-conduit wiring briefing based on GB 50303, the Code for Acceptance of Construction Quality of Building Electrical Engineering, which defined the conditions and procedures for cable installation. Briefings must reach each work crew and be acknowledged by signature and fingerprint to ensure consistent workmanship and safe practices.

Figure 7. Early-stage site work: CAD design coordination and verification, with functional layouts such as the VIP lounge checked item by item (April 2021).
In accordance with the construction plan, the project team completed pre-construction investigations of weather, terrain and above- and below-ground conditions. The team reviewed the construction drawings and aimed to resolve drawing issues before work began. Site images from late April 2021 show designers and construction personnel checking functional layouts against CAD drawings, confirming areas such as the VIP lounge and corridors one by one. Parameters including acoustic-panel perforation ratios and furring-channel layouts were finalized at the drawing stage. In early July, the owner approved the renderings for spaces including the basketball court; the approval panel was dated July 8, 2021, and the design scheme was formally finalized.
The first major challenge in a hall with an 11-meter clear height was vertical access and work-at-height safety. The project used two complementary methods. Full-height scaffolding was the primary access method for large-scale ceiling and wall works, and the scaffolding throughout the hall had been completed by June 2021. Scissor lifts were also used for panel installation and mechanical/electrical works, reducing the need for workers to climb manually. Site images from late July 2021 show two lifts operating simultaneously beneath the steel roof structure, making the scale of the work clearly visible. Safety measures followed the project's risk-control plan: a dedicated safety officer supervised work at height, all workers completed site-entry safety training and registration, and scissor-lift operators were required to have completed and retained the relevant safety briefing records.

Figure 8. Construction in progress: two scissor lifts operating simultaneously beneath the steel roof structure (July 2021).

Figure 9. Construction in progress: wall substrate preparation on scaffolding, with workers correctly wearing personal protective equipment (May 2021).
The entire suspended-ceiling system relied on the steel ceiling transfer framework. The 803 m² framework was connected to the main structure using No. 5 angle steel and φ12 expansion bolts. The steel treatment process was specified in full: Sa 2.5 surface preparation, one coat of anti-rust paint, two coats of red-lead primer, two coats of topcoat, and 4.5 mm of sprayed fireproof coating. Site images from June 2021 show the transfer-framework steel members, timber battens and mechanical/electrical services such as ducts arranged in separate ceiling layers, with accurate elevations reserved for the acoustic construction. This is a typical concealed-work package: it cannot be seen after the ceiling is closed, but the structural safety and fire performance of the system depend on it. Each stage must therefore be inspected against the specified parameters, with no steps omitted.

Figure 10. Construction in progress: steel members of the ceiling transfer framework and building services arranged in separate layers (June 2021).
The acoustic system is the heart of this gymnasium. Ceiling acoustic wool was enclosed using a double-bagged, anti-leakage installation method to prevent fibers from escaping. Perforated aluminum honeycomb acoustic panels were installed in different wall zones, with perforation ratios customized to the drawings. Images from mid-June 2021 document the installation of the perforated aluminum wall panels, whose white perforation patterns are clearly visible under the lighting. The wall acoustic system was flexibly connected to the main wall, with additional high-performance absorption and low-frequency resonance treatment behind it. Steel connection components received 5 mm of fireproof coating, providing a fire-resistance limit of 1.5 hours. In late August 2021, aerial lifts supported the installation and closure of the aluminum acoustic ceiling panels, gradually completing the acoustic ceiling 11 meters above the floor.

Figure 11. Construction in progress: installation of perforated aluminum acoustic wall panels, with perforation patterns customized to the drawings (June 2021).

Figure 12. Construction in progress: aerial lifts supporting the installation and closure of aluminum acoustic ceiling panels (August 2021).
The floor directly affects the sporting experience and is also essential to sound insulation between floors. The floor system comprised three layers. First, a 100 mm-high raised vibration-isolation base was installed over the concrete slab, using two layers of 3.7 mm damping acoustic underlay. The underlay provided a sound insulation rating of more than 30 dB and had an areal density above 2.45 kg/m². Next came 18 mm-thick specialist solid-wood sports flooring, finished with MFMA-certified Grade 1 maple boards. Dedicated rubber mats were added in the badminton area. Site images from late June to early July 2022 show the large-scale installation of the damping acoustic underlay, with the black underlay spread across the hall and aerial lifts on standby for the final flooring installation. The facility was also fitted with two full-size competition-grade mobile single-post basketball systems with 2.25 m extensions, protective steel mesh and custom stainless-steel skirting, completing the supporting details as part of the same package.

Figure 13. Construction in progress: large-scale installation of the double-layer damping acoustic underlay forming the vibration-isolation base (July 2022).
During the later construction stage, the different areas progressively entered the finishing phase. The auditorium's wave-shaped acoustic ceiling and tiered seating area took shape, the wall acoustic panels were closed in, and standard electrical conduits, switches, sockets and light fixtures were installed in accordance with the schedule. Finishing works across different trades were coordinated under the master schedule: decorative finishes, mechanical/electrical terminals and sports equipment were installed in sequence by zone, with regular coordination meetings to ensure smooth handovers between trades. Images from early September 2021 show that the main ceiling design and stepped floor of the tiered classroom had been completed, and the space was moving into cleaning and detailed finishing.

Figure 14. Later-stage construction: wave-shaped acoustic ceiling and tiered seating area in the tiered classroom (September 2021).
In accordance with the project's risk-control plan, two essential checks were carried out before handover. The first was indoor air-quality testing. Because environmental requirements for educational facilities are stringent, all fit-out materials had to comply with the applicable standards for school premises, and the indoor air-quality results had to pass before handover. The second was inspection of construction details and functions, including the acoustic construction methods, corrosion and fire protection of the steel structure, sports-floor flatness, and electrical insulation and grounding. Only after both checks were passed could the acceptance report state: “Complies with the design requirements; acceptance passed.”
The project passed completion acceptance on September 8, 2022. The acceptance report records the project name (Baiyun Xincheng Phases 5–8, 95-Mu Educational Facilities Project), the general contractor (China Construction Eighth Engineering Division Corp., Ltd.), the specialist subcontractor (Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd.), the contract value of RMB 14.2266 million, the acceptance date, and a summary of the scope: secondary fit-out of the auditorium, gymnasium and tiered classroom. The acceptance conclusion was “Complies with the design requirements; acceptance passed.” The subcontractor's seal and signature were applied in September 2022, and the general contractor's project engineering and technical seal appears on the same page. For the owner, this report is an original record for facility maintenance and the allocation of responsibility. For the contractor, it is the final confirmation of construction quality.
In addition to visual inspection and document review, acceptance of a gymnasium project should focus on five areas: the acoustic construction methods and concealed-work inspection records; corrosion- and fire-protection documentation for the steel transfer framework; the installation quality of the sports flooring and the construction of its vibration-isolation base; insulation-resistance and grounding-resistance test results for electrical wiring; and the indoor air-quality test report. Acoustic performance can also be verified through on-site measurements of reverberation time and other indicators in accordance with the applicable sports-venue acoustic measurement procedures. Acceptance supported by measured data is the only objective way to determine whether the required performance has been achieved.
After completion and handover, the gymnasium entered everyday school use. Physical education classes, basketball games and badminton training rotate between the competition area and the main hall, while the fitness room and table tennis rooms support daily exercise by students and staff. The quality of the specialist construction continues to be tested through regular use. Follow-up images from September 2023 show that the perforated acoustic ceiling and lighting remained in good condition; after selected access panels were opened for inspection, they were returned to their original condition. Transformed from an unfinished hall beneath a steel roof into a fully equipped sports facility with acoustic performance in place, the venue demonstrates that investment in school sports spaces delivers benefits students can use every day.

Figure 16. Follow-up site visit (September 2023): perforated acoustic ceiling and lighting in good condition; access panels restored after inspection.
Q: Why does a school gymnasium need acoustic fit-out?
A: A gymnasium is a large-volume space with extensive hard, reflective surfaces. Without sound absorption, reverberation time can easily reach five or six seconds. Whistles, public-address announcements and ball impacts overlap, creating an unpleasant “booming” sound that makes both game announcements and physical-education instructions difficult to understand. Acoustic fit-out combines high-performance ceiling absorption, wall acoustic panels and low-frequency resonance treatment to bring reverberation time into the applicable range for sports venues, making announcements clearer and whistles sharper. In this project, the combined ceiling and wall acoustic treatment in the basketball hall covered more than 2,000 m², all designed to achieve this objective.
Q: How much does acoustic fit-out for a school gymnasium usually cost?
A: The cost depends on the floor area, clear height and construction specification. The greater the height, the larger the share of costs associated with scaffolding and work at height. Higher standards for acoustic treatment and sports flooring also increase the unit cost. In this project, the preliminary estimate for acoustic fit-out in the basketball-hall area was approximately RMB 4.76 million, covering the basketball competition area, main hall, fitness room and table tennis rooms. The three largest cost items were the steel ceiling transfer framework, acoustic walls and ceilings, and sports flooring. The actual price should be based on a site survey and an itemized quotation prepared after detailed design.
Q: Why is maple sports flooring commonly used in basketball halls?
A: Maple has a dense grain structure and good elasticity and resilience, making it a widely used sports-surface material for international competitions. Buyers should check two things: first, MFMA certification from the Maple Flooring Manufacturers Association, which has clear grading and board-length classifications; and second, the thickness of the flooring boards. A common specification is 18 mm specialist solid-wood flooring. This project used finished Grade 1 MFMA-certified maple boards over a double-layer damping acoustic underlay, balancing sports performance with sound insulation for the space below.
Q: Can acoustic wool fibers come loose, and how is environmental safety ensured?
A: The key lies in the installation method, not just the material itself. In this project, ceiling acoustic wool was installed using a double-bagged anti-leakage method: an inner film layer 0.2–0.3 mm thick and an outer fiberglass-cloth layer. The fibers are fully enclosed within the construction build-up and do not come into direct contact with indoor air. In addition, as an educational facilities project, it was subject to stringent environmental requirements. Materials had to meet the applicable standards for educational premises, and indoor air-quality testing was conducted after completion. Handover was permitted only after the results met the requirements.
Q: How is safety managed when working inside a hall with an 11-meter clear height?
A: The project used two parallel approaches. First, equipment: scissor lifts replaced some work that would otherwise have required full-height scaffolding, reducing the need for workers to climb. Second, management: work at height was listed as a major project risk, a dedicated safety officer supervised the work on site, and workers completed three-level safety induction, signed and registered their employment contracts, and wore the required protective equipment. The project retained the aerial-work-platform safety briefing records and new-worker site-entry safety handbook, documenting the safety-control measures.
Q: How can construction on a school campus minimize disruption to teaching?
A: Three practices are important. First, restrict and segregate the construction area physically from teaching areas, and require personnel and material deliveries to enter with authorization. Second, schedule work in suitable time windows: noisy and dusty operations should avoid class times, and material deliveries should follow agreed routes and schedules. Third, follow the general contractor's overall site coordination. This project operated under China Construction Eighth Engineering Division's safety-management rules for the campus facilities project and required each work area to be cleaned and materials organized at the end of each shift.
Q: What should be checked during completion acceptance of a gymnasium?
A: In addition to routine visual inspection and document review, acoustic fit-out projects should focus on five items: acoustic construction methods and concealed-work acceptance records; corrosion and fire protection of the steel transfer framework and weld quality; sports-floor flatness and the vibration-isolation base construction; electrical insulation and grounding tests; and the indoor air-quality test report. This project passed completion acceptance on September 8, 2022, with the conclusion “Complies with the design requirements; acceptance passed,” confirmed by the seals of both the general contractor and specialist subcontractor.
Pitfall: Carrying out ordinary interior decoration without dedicated acoustic treatment.
Solution: Ordinary decoration addresses appearance; acoustic fit-out addresses what people hear. In a large untreated space, excessive reverberation makes announcements indistinct and whistles linger. Even luxurious finishes cannot solve the fundamental problem of poor speech intelligibility. The correct approach is to incorporate high-performance ceiling absorption, wall absorption and low-frequency resonance treatment into the design from the beginning.
Pitfall: Choosing acoustic materials based only on their absorption coefficient while ignoring fire safety and fiber containment.
Solution: The sound absorption coefficient is only one performance indicator. A gymnasium has high foot traffic, so materials must also meet the required fire-performance classification. If loose-fiber materials are not enclosed to prevent leakage, fibers may be carried by airflow and affect indoor air quality. Proper practice requires a sealed double-bagged construction and fire-test documentation; neither should be omitted.
Pitfall: Welding the steel transfer framework by experience alone and cutting corners on corrosion and fire protection.
Solution: The ceiling transfer framework carries the load of the entire suspended-ceiling system. Surface-preparation grade, the number of primer and topcoat layers, and the thickness of fireproof coating are all specified requirements. This project used Sa 2.5 surface preparation, two coats of red-lead primer, two coats of topcoat and 4.5 mm of fireproof coating. Omitting any step may not cause an immediate visible problem, but corrosion or failure of fire protection several years later can create serious risks.
Pitfall: Using makeshift mobile scaffolding for work at height simply to save money.
Solution: Work inside an 11-meter-high hall creates risks of scaffolding overturning during erection and movement. Select access equipment according to the task: use scissor lifts for large-area installation and mobile platforms only for localized repairs, with a dedicated safety officer supervising the work. The equipment cost saved is insignificant compared with the consequences of a fall-from-height accident.
Pitfall: Installing sports flooring directly on the structural slab without a vibration-isolation base.
Solution: When sports flooring is installed directly on the slab, footsteps and ball impacts can travel through the floor structure to the space below, creating disruptive impact noise. The appropriate method is to install a raised vibration-isolation base first. This project used two layers of 3.7 mm damping acoustic underlay, with a sound insulation rating above 30 dB, followed by maple flooring. This approach supports both sports performance and floor-to-floor sound insulation.
Pitfall: Allowing construction activities and teaching to mix on campus without restricted access or physical separation.
Solution: The greatest risk of campus construction is not the construction work itself, but the uncontrolled interaction between the public workforce and underage students. The construction zone must be enclosed, access must be controlled, and workers must complete site-entry safety training and registration. The general contractor's formal site-management procedures on this project—including site-entry instructions, fingerprint collection and identity-document filing—provide a useful reference for other school projects.
School gymnasium projects involve architectural acoustics, interior decoration, steel structures, flooring, fire safety, environmental requirements and electrical engineering. Design and acceptance should be based on the following national and industry standards:
Standard No. | Standard title |
JGJ 31-2003 | Code for Design of Sports Buildings |
JGJ/T 131-2012 | Code for Acoustic Design and Measurement of Sports Venues |
GB/T 50356-2005 | Code for Acoustic Design of Theaters, Cinemas and Multipurpose Halls |
GB 50118-2010 | Code for Design of Sound Insulation of Civil Buildings |
GB 50325-2020 | Standard for Indoor Environmental Pollution Control of Civil Building Engineering |
GB 18580-2017 | Indoor Decorating and Refurbishing Materials – Limit of Formaldehyde Emission of Wood-Based Panels and Finishing Products |
GB 50222-2017 | Code for Fire Prevention in Interior Decoration Design of Buildings |
GB 50210-2018 | Unified Standard for Acceptance of Construction Quality of Building Decoration and Fit-Out Works |
GB 50209-2010 | Code for Acceptance of Construction Quality of Building Ground Works |
GB 50205-2020 | Standard for Acceptance of Construction Quality of Steel Structure Works |
GB 50303-2015 | Code for Acceptance of Construction Quality of Building Electrical Engineering |
GB 55024-2022 | General Code for Building Electrical and Intelligent Systems |
Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. has extensive experience in acoustic and lighting engineering. Its services cover acoustic fit-out and integrated audio, lighting and video systems for gymnasiums, basketball halls, auditoriums, assembly halls, theaters, concert halls, studios and recording rooms. The company undertakes projects in China and overseas, with a focus on South China—including Guangzhou, Shenzhen, Foshan, Dongguan and Zhuhai in the Pearl River Delta—as well as East China, Central China and Southwest China. For school gymnasiums, covered sports grounds, auditoriums and cultural venues, the company provides one-stop services from acoustic design and preliminary cost estimates to integrated system installation, maintenance and after-sales support.