New York TV Studio Complex: SinoVision Acoustic Build

Views: 196     Author: Saijia Acoustic     Publish Time: 2026-11-18      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
Reddit sharing button
Threads sharing button
sharethis sharing button

SinoVision U.S. Chinese Television Studio Acoustic Fit-Out, Lighting Systems and Stage Machinery Project: From Concept to Delivery


At Collins Place in Queens, New York, an international Chinese-language media organization with more than three decades on air brought the sound, lighting and stage machinery for its new news production center together in one procurement and installation project. Three spaces were completed on the same floor: an approximately 300 m² multimedia studio, an approximately 120 m² cooking-show recording studio, and an approximately 300 m² multipurpose black-box theater. The project was commissioned by SinoVision U.S. Chinese Television and undertaken by Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd., which was responsible for the studio acoustic fit-out and the procurement and installation of lighting equipment. Delivery spanned the Pacific, from the design concept in March 2017 to procurement and installation in 2018. Following the timeline from design and pre-construction preparation through key construction activities, completion and acceptance, this case study reviews the overseas studio project using design renderings, cost-estimate documents, technical briefings and site photographs. It is intended as a reference for organizations planning international Chinese-language media centers and overseas studios.


1. Project Profile: Key Facts at a Glance

1.1 Project Overview

Project Element

Details

Project name

SinoVision U.S. Chinese Television Studio Acoustic Fit-Out, Lighting Systems and Stage Machinery Procurement and Installation Project

Client / owner

SinoVision U.S. Chinese Television (an international Chinese-language media organization launched in 1990 and serving the Greater New York area)

Project location

New news production center, 34-47 Collins Place, Queens, New York, USA

Functional program

Multimedia studio (approx. 300 m²; news, interviews and features) + cooking-show recording studio and multipurpose room (approx. 120 m²) + multipurpose black-box theater (approx. 300 m²; variety shows, talk shows and theatrical performances) + supporting technical rooms

Main systems

Architectural acoustic fit-out; scenic design and set construction; lighting; sound reinforcement and large-screen display; sound insulation and vibration isolation; television lighting suspension; stage machinery (seven systems in total)

Timeline

March 2017: design concept → July 2017: integrated audio-visual design drawings → 2018: procurement and installation

Contractor

Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. (scope: studio acoustic fit-out, including acoustic components, and procurement and installation of lighting equipment)

Design partners

Integrated acoustic and lighting design scheme and cost estimate: Guangzhou Sicheng Stage Design (July 2017); building-permit design: LU NING ARCHITECTURE, New York

Acoustic criteria

Studio reverberation time: 0.45 ± 0.1 s; black-box theater: 0.8–1.0 s; background noise: NR-25; acoustic doors: ≥35 dB; acoustic observation windows: ≥50 dB; RASTI: >0.65

Delivery highlights

Integrated planning for three spaces; NR-25 background-noise environment; compatibility between studio and theater production requirements; coordinated international procurement and on-site installation


Four details in the project record are particularly important. First, the location: 34-47 Collins Place, Queens, New York, the new site of SinoVision's news production center, with building-permit documents prepared by a local New York architecture firm. Second, the functional program: a multimedia studio, a cooking-show recording studio and a multipurpose black-box theater, supporting news presentation, interviews and features, live cooking production, variety shows and stage performances. Third, the acoustic criteria: NR-25 background-noise requirements, different reverberation-time targets for different spaces, and specified sound-insulation ratings for acoustic doors and observation windows—all expressed as measurable acceptance criteria. Fourth, the nature of the project: an international procurement and installation contract, with equipment and acoustic components consolidated and shipped from China and installation and commissioning completed on the other side of the Pacific.


1

Figure 1. Aerial layout of the multimedia studio (design rendering): an integrated arrangement of the curved anchor desk, interview area, multi-screen columns and station-logo wall.


1.2 Why an International Chinese-Language Media Organization Chose a Chinese Project Team

SinoVision U.S. Chinese Television began broadcasting in 1990 and serves the Greater New York area. Its programming spans news presentation, interviews and features, cooking shows and variety entertainment. For an international Chinese-language media organization of this kind, the studio is both a technical environment and the public face of the Chinese-language voice: acoustics determine speech intelligibility, lighting shapes the on-camera image, and stage machinery establishes the safety baseline for variety programs and theatrical performances. Acoustic, lighting and stage-machinery integration is a highly specialized discipline. Few teams in the industry combine the ability to develop integrated designs for multiple spaces with an established equipment supply chain and the organization needed for cross-border delivery. This was why the project bundled acoustic fit-out, lighting systems and stage machinery into one procurement package awarded to Guangzhou Saijia.


2. Design Development: An Integrated Audio-Visual Plan for Three Spaces

2.1 Design Concept: A 360° Open Multimedia Studio Environment

The design concept presentation completed on March 1, 2017 established the project's direction. It drew on current trends and advanced concepts in leading European and American television media, combining an open studio layout with the international evolution of news production. The design considered the characteristics of television news: authority, diversity, multimedia integration, openness and a strong connection to everyday life. The multimedia studio was divided into three functional zones: the news interview area, the news presentation area and the virtual chroma-key area. The news interview desk was designed to rotate through 360 degrees, with a large background screen creating dynamic news visuals. The studio adopted an open layout in all directions to make maximum use of the available space and allow camera positions and shooting formats to change. Whether the presenter was seated, standing or walking, the background composition could be reused consistently, supporting multi-camera, multiple-shot-size and full 360-degree high-definition television production.


In plan, the first floor accommodated the studio, voice-over area, equipment area and main broadcast studio, while the second floor contained additional studio and equipment areas as well as meeting rooms. The functional spaces were independent yet connected by coherent circulation routes. The design renderings below show the overall open layout: the curved anchor desk, NEWS HOUSE interview set, US News stand-up area and three-screen interview zone could all be used flexibly within the same space.


2

Figure 2. Overall multimedia studio rendering: large screen in the news anchor area, three-screen interview zone, SinoVision logo wall and lighting rig.


3

Figure 3. Studio set rendering: NEWS HOUSE interview set, US News stand-up area and director's control-room window.


4

Figure 4. Second aerial view of the studio layout (design rendering): spatial relationships among the interview set, stand-up area and anchor area.


5

Figure 5. News anchor area (design rendering): curved anchor desk, BREAKING NEWS screen and cove lighting.


2.2 Interview and Feature Sets: Three-Screen Interaction and On-Camera Composition

Interviews and feature programs are a core part of the daily output of international Chinese-language media. The design placed three linked screens against an orange feature wall in the interview zone. Sofas and an armchair were arranged in a curved configuration, and camera-framing simulations were used to rehearse single-presenter news delivery, multi-person interviews and small interactive performances. Particular attention was paid to on-camera composition. Dedicated camera views were illustrated for medium close-ups of a solo news presenter, interview close-ups and close-ups of an individual anchor. The set design and lighting therefore had to support live broadcasts, movement, multiple cameras and a range of shot sizes—not simply create an attractive background.


6

Figure 6. Interview-zone camera view (design rendering): three linked displays, curved sofa arrangement and multi-camera shooting positions.


7

Figure 7. NEWS HOUSE interview set (design rendering): city-skyline screen, curved sofa and circular platform.


8

Figure 8. Interview-set camera view (design rendering): background reuse and shot composition within the television frame.


2.3 Quantifying Acoustic Performance: How NR-25 and RASTI > 0.65 Are Achieved

The project established clear quantitative targets for its two principal spaces. The multimedia studio was designed for a reverberation time (RT) of 0.45 ± 0.1 seconds, while the multipurpose black-box theater was designed for 0.8–1.0 seconds (±0.1 seconds). Both spaces were required to meet the NR-25 background-noise rating curve. The sound-insulation rating was specified at no less than 35 dB for acoustic doors and 50 dB for acoustic observation windows, while the Rapid Speech Transmission Index (RASTI) had to exceed 0.65. Setting measurable targets first meant that the proportions of absorption, diffusion and sound-insulating construction were determined by performance requirements rather than guesswork. Noise control came first, followed by sound quality: the studio needed clean, intelligible speech, while the black-box theater needed to preserve speech clarity and the fullness required for performances. The project was designed to accommodate both quiet and active uses under one roof. Each space had independent sound-insulating construction and a separate air-conditioning route, with corridors and technical rooms serving as buffer zones to prevent sound from one space interfering with another.


2.4 Integrated Design Development for Seven Systems

The guiding principle for a multi-space project is integration. Stage lighting and stage machinery must be coordinated on the same detailed drawings; sound reinforcement, large-screen displays and scenic design must be developed together; and the television lighting suspension system must be coordinated with the building-acoustics embeds before construction. One interface schedule for all seven systems and one integrated commissioning process help avoid the most expensive form of rework on overseas projects: a second mobilization across the ocean. The table below summarizes the seven systems, their design priorities and Saijia's proposed solutions.


System

Design priorities

Saijia's proposed solution

Architectural acoustic fit-out

Reverberation time, background noise, sound insulation and speech intelligibility

Set separate acoustic targets for the studio and black-box theater; proportion sound-absorbing and diffusive surfaces according to the performance criteria.

Scenic design and set construction

Set shapes, scenic-panel fabrication and visual presentation

Coordinate drawings with architectural acoustics and lighting positions to prevent scenic panels from obstructing acoustic surfaces.

Lighting system

Studio lighting, theater lighting design, installation and commissioning

Verify television lighting for illuminance, color-temperature consistency and color rendering index (Ra), supporting both news and variety-show modes.

Sound reinforcement and large-screen display

Sound-system design and large-screen installation and commissioning

Configure separate sound-reinforcement systems for the studio and black-box theater; integrate large-screen design with the scenic design.

Sound insulation and vibration isolation

Sound-insulating assemblies, door and window sealing, and equipment vibration isolation

Acoustic doors rated at ≥35 dB and acoustic windows at ≥50 dB to isolate urban environmental noise.

Television lighting suspension system

Suspension positions, travel range and safety accessories

Complete load calculations and fall-prevention measures; provide safety chains, fixture hooks and identification tags for each unit.

Stage machinery system

Black-box theater battens, lifting equipment and stage machinery

Check against applicable safety and acceptance-inspection requirements for overhead stage equipment; support variety shows and theatrical performances.


According to the integrated cost estimate prepared during the design stage in July 2017, the main equipment provisions for each system were as follows. The multimedia studio primarily used 180 W LED spotlights and 120 W LED soft panels, with two color-temperature settings of 5600 K ± 150 K and 3200 K ± 150 K and a color rendering index above 90. The black-box theater was equipped with LED wash lights, moving-head beam lights and LED moving-head pattern lights, together with seven fixed 8 m lighting battens and two 4.5 m battens. The theater sound-reinforcement system included professional two-way loudspeakers and subwoofers, a digital mixing console and wireless microphones. For video displays, the news area used a curved P2.5 full-color LED screen measuring approximately 5.28 m × 1.92 m, while the theater's main screen was a P5 full-color LED display measuring approximately 7.68 m × 4.8 m. Acoustic fit-out included an integrated sound-absorbing ceiling, modular acoustic wall panels, a chroma-key green screen, Grade III lightweight acoustic doors in accordance with the referenced Chinese standard, and acoustic observation windows. The black-box theater had 203 audience seats, arranged to meet the acoustic design requirements. These were the system provisions specified in the design scheme; actual procurement was subject to the executed contract.


3. Before Construction: Permitting Coordination, Existing Conditions and Technical Briefings

3.1 Existing Site Conditions: Converting an Existing Building into a Television Production Facility

The project was located in an existing two-story building in Queens, New York. The building-permit documents described the overall plan to reorganize the interior for television production. The building section identified the broadcast area, production area, Studio C, Open Studio and Auditorium in their respective locations. The site plan and zoning drawings below show the site boundaries, building gridlines and functional areas, providing the spatial base for all subsequent acoustic and lighting design development.


9

Figure 9. Building-permit site plan and zoning drawings prepared by LU NING ARCHITECTURE, New York: site and studio functional zones at 34-47 Collins Place.


Site photographs show the original condition before renovation: a large-span, industrial-style space with a steel structure, masonry-block walls and an exposed industrial roof frame. Its daylighting and acoustic conditions were far from suitable for television production. Urban environmental noise, reflections from the roof structure and floor-borne vibration all had to be addressed in the acoustic design. These existing conditions were also why sound insulation and vibration isolation were treated as one of the project's seven major systems. The specified ratings—at least 35 dB for acoustic doors and 50 dB for acoustic observation windows—were intended to create a quiet production environment within this industrial shell.


10

Figure 10. Existing site before renovation, view 1: large-span steel structure and masonry-block walls.


11

Figure 11. Existing site before renovation, view 2: indoor industrial shelving and original roof structure.


12

Figure 12. Existing site before renovation, view 3: site entrance and overall original space.


3.2 Comprehensive Technical Briefings: Translating Workmanship Requirements into Site Practice

The project records contain four construction quality and technical briefing documents covering lighting, switches and socket installation; structured cabling; doors and windows; and wood veneer panel installation. Each document identifies the project as “SinoVision Chinese Television Acoustic Components” and Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. as the construction contractor, with the recipients signing and stamping the records individually. The lighting briefing, for example, covered the internal diameter and wall thickness of steel suspension conduits, selection of support materials, and the requirement that luminaires weighing more than 3 kg be connected to the building structure through suspension bolts and dedicated framing. It also specified the use of cool-light sources and fire-resistant thermal insulation in flammable areas, as well as wiring, grounding and allowable deviations for switches and sockets. All items were briefed in accordance with the applicable code for acceptance of building electrical work. The structured-cabling briefing specified cable-tray dimensions, junction-box placement at bends in concealed conduits, cable allowances and cable identification and continuity checks. Consistent workmanship depends on ensuring that every work crew receives and understands the technical briefing—a quality baseline that must be maintained even when an overseas project relies on remote guidance.


3.3 Preparing Equipment for International Shipment: Ordering Long-Lead Items First

Preparing equipment for export was a key part of this international project. The project followed three principles: complete detailed design first, place orders for long-lead equipment early, and ship in batches. Lighting fixtures, suspension components, dimming equipment and acoustic materials were centrally procured in China. Suspension components and mechanical parts were pre-assembled and inspected before leaving the factory, while sea-freight packaging was designed to protect against moisture and impact. Large-screen modules, audio equipment and studio furniture were scheduled for shipment according to the installation sequence. Upon arrival, each item was checked against its packing list, with replacement shipments initiated immediately if damage or shortages were found. Keeping the uncertainty of international logistics from disrupting the critical construction schedule was a top priority during preparation.


4. Key Construction Activities: Four Major Challenges in a Cross-Border Project

4.1 Four Major Challenges and Their Countermeasures

The project's challenge-and-countermeasure schedule identified each risk and set out a corresponding control measure. The following table summarizes the four major challenges and responses confirmed by the construction records.


No.

Key challenge

Challenge analysis

Countermeasure

1

Cross-border transportation of acoustic materials and equipment

Long shipping distances and complex cross-border procedures create risks of transport damage, customs delays and unpredictable logistics lead times.

Use a logistics provider experienced in international shipments; plan routes and customs clearance in advance; use custom protective packaging for acoustic components; pre-assemble and inspect suspension and mechanical parts before dispatch; inspect each package on arrival and initiate replacement shipments immediately for missing or damaged items.

2

Implementing remote technical guidance on site

Communication barriers and differences in overseas site conditions can make it difficult to implement technical requirements correctly.

Prepare detailed installation manuals and video instructions for acoustic components; assign a dedicated technical liaison; provide ongoing guidance through real-time online communication and milestone inspections.

3

Coordination with New York local regulations

Technical processes follow Chinese broadcasting and acoustics industry standards, while building, fire-safety, electrical and construction-safety work must comply with local regulations.

Apply dual compliance: brief the owner's technical team item by item before mobilization, confirm structural loading, electrical and fire-safety interfaces in advance, separate the construction zone from broadcast and office areas, and schedule high-noise work outside critical operating periods.

4

Managing simultaneous construction across multiple spaces

The three spaces are similar in scale and involve interdependent trades; poorly coordinated interfaces can easily lead to rework.

Sequence work as “concealed works before finishes, acoustics before equipment.” Complete sound-insulation, vibration-isolation and suspension embeds first; coordinate acoustic finishes with scenic construction; check interfaces and protect completed work every day.


Of these four challenges, the first two—cross-border transportation and remote technical guidance—are specific to overseas projects. The other two—coordination with local regulations and simultaneous work across multiple spaces—are common to large-scale integrated acoustic and lighting projects. None can be solved simply by purchasing better equipment; all require careful organization and workmanship. Dual compliance is particularly important: technical processes follow the relevant Chinese broadcasting and acoustics industry standards, while building, fire-safety, electrical and construction-safety requirements must comply with local regulations. The two frameworks need to be aligned during the site-entry briefings, before work begins.


4.2 Acoustic Construction Methods: Building Performance into the Assembly

Acoustic performance is not achieved simply by applying a finish material; it is created by the complete construction assembly. The design drawings included a detailed schedule defining the materials and methods for each surface. The ceiling used an aluminum-grille sound-absorbing ceiling (Series 150 aluminum grilles with acoustic wool behind) and custom F1 acoustic ceiling panels. The main wall system used perforated aluminum acoustic finishes, comprising a light-gauge steel frame, two layers of gypsum board with glass-wool acoustic infill, 8 mm perforated aluminum panels with an approximately 12% open area, and a nonwoven backing. Additional assemblies included upholstered acoustic feature walls and perforated eco-wood acoustic finishes. Flooring varied by space and included resilient vinyl flooring, solid-wood flooring and tempered-glass flooring. Acoustic doors, observation windows and silenced fresh-air ventilation systems were selected to meet the specified performance targets. The thickness of each material layer, stud spacing and density of the acoustic wool all contribute to the two key performance figures: reverberation time and background noise.


13

Figure 13. Main interior construction and material schedule (design drawing SM-01): layered assemblies for aluminum-grille acoustic ceilings, perforated aluminum acoustic walls and sound-insulating floors.


4.3 Suspension and Stage Machinery Safety: Completing Load Calculations Up Front

The black-box theater had to accommodate variety shows, stage art and theatrical performances. Lighting and machinery therefore required integrated detailed design. The front-light, side-light and backlight positions had to be coordinated on the same drawing with the travel paths of stage battens and the locations of lifting points, avoiding conflicts between lighting bars and stage machinery. Each suspension point and item of overhead equipment required an individual load calculation. Luminaires were supplied with matching hooks, safety chains, identification tags and connectors. Fall protection and travel-limit safeguards were incorporated from the outset. Acceptance was to be based on applicable industry requirements, including relevant safety and inspection standards for stage machinery and overhead equipment. Reliable machinery operation is fundamental to theater safety, and this requirement is no less important for an overseas project.


5. Completion: Integrated Acoustic and Lighting Environments Across Multiple Spaces

5.1 Cooking Studio: A Professional Production Space for Food Programs

The cooking-show recording studio and multipurpose room, with an area of approximately 120 m², were among the most practical and activity-oriented spaces in the project. They had to support both live broadcasts and recordings of cooking and food programs, while also serving as a multipurpose activity venue. The design centered on an island workstation and a large background screen. The range hood, sink and cooking appliances were arranged according to the production workflow. Lighting suspension equipment and soft-light coves were concealed within the black ceiling. Food programming places particularly high demands on color rendering: whether ingredients appear true to life on camera is a direct test of the lighting design. The following renderings show the design for this space.


14

Figure 14. Cooking studio design rendering 1: island workstation, large background screen and lighting rig integrated into the black ceiling.


15

Figure 15. Cooking studio design rendering 2: range hood, cooking appliances and overall visual concept for the program.


16

Figure 16. Cooking studio design rendering 3: combined workflow between the preparation area and tasting counter.


5.2 Multipurpose Black-Box Theater: An Audio-Visual Stage for Variety Shows and Theatrical Performances

The multipurpose black-box theater, approximately 300 m², was designed for auditorium-quality sound, with a noticeably longer reverberation time than the studio to accommodate variety shows and theatrical performances. Its 203 audience seats were arranged to meet the acoustic design requirements. A central hexagonal screen and arrays of LED side screens formed the main visual elements of the stage, while a circular lighting truss and front-light bridge covered the full performance area. The stage machinery system, including battens and lifting equipment, supported live broadcasts and recordings of variety shows, talk shows and talent competitions. Stable machinery operation is fundamental to performance safety. The following renderings show the design for this space.


17

Figure 17. Multipurpose black-box theater design rendering 1: view from the audience seating toward the central hexagonal screen and LED side-screen arrays.


18

Figure 18. Multipurpose black-box theater design rendering 2: view from the stage toward the audience seating and circular lighting truss.


19

Figure 19. Multipurpose black-box theater design rendering 3: stage lighting and scenic design for a theatrical performance setup.


For accuracy, it should be noted that the publicly available project materials contain design renderings, but no photographs of the completed project after final acceptance were retained. All images above are therefore correctly identified as design renderings and are not presented as photographs of the completed facility. The actual delivery status is documented by the procurement and installation contract, technical briefing records and commissioning records, as explained in the acceptance section below.


6. Acceptance: Equipment-Level Commissioning, Integrated Commissioning and Performance Retesting

6.1 Two-Stage Commissioning and Acoustic Retesting

Acceptance followed a two-stage process: individual equipment commissioning first, followed by integrated commissioning. During individual commissioning, the function and safety of each luminaire, suspension component, stage-machinery unit, sound-reinforcement device and large-screen system were checked separately. Integrated commissioning then tested the complete system under coordinated operation. In the studio, the key checks included color-temperature consistency, audio-video synchronization and speech intelligibility. In the black-box theater, the focus was on coordinated lighting and machinery operation and the sound-reinforcement coverage. Acoustic performance was also retested on site, including reverberation time and background noise. The facility was handed over to the owner for trial broadcasts and performances only after all specified targets had been met. The measurement methods for reverberation time and speech intelligibility are covered by the relevant standards listed in Section 10. Measured results provide the basis for acceptance and future maintenance.


6.2 Clarification of the Available Handover Records

The project archive does not contain a separate scanned copy of the final completion acceptance report. This case study therefore documents the delivery process based on the procurement and installation contract, four construction technical briefing records, the challenge-and-countermeasure documents and the design cost estimate. No acceptance data has been invented. For an overseas project, actual use is the ultimate test: whether news presentation sounds clean, interviews remain intelligible, and the lighting and machinery for variety performances operate reliably are all verified during trial broadcasts and performances. The approach of “putting performance criteria in the contract and letting commissioning data speak for itself” is also one of the most reliable forms of delivery evidence for cross-border projects.


7. Long-Term Operation: Keeping an International Media Center Running Reliably

Programming schedules at international media organizations are measured in hours, so the long-term stability of technical spaces depends on systematic maintenance. Three practices form the basis of reliable operation. First, routine inspection of acoustic assemblies: regularly check acoustic finishes, acoustic doors, seals on observation windows, and vibration-isolating hangers and supports. Repair cracks or loose components promptly, and consider retesting acoustic performance annually against the handover values. Second, safety inspections of lighting suspension systems and stage machinery: periodically inspect luminaire drivers and light-output depreciation, wear on suspension components and wire ropes, fall-protection provisions and load capacity of television lighting rigs, as well as the drive chains, travel limits and braking systems of stage machinery. Keep maintenance records. Third, integrated maintenance of audio, large-screen displays and system interfaces: periodically verify sound coverage and transmission gain, inspect LED-screen alignment and heat dissipation, and maintain asset registers and inspection schedules for production control, switching and signal paths. Remote response and spare-parts support from the contractor's project service team help keep broadcasts and performances running across the Pacific without interruption.


8. FAQ: Frequently Asked Questions About Building International Chinese-Language Media Centers

Q: How can a Chinese engineering company deliver a studio project overseas, for example in the United States?

A: A common approach is “detailed design in China + centralized equipment procurement and sea freight + on-site installation and commissioning.” The technical scheme and acoustic calculations are completed in China, core equipment is procured domestically and shipped overseas, and an installation and commissioning team carries out the work on site. At the same time, the project must comply with local building, fire-safety and electrical regulations, ensuring dual compliance.


Q: How does acoustic design differ between a television studio and a black-box theater?

A: A television studio is mainly used for speech-based programming, so it requires a short reverberation time (0.45 ± 0.1 seconds in this project) and strict background-noise control (NR-25). A black-box theater is designed for performances and uses a longer reverberation time (0.8–1.0 seconds in this project) to create a fuller sound. The two spaces need independent acoustic construction and zoning to prevent sound transmission between them.


Q: What do the NR-25 and RASTI > 0.65 targets mean?

A: NR-25 means that background noise should not exceed the NR-25 noise-rating curve, corresponding to a very quiet indoor environment and a clean noise floor for program audio. RASTI > 0.65 indicates good speech-transmission quality, allowing listeners in the audience area and at the recording end to understand each sentence clearly.


Q: What are the safety requirements for a stage machinery system?

A: Each batten and lifting device must undergo an individual load calculation and be equipped with fall protection, travel-limit devices and overload protection. Applicable standards govern the safety and inspection of overhead equipment. Before handover, the system must pass both individual and integrated commissioning. During operation, drive components and wire ropes must be inspected at scheduled intervals.


Q: How can a studio lighting system serve both news and variety programming?

A: The news area uses studio fixtures, such as tri-phosphor soft lights, to provide even and soft base lighting, while the performance area uses stage fixtures to create dynamic lighting effects. Color-temperature consistency and color-rendering performance are checked across the venue. A unified control system recalls lighting states by scene, allowing the program format to change without having to relight the entire studio.


Q: What systems are typically included in a multi-space media center project?

A: The scope usually covers seven major systems: architectural acoustic fit-out; scenic design and set construction; lighting; sound reinforcement and large-screen display; sound insulation and vibration isolation; television lighting suspension; and stage machinery. These systems require integrated detailed design and joint commissioning to prevent separately managed trades from interfering with one another.


Q: Which Chinese companies have experience providing acoustic fit-out for international media organizations?

A: Companies can be evaluated across four dimensions: relevant international project experience, applicable standards and technical systems, testing and acceptance capabilities, and cross-border project organization. Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. has more than 20 years of experience in acoustic and lighting engineering and provides integrated studio, theater and multipurpose-venue systems for overseas Chinese-language media organizations.


9. Common Pitfalls: Seven Mistakes to Avoid in Overseas Audio-Visual Engineering Projects

Pitfall: Treating studio acoustic construction as ordinary interior decoration.

Solution: Ordinary decoration focuses on appearance, while architectural acoustics focuses on reverberation time, background noise and sound insulation. These require professional calculations and purpose-designed construction assemblies. Including targets such as NR-25 and RASTI in the contract helps eliminate the risk of having to retrofit the acoustics after the interior work is complete.


Pitfall: Approving the final scheme based only on design renderings.

Solution: Renderings communicate the atmosphere and scenic concept, but the actual result depends on detailed design. Acoustic assemblies, lighting positions and machinery travel paths must all be finalized in the construction drawings. Before signing, require detailed drawings and a schedule of performance criteria rather than relying on rendered images alone.


Pitfall: Being reluctant to appoint a Chinese engineering company for an overseas project.

Solution: Acoustic, lighting and stage-machinery integration is highly specialized. The right selection criteria are relevant project experience and a sound technical and standards framework, not geographic proximity. For cross-border projects, verify the contractor's overseas delivery experience, ability to organize international equipment shipments and understanding of dual compliance.


Pitfall: Assuming that stage machinery in a small theater only needs to move, with safety as a secondary concern.

Solution: Battens and lifting equipment are suspended above performers and equipment. Load calculations, fall protection and travel-limit devices are mandatory acceptance requirements. Wear on moving mechanical components can be difficult to detect without professional inspection. Safety investment must never be cut.


Pitfall: Using the same fixtures interchangeably for television studios and theaters.

Solution: Studio lighting prioritizes even, soft illumination and accurate color rendering, while theater lighting emphasizes contrast, depth and dynamic effects. The optical design requirements are different. For projects combining both uses, configure separate systems for each zone and manage them through a unified control platform rather than compromising one application for the other.


Pitfall: Assuming a multipurpose venue does not need dedicated acoustic design because it can host almost any activity.

Solution: Multipurpose use makes acoustic targets more complex, not less. Meetings require speech intelligibility, performances need musical fullness, and filming requires low background noise. Without targeted sound absorption and, where appropriate, variable acoustic design, a multipurpose venue may end up being mediocre at every use.


Pitfall: Assuming that a professional technical space needs no further attention once construction is complete.

Solution: Aging acoustic seals, worn suspension wire ropes, loose mechanical drive components and declining luminaire output can all gradually undermine the accepted performance. A systematic maintenance program is essential to keep the acoustic and lighting environment at its original delivery standard.


10. Applicable Standards: References for Design and Acceptance

The project was carried out in New York, United States. The Chinese national and broadcasting-industry standards cited in this case study are presented as general references for the design, construction and acceptance of comparable projects. The project must also comply with applicable local building, fire-safety and electrical-safety regulations. The following standards are referenced, subject to confirmation of the latest applicable editions:


Standard No.

Standard title

Application

GY/T 5086-2012

Code for Acoustic Design of Radio and Television Recording Studios and Television Studios

Studio acoustic design

GY 5022-2007

Code for Measurement of Reverberation Time in Radio and Television Announcing and Studio Rooms

Reverberation-time measurement

GY 5045-2006

Code for Design of Lighting Systems for Television Studios (including mandatory provisions)

Studio lighting design

GY/T 5043-2013

Indoor Environmental Requirements for Technical Rooms in Radio and Television Centers

Technical-room environment

GB/T 50076-2013

Code for Measurement of Reverberation Time in Rooms

Reverberation-time measurement

JGJ 57-2016

Code for Design of Theater Buildings (Section 6.3 Stage Machinery / 6.4 Stage Lighting / 6.5 Stage Sound / Chapter 9 Acoustics)

Integrated black-box theater design

WH/T 60-2013

General Technical Requirements for LED Stage Lighting Fixtures

Lighting fixture selection and verification

WH/T 28-2007

Stage Machinery – Safety of Overhead Equipment

Stage machinery safety

GB/T 36727-2018

Stage Machinery – Acceptance Inspection Code

Stage machinery acceptance

GB 50371-2006

Code for Design of Sound Reinforcement Systems in Auditoriums

Black-box theater sound-system design

GB/T 4959-2011

Methods of Measurement for Sound Reinforcement Characteristics in Auditoriums

Sound-system performance measurement

GB 50118-2010

Code for Design of Sound Insulation of Civil Buildings

Sound insulation and vibration isolation

GB/T 15508-1995

Acoustics – Methods for Testing Speech Intelligibility

Speech-intelligibility evaluation

GB 50016-2014

Code for Fire Protection Design of Buildings

Fire safety

GB 50303-2015

Code for Acceptance of Construction Quality of Building Electrical Engineering

Electrical installation acceptance


11. Service Coverage: Integrated Project Delivery in China and Overseas

Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. has extensive experience in acoustic and lighting engineering. Its work covers acoustic fit-out and integrated audio, lighting and video systems for television studios, radio broadcast areas, recording studios, theaters, concert halls, assembly halls, auditoriums and gymnasiums. The company undertakes projects in China and overseas, with a focus on South China, East China, Central China and Southwest China. Supported by its headquarters in South China, it provides one-stop services from detailed design and international shipping to installation and commissioning. This project is a representative example of its work for an international Chinese-language media organization, delivering an integrated studio acoustic, lighting and stage-machinery solution in New York.


Consultation: +86 20 8629 9208 | Address: Room 615, Building 3, No. 135 Huangyuan Road, Baiyun District, Guangzhou, China. If you are planning to build or upgrade a television studio, converged-media center or multipurpose venue, or are considering an overseas studio audio-visual engineering project, please contact us to discuss your requirements and obtain a tailored proposal.

Content Menu
CONTACT
Add: Room 615, Building 3, No. 135 Huangyuan Road, Baiyun District, Guangzhou City, Guangdong Province
E-mail: saijia.avl@gmail.com
Mobile: +86-13802436547,  +86-18600228211
INFORMATION
Sign up to receive our weekly newsletter
Contact us
Copyright © 2026 Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. (SJAVL)