A school auditorium is a central venue for opening ceremonies, grade assemblies, open classes, artistic performances, club showcases, and external exchanges. It is also one of the most frequently used and versatile public spaces on campus. For the Auditorium Audio and Lighting System Procurement Project at Peiying Middle School (Science City Campus), Guangzhou, the priority was not to renovate the entire space, but to deliver two core systems that directly determine what audiences hear and see: sound reinforcement and professional lighting. During opening ceremonies, grade assemblies, and consecutive performances, speech from the lectern must reach every row clearly, presentations and video must remain stable on the large screens, and the overhead lighting array must shift from soft conference lighting to performance effects as required. Using this project as a case study, this article covers the project overview, procurement scope and system composition, design stage, design highlights, implementation challenges, construction records, completed-site presentation, FAQs, common pitfalls, applicable standards, and service regions. It also answers schools' key questions: what an auditorium audio and lighting system includes, how conference and performance modes are switched, and what must be tested at acceptance. Except for design drawings marked “Figure D-×”, all images are on-site photographs or frames captured from on-site videos, not design renderings. The existing three-screen LED display, audience seating, and stage facilities are venue-provided infrastructure; this article discusses only the project's audio and lighting systems and how they work with those facilities.
Peiying Middle School in Guangzhou has a history of more than a century and now operates across multiple campuses. Its Science City Campus is located in Baiyun Lake Digital Science and Technology City, Shimen Subdistrict, Baiyun District, Guangzhou. It was officially inaugurated in April 2025 and has a planned scale of 54 classes across primary and junior secondary levels. As a key public and cultural space on the new campus, the auditorium (the school's multifunctional lecture hall) was expected from the outset to host school-wide assemblies, opening ceremonies, grade assemblies, open classes, campus galas, club performances, and visits from external guests. Events of different types are scheduled almost every week.
This high-frequency, diverse, cross-age usage means the auditorium audio and lighting procurement cannot be configured as a single-purpose hall. During meetings, speech at the lectern must be clear, audience-area illuminance comfortable, and lighting free of glare. During performances, the venue also needs front light, top light, beam effects, and sufficient dynamic headroom for music reinforcement. If audio and lighting are assigned to separate contractors, common consequences include incompatible signal paths, manual reconnection during scene changes, and half an hour of last-minute adjustment before an event. This project adopted an integrated delivery approach for sound reinforcement and professional lighting, linking design development, equipment selection, supply and installation, integrated commissioning, and operator training into one complete process, while coordinating interfaces with the existing display, stage, and interior-finish conditions.
Project | Details |
Project name | Auditorium Audio and Lighting System Procurement Project, Peiying Middle School (Science City Campus), Guangzhou |
Project location | Science City Campus of Peiying Middle School, Baiyun Lake Digital Science and Technology City (Shimen Subdistrict), Baiyun District, Guangzhou |
Venue type | Auditorium (school multifunctional lecture hall) |
Campus background | Inaugurated in April 2025; planned capacity of 54 classes across primary and junior secondary levels |
Venue functions | School-wide assemblies, opening ceremonies, grade assemblies, open classes, artistic performances, club showcases, and external exchanges |
Procurement scope | Sound reinforcement system, professional lighting system, and the associated control, signal-processing, and installation components |
Existing coordinated facilities | Existing main screen and two side screens, audience seating, stage, and acoustic/interior-finish interfaces (not included in this project's procurement scope) |
Main equipment categories | Line-array speaker system, digital mixing console, microphones and feedback-suppression equipment, moving-beam lights, LED PAR lights, and dimming-control equipment |
Delivery status | Equipment supplied, installed, commissioned, and integrated; system has entered actual event use |
The site photographs show an audience area dominated by grass-green upholstered chairs and wood-tone and light-colored walls. The side walls feature vertical acoustic treatments, while the ceiling carries lighting fixtures arranged in zones. The stage has a main LED screen and two side screens, with loudspeakers mounted on both sides. For this project, the audio system is responsible for even sound coverage and clear speech; the lighting system must ensure that both the lectern and stage are visible and camera-ready in different scenarios. The three screens, curtains, and audience seating are existing venue conditions. Speaker and lighting positions, circuits, and scene presets therefore had to be designed within those established boundaries rather than starting from scratch.

Figure 1 | Auditorium on-site view: main LED screen and two side screens, overhead lighting array, and grass-green upholstered seating; the event banner reads “Opening Ceremony of Peiying Middle School, Science City Campus, Guangzhou” (on-site photograph).
The procurement scope can be summarized as two core systems—sound reinforcement and professional lighting—together with shared control and signal-processing components. Each system has its own technical standards and acceptance methods, but both must operate within the same scene logic. Control and signal processing form the layer that keeps complex technical work with the implementation team while giving the school simple, consistent operation. The table below lists the work scope, key control points, and applicable standards by category to help schools prepare requirement documents and check procurement lists item by item.
System category | Main procurement and construction scope | Key control points | Key standards |
Sound reinforcement system | Sound-field simulation; speaker positioning and selection; amplifier configuration; digital mixing console and signal-path setup; microphone and feedback-suppression preset commissioning; standardized cable and connector installation | Maximum sound pressure level; steady-state sound-field non-uniformity; acoustic gain; speech intelligibility; feedback suppression | GB 50371-2006; GB/T 4959-2011 |
Professional lighting system | Fixtures for conference/performance dual modes; fixture layout and beam-path adjustment; dimming-control deployment; cable routing and insulation protection; heat-dissipation planning; control-program presets | Front-light uniformity; suspension safety; dimming consistency; one-touch scene recall | WH/T 97-2022; GB/T 14218-2018 |
Control and signal processing | Aggregation of audio and lighting signals; presets for meetings, performances, ceremonies, and exchanges; one-touch switching logic; simplified permissions and operating interface | Ease of operation; protection against misoperation; repeatability of presets | GB 55024-2022 |
Installation and acoustic coordination | Verification of suspension points; cable routing; interfaces with the control room and existing acoustic finishes; sealing of wall penetrations | Complete concealed work before enclosure; prevent breaches in sound-insulation assemblies | GB/T 50356-2005; GB 50118-2010 |
Existing venue interfaces | Signal and scene coordination with the existing main screen, two side screens, stage, and curtain facilities (not included in procurement scope) | Reserved interfaces; synchronized operation; no duplicate construction | GB 50034-2013; GB 50303-2015 |
Lighting in school auditoriums is often underestimated. Some schools approach it as ordinary room lighting and focus only on making the space “bright enough”. The result can be glare in the audience area and flat-looking presenters during meetings, with no front light to separate performers from the background during shows. This project uses a dual-track design for conference and performance modes. Conference mode relies mainly on basic overhead lighting and front light for the lectern, providing even illuminance on desks and in the audience area, consistent color temperature, and camera images without obvious color casts. Performance mode combines moving-beam lights, LED PAR lights, front light, and top light. Preset programs provide fades, cuts, and different scene atmospheres. Fixture layout, beam aiming, dimming circuits, and heat-dissipation provisions were finalized together during design development to avoid damaging the existing ceiling design when adding fixtures later.

Figure 2 | Professional lighting effect: blue scene lighting and overhead beam-light array; on-site video frame showing tests of the conference/performance presets.
The goal of auditorium sound reinforcement is not simply to make the sound loud; it is to make every row hear clearly. The project uses a line-array system and sound-field simulation to determine speaker mounting positions, down-tilt angles, and coverage angles, preventing excessive levels in the front rows and weak sound in the rear. The digital mixing console manages input gain structure, equalization, delay, and feedback-suppression presets. Cables and connectors between amplifiers and speakers are installed in accordance with applicable requirements. Following GB 50371-2006, acceptance should focus on four key characteristics: maximum sound pressure level, transmission frequency response, sound-field non-uniformity, and acoustic gain. Measurements are conducted in accordance with GB/T 4959-2011. In primary and secondary school environments, speech intelligibility takes priority, followed by musical fullness. Scene presets address these two needs separately. Where room acoustics are involved, reverberation-time calculations and Rapid Speech Transmission Index-related checks should also be considered rather than relying solely on listening tests.

Figure 3 | Auditorium audience area: wall-mounted loudspeakers on both sides, vertically striped acoustic wall treatment, and ceiling lighting array (on-site photograph).
The site photographs clearly show a three-screen stage layout: a central main screen for presentations, videos, and performance backgrounds, with two side screens for event banners, subtitles, and prompts. These are existing venue facilities, not part of this project's procurement scope. The audio and lighting systems must nevertheless coordinate with them. When lighting scenes change, screen brightness and color temperature should be matched to avoid overexposed or discolored faces. In performance mode, audio presets and image-switching timing should remain synchronized. Signal channels must also be reserved for external devices. Clearly defining these boundaries prevents duplicate procurement and avoids a responsibility gap during integrated commissioning.

Figure 4 | Full frontal view of the stage: existing three-screen display, wall-mounted loudspeakers, and overhead lighting array (on-site video frame).
A large part of audio and lighting performance is determined by concealed construction. The side-wall acoustic treatment, upholstered seating, and ceiling interfaces affect reverberation time and strong-reflection patterns, directly influencing speech intelligibility. Fixture and speaker suspension points, power and dimming circuits, and wall penetrations must be checked against the existing interior-finish interfaces. Any omission can lead to demolition and rework after completion. This project made point verification, cable routing, and sealing of penetrations the first installation tasks, with item-by-item inspection coordinated with the interior works. After conduits are installed, wall penetrations are sealed with elastic sealing materials to meet fire and electrical requirements while preventing gaps in the sound-insulation assembly. In densely occupied primary and secondary schools, suspension safety and cable insulation take priority over adding visual effects.
The more integrated the technology, the simpler the operation should be. The control and signal-processing layer brings the audio and lighting signal paths into one interface and provides presets for assemblies and open classes, artistic performances, and external exchanges. The first optimizes speech reinforcement, sets lighting to soft conference mode, and reserves large-screen signal channels. The second activates performance-lighting presets and the corresponding audio dynamic headroom, with audio-visual linkage. The third focuses on compatibility with external equipment. On handover, on-site operator training covers basic power-up and shutdown, scene selection, wireless microphones, external-device connections, and simple fault identification. System drawings, equipment lists, and operating instructions are also handed over to lower the learning curve for school support staff.

Figure 5 | Close-up of the digital mixing console in the audio/lighting control room: fader section, scene presets, and signal-path labels (on-site video frame).
This chapter reviews the design-stage calculations. Geometric and construction parameters are design assumptions (identified as assumptions in the text), and all indicators are design targets or calculated design values; they are not directly comparable with as-built measurement data. Actual measurements for this project are governed by the completion and acceptance records. This chapter contains no third-party test conclusions and does not cite any test-report number.
The review addresses one question: how were the auditorium's acoustic and lighting targets derived step by step from the room conditions, and how were they checked in return? The following sections therefore do not simply list equipment by system. Instead, they follow the sequence of “inputs—target setting—back-calculation—verification—trade-offs”, with each figure traceable to an upstream parameter.
Design inputs are not simply “how large is the room?” They are three sets of values that can be entered directly into formulas: clear dimensions and net volume; the construction and developed area of each of the six surfaces; and audience capacity and seat type. The hall is modeled at 18.0 m deep × 15.0 m wide × 6.0 m average clear height, with a 10.0 m × 5.0 m proscenium opening and an 8.0 m main-stage depth. The gross volume is 1,620 m³. After deducting the void behind the proscenium and the solid volume of the raked seating structure, the net volume is taken as 1,550 m³. This converts room volume into volume per seat: 1,550 ÷ 260 = 5.96 m³/seat, near the upper end of the commonly used 4–6 m³/seat range for lecture halls. The greater the volume per seat, the more absorption is needed to achieve the same reverberation time; this becomes the basis for the absorption-area calculations that follow.
Ceiling, 270 m²: gypsum-board substrate and light troughs, 215 m²; localized acoustic-absorption bands (50 mm mineral wool + 150 mm cavity), 55 m².
Side walls, 216 m²: 108 m² on each side. Vertically striped acoustic treatment (15 mm perforated wood finish + 50 mm cavity) covers 45 m² on each side; the remaining area uses wood finish and plaster substrate.
Rear wall, 90 m²: 40 m² fabric-wrapped acoustic panels + 50 m² wooden diffusers and substrate. A 30 m² membrane-type low-frequency absorption cavity is also provided in the rear corner, measured by developed area.
Floor, 270 m²: 190 m² stepped audience-area finish + 80 m² raised timber stage floor inside the proscenium. Proscenium wall surfaces (wood finish on both sides and above the opening), 50 m².
The total developed area of the six surfaces is 926 m², 1.1% below the geometric surface area of 936 m² calculated from 18 × 15 × 6. This is a normal difference after deducting the proscenium opening. This consistency check must pass first; otherwise, the volume and absorption areas would be based on two different geometries, and the calculated reverberation time could appear valid while being entirely wrong. Environmental conditions are set at 26°C and 65% RH for Guangzhou in summer. Air absorption is included by frequency band in accordance with ISO 9613-1; the 8 kHz band alone contributes 106 m² of equivalent absorption area, which is one reason high-frequency reverberation is naturally shorter than mid-frequency reverberation.
It should be emphasized that the dimensions, assemblies, and absorption coefficients above are illustrative design assumptions. The completed project must be verified against drawings and measurements. However, the assumptions must be internally consistent; that is the starting point for this review.
For a lecture hall/auditorium, the use-based preset specifies a mid-frequency target of 0.95 s, with an allowable range of 0.75–1.20 s. The target curve is slightly longer at low frequencies and shorter at high frequencies (63 Hz is 1.20 times the mid-frequency value; 8 kHz is 0.85 times the mid-frequency value). This preset provides a range but does not specify the exact point for this hall. Since the setpoint directly determines the absorption budget, it must be selected first.
Two constraints guide the setpoint. The first is the intended use: school-wide assemblies, grade meetings, and open classes are speech-oriented, so intelligibility takes priority and the drier side of the range is preferred. The second is the unoccupied-room limit: the absorption difference between an empty hall and a full 260-seat hall with upholstered chairs is substantial. If the design is set only for a full audience, reverberation in the empty hall may exceed the 1.20 s upper limit, requiring repeated console adjustments before every event. Considering both constraints, the mid-frequency setpoint for this hall is 0.85 s, 0.10 s below the preset midpoint and in the lower half of the range. This is intentional: a small reduction in musical fullness is accepted so that major parameter changes are not needed when the hall is empty.
Background noise is set in the same way. The lecture hall is controlled to NR 25. The main noise sources are the urban road along one exterior wall and adjacent teaching rooms. Required sound insulation for the exterior walls, doors, and windows is back-calculated by frequency band using the controlling band (125 Hz). The resulting values are NR 22 with a full audience and NR 24 when empty, both below the target. The Speech Transmission Index, calculated using the modulation transfer function method, is 0.59 (Category C), above the 0.50 intelligibility threshold. This indicates that the combination of “0.85 s + NR 25” is reasonable for speech clarity.
Table 1 | Design Target-Setting Schedule: From Standards to Verifiable Design Values
Indicator | Reference | Design target | Calculated design value | Conclusion |
Mid-frequency reverberation T60 (500/1,000 Hz) | GB/T 50356-2005 lecture-hall preset | 0.85 s (range 0.75–1.20) | 0.83 s / 0.78 s (full occupancy) | Meets target |
Empty-room reverberation T60 (500 Hz) | Same as above; empty-room condition as a second constraint | ≤1.20 s | 1.14 s | Meets target |
Volume per seat | Lecture-hall engineering practice: 4–6 m³/seat | 5.5–6.0 m³/seat | 5.96 m³/seat | Meets target |
Background noise | GB/T 50356-2005; NR rating curves | NR 25 | NR 22 full / NR 24 empty | Meets target |
Speech Transmission Index (STI) | IEC 60268-16 modulation transfer function method | ≥0.50 | 0.59 (Category C) | Meets target |
Sound-field non-uniformity (1 kHz) | GB 50371-2006 | ≤6 dB | 4.7 dB | Meets target |
Audience-area illuminance (conference mode) | GB 50034-2013 | 200 lx | 196 lx | Meets target (−2%) |
Airborne sound insulation to adjacent teaching rooms | GB 50118-2010; GB 50099-2011 | ≥50 dB (Rw+C) | 51.6 (composite) / 50.0 (field estimate) | Meets target (resilient junction) |
In this table, T60 values are statistical-acoustics calculations; sound pressure level and illuminance are engineering-calculation values; sound insulation values are typical component-library values adjusted for junction details. None are measured results.
Substituting the six surface assemblies into T = 0.161V/A first gives a baseline for a room with no additional treatment: the full-house reverberation time at 500 Hz is 1.42 s, with total absorption of 175.2 m² sabin, comprising 119.6 from the audience, only 50.6 from surfaces, and 5.0 from air. With the same assemblies, the empty-room value is 2.71 s. The difference between this baseline and 0.85 s is the absorption that must be added.
Step 1: Back-calculate using the preset 0.95 s target. Required ΣA = 0.161 × 1,550 ÷ 0.95 = 262.7 m² sabin, leaving a deficit of 87.5 m². Step 2: Check whether one wall can solve the problem. If all treatment were placed on one side wall as vertically striped acoustic treatment (perforated wood finish, α500 = 0.70), the available area of 108 m² could provide at most 75.6 m² of absorption, still 11.9 m² short of the 87.5 m² requirement. The calculation therefore shows that a single surface cannot meet the target; treatment must be distributed. This is why the striped treatment cannot be installed on only one side or rely on walls alone.
Step 3: Add the empty-room constraint. If only 87.5 m² of absorption were added, empty-room ΣA would be 175.2 − 119.6 + 87.5 + 36.4 = 179.5 m², giving an empty-room reverberation time of 1.39 s, above the 1.20 s limit. Solving the empty-room limit as a second equation requires empty-room ΣA ≥ 208 m², or surface absorption of at least 166.6 m², corresponding to no less than 116 m² sabin of additional absorption. Step 4: Select the implementation value. Surface absorption is increased to 176.9 m² (an addition of 126.3, leaving approximately 8% headroom). Full-house ΣA is 301.4 m², and T60(500) = 0.161 × 1,550 ÷ 301.4 = 0.83 s.
The additional 126.3 m² of absorption is allocated according to available area and suitable construction: the 55 m² ceiling absorption band contributes 43.5 (net increase over the substrate); the 45 m² vertically striped treatment on each side wall contributes 60.3 in total; 40 m² of rear-wall fabric panels contributes 12.0; and the 30 m² low-frequency cavity in the rear corner contributes 10.5. One deliberate trade-off is that side-wall treatment is limited to 45 m² per side (42% coverage), rather than covering the entire wall. The vertical stripes are part of the room's architectural language; coverage above half would disrupt the wall's vertical proportions. The remaining absorption is provided by the ceiling bands and rear-wall panels, which are less visually prominent.

Figure D-01 | Developed acoustic-treatment elevations and absorption composition: surface-by-surface assemblies, areas, mid-frequency absorption coefficients, and the four-step back-calculation.
The same construction is evaluated under two occupancy conditions. At mid frequencies (500/1,000 Hz), reverberation is 0.83/0.78 s with a full audience and 1.14/1.08 s when empty, a 0.31 s difference at 500 Hz. The corresponding difference for the untreated baseline is 1.29 s (2.71 versus 1.42). This reduction is not achieved simply by adding more absorption; it comes from reducing the audience's share of total absorption. In the full-house ΣA, the audience accounts for 39.7% and surface absorption for 58.7%. When the room is empty, the audience contribution drops from 119.6 to 36.4 while surface absorption remains unchanged, reducing the relative decline in total absorption.
Table 2 | Reverberation Time and Absorption by Octave Band (Calculated Design Values)
Frequency band (Hz) | Target T60 (s) | Full occupancy Sabine | Full occupancy Eyring | Empty room Sabine | Full occupancy ΣA (m² sabin) |
63 | 1.50 | 1.88 | 1.83 | 2.46 | 132.5 |
125 | 1.20 | 1.36 | 1.30 | 1.82 | 184.2 |
250 | 1.00 | 1.01 | 0.96 | 1.40 | 246.4 |
500 | 0.85 | 0.83 | 0.78 | 1.14 | 301.4 |
1,000 | 0.85 | 0.78 | 0.73 | 1.08 | 320.1 |
2,000 | 0.80 | 0.77 | 0.73 | 1.08 | 322.3 |
4,000 | 0.75 | 0.73 | 0.70 | 1.01 | 339.6 |
8,000 | 0.72 | 0.62 | 0.59 | 0.81 | 403.5 |
V = 1,550 m³, S = 926 m², 260 seats. Values are statistical-acoustics calculations, not measured results.
Two points in the table require explanation. First, reverberation is relatively long at 63–125 Hz (1.88/1.36 s with a full audience). This is an inherent characteristic of lightweight acoustic assemblies: perforated panels and mineral wool have low-frequency absorption coefficients of only 0.10–0.20, while each audience member contributes only 0.20 sabin at 63 Hz. Reducing 63 Hz to 1.20 s would require another 132 m² sabin, equivalent to adding 130 m² of low-frequency absorption cavities, which is incompatible with the available wall area and budget. The main control range for speech is 250–4,000 Hz, so low frequencies are managed by reducing them rather than forcing them to match the mid-frequency target. The 30 m² membrane-type low-frequency cavity reduces the empty-room 63 Hz value from around 3.1 s to 2.46 s. Second, Sabine and Eyring differ by 6% at mid frequencies (0.83 versus 0.78 s), with greater differences in bands having higher absorption coefficients (5% at 8 kHz). The more conservative Sabine values are adopted. The peak average absorption coefficient is 0.19, below Eyring's suggested 0.20 threshold; the two formulas are used in parallel only for cross-checking.

Figure D-02 | Reverberation-time frequency response: calculated design values compared with the GB/T 50356 target range.
The 260 seats are arranged in 12 rows at a 900 mm row pitch. The first-row eye position is 3,500 mm from the proscenium line, and the last row is 13,400 mm away. Each row has 19–24 seats (260 in total), with 570 mm seat spacing. The last-row clear width is 13,680 mm, with 660 mm side aisles on both sides. The row pitch is set at the minimum of 900 mm because the room is only 18 m deep: adding 100 mm to each row would consume another 1.1 m across 12 rows, leaving insufficient space for rear-area egress and cross aisles.
The first step in sightline calculations is not to calculate the rake, but to define the viewing point. Of the three possible reference lines—the proscenium line, front-curtain line, and stage-lip line—only the proscenium line should be used. The stage-lip line is 1.5–8 m toward the audience from the proscenium line and would make all downward viewing angles appear smaller. There are also two conventions for viewing-point height: the stage-floor elevation commonly used for performances, and 1.0–1.1 m above the stage floor (the speaker's face height) commonly used for lecture halls. This hall adopts the latter, at +1,600 mm, because its routine uses are speeches, teaching, and screen viewing. The audience looks at the upper body of a speaker and the lower part of the screen, not the stage floor. This is not an aesthetic preference; the calculations show why. If the stage floor (+600) were used as the viewing point, each row would require a rise of 292–435 mm and the last-row floor would be pushed to 4.23 m, conflicting with the 6.0 m average clear height. With the +1,600 mm viewing point, row rises fall to 120–320 mm and the last-row floor is 2.60 m, leaving 3.4 m of clear standing height.
The rake is calculated row by row so that the rear-row sightline clears the head of the person in front, leaving 120 mm between eye level and the top of the head. Each rise is rounded up to the next 10 mm; rounding can only increase the rise, keeping the C-value positive by construction. Floor elevations by row are 0/120/270/450/650/880/1,120/1,390/1,670/1,970/2,280/2,600 mm. Actual C-values range from 52 to 68 mm, with the minimum at Row 7 (52 mm), meeting the C ≥ 50 mm check. The downward viewing angle changes from −7.3° in the first row (slightly upward) to +9.1° in the last row, remaining within the ±30° comfort range.
The same rake must also be checked in reverse. If the stage floor (+600) is used as the viewing point for floor-level performance actions, Rows 2–12 are all obstructed, with C-values from −137 to −12 mm. Moving the viewing point 1.0 m inward (corresponding to the main performance area being 1 m inside the proscenium line) reduces the obstruction range to −112 to +3 mm, with no obstruction from Row 10 onward. This conclusion should be included in the design briefing: the rake is set for teaching and lecture use. During performances, floor-level actions may be obstructed in the front area. The solution is to treat the first two rows as flexible seating and keep the main visual content in the lower-middle 70% of the screen, rather than raising the entire seating rake by another 1.6 m.

Figure D-03 | Longitudinal sightline section: viewing point, row-by-row rise, C-value annotations, and sightline schedule.
The screen dimensions are determined by balancing two constraints. First, back-calculation from viewing distance: the last row is 14.20 m from the screen. Requiring a vertical viewing angle of at least 12° gives a screen height of 2,985 mm and, at 16:9, a width of 5,307 mm. This is the minimum for legibility. Second, back-calculation from the proscenium proportion: screen width should ideally be 0.75–1.00 times the proscenium width, or 7.5–10.0 m, to maintain visual presence on the stage. The two lower limits differ by more than a factor of two, so a compromise is selected: 7,000 × 3,938 mm (16:9), with a screen-width-to-proscenium-width ratio of 0.70, slightly below the recommended range.
Why not make the screen larger? Because its height would increase at the same time. At a width of 7.5 m (ratio 0.75), a 16:9 screen would be 4,219 mm high. With its bottom at 950 mm, the top would reach 5,519 mm, increasing the first-row upward viewing angle from 41.0° to 45.4° and making an already excessive angle worse. Why not make it smaller? The last-row vertical viewing angle would approach 12°, making subtitles and charts difficult to read, and a 5.3 m-wide screen would look undersized within a 10 m proscenium. A width of 7.0 m is the intersection of these two constraints.
The first-row upward viewing angle is the only item that does not meet the target in this screen design. The screen top is at 4,888 mm; the first-row eye position is 1,150 mm and 4.30 m from the screen, producing an upward angle of 41.0°, above the 30° comfort range. Three remedies were evaluated in sequence: lowering the screen bottom from 700 to 350 mm above the stage (reducing the angle from 43.6° to 41.0°, a gain of 2.6°); reducing screen height (which conflicts with the proscenium proportion); and moving the first row back (each additional metre recovers only about 3°, while seat capacity falls quickly). The final approach is to meet the target from Row 3 onward: Row 2 is 36.1°, Row 3 is 27.1°. The first two rows are designated for VIP seating and flexible use, and the main image content is kept within the lower-middle 70% of the screen, bringing the effective viewing angle within 28°. This conclusion and the elevations are included in the construction drawings to prevent the issue from being discovered only after completion.
The narrow, vertical side screens are also determined by geometry. The clear proscenium width is 10,000 mm; subtracting the 7,000 mm main screen leaves 1,500 mm on each side. Since the main screen occupies most of the available width, the side screens extend vertically and are sized at 1,500 × 3,400 mm (approximately 1:2.27). They are used for vertically arranged event banners, timing, and prompts, matching the existing three-screen configuration. The pixel pitch is P2.5, with a minimum clear viewing distance of 2.5 m, less than the 4.30 m distance from the first row to the screen, so no row should see individual pixels. The last-row vertical viewing angle is 15.8°, above the 12° minimum.
Table 3 | Sightline and Key Screen-Design Checks
Check item | Calculated design value | Criterion | Conclusion |
First-row horizontal viewing angle | 110.0° | ≤120° (JGJ 57-2016) | Pass |
Last-row horizontal viewing angle | 40.9° | ≥30° | Pass |
Last-row viewing distance | 13.40 m (15.12 m at side seat) | ≤33 m | Pass |
C-value by row | 52–68 mm | ≥50 mm (lecture-hall criterion) | Pass |
Rise by row | 120–320 mm per level | ≥120 mm eye-to-head clearance | Pass |
Last-row downward viewing angle | 9.1° | ≤30° | Pass |
First-row upward angle to screen top | 41.0° | ≤30° | Meets target from Row 3 |
Last-row vertical screen viewing angle | 15.8° | ≥12° | Pass |
Screen width / proscenium width | 0.70 | 0.75–1.00 | Tight; selected compromise |
Criteria are based on JGJ 57-2016 and lecture-hall engineering practice. The 30° upward angle is a comfort limit, not a mandatory code clause.

Figure D-04 | Auditorium audio and lighting layout plan: seating zones, line-array suspension points and coverage angles, wall-mounted fill speakers, and overhead lighting array.
The main PA uses two line-array groups, suspended at 4,200 mm with a 6° down-tilt and ±48° horizontal coverage. The suspension points are set 300 mm inside the proscenium line so that the main acoustic energy falls on the audience rather than the stage microphone area. Coverage is calculated at 1 kHz. The axis distance increases from 4.42 m at the first row to 13.11 m at the last row, accounting for the 2,600 mm last-row rise that offsets the height difference. Two models are compared. Under free-field point-source attenuation of −6 dB per distance doubling, the level falls from 102.0 dB in the first row to 92.6 dB in the last row, a 9.4 dB difference that exceeds the 6 dB allowable non-uniformity. Under the near-field cylindrical attenuation model for a line array (−3 dB per distance doubling), the last-row level is 97.3 dB, a 4.7 dB difference within the allowable range.
The 4.7 dB result does not come from the speaker specifications alone; it is achieved through vertical directivity control. The line array concentrates sound energy in a narrow vertical band covering the audience. The attenuation rate at distance is reduced from about 6 dB for spherical spreading to about 3 dB. The trade-off is lower sound pressure outside the coverage band, such as at the ceiling and upper side walls, which also reduces reflections and reverberation excitation from those surfaces. The down-tilt should not simply be increased. Beyond 10°, Rows 3–5 in the front area would enter the array's strong coverage lobe, making their levels higher than those in the rear. The steeper incidence angle would also increase coupling between floor reflections and the microphone pickup area, raising feedback risk. A 6° down-tilt is the compromise that avoids excessive front coverage and insufficient rear coverage in this hall.
The sound-pressure budget assumes four speakers per side at 100 W each. With a sensitivity of 100 dB/W/m, 400 W corresponds to 126 dB at 1 m. Combining both sides adds 3 dB, giving 129 dB. Geometric attenuation over the 4.42 m distance to the first row is −12.9 dB, so the maximum level there is 116 dB. The design operating point is 102 dB, leaving 14 dB of peak and feedback headroom. This headroom is not wasteful: school events often combine children's choirs, live instruments, and wireless microphones, with peak factors far higher than steady speech. Without sufficient headroom, the limiter must work excessively and sound quality will deteriorate first.

Figure D-05 | Sound-coverage calculation: comparison of sound-pressure-level differences under free-field and line-array directivity models, with the output budget.
The difference between conference and performance modes may appear to be simply “bright versus dark”, but the evaluation criteria are different. Conference mode evaluates horizontal illuminance in the audience area (at 0.75 m, for notes and presentations), vertical illuminance at the lectern (at 1.2 m, for faces), uniformity, and glare. Performance mode evaluates vertical illuminance on the performance area (to separate performers from the background), adjustable color-temperature range, and color-rendering index. The same fixture inventory serves both sets of targets through beam distribution, aiming angles, and dimming curves rather than purchasing two separate systems.
The lumen method is used: E = Φ·N·CU·MF/A. All parameters are shown in the drawings for verification. Conference mode: 24 LED PAR fixtures in the audience area (5,000 lm each), CU 0.55, MF 0.80, over 270 m², produce 196 lx (target 200); 12 LED front-light fixtures at the lectern (6,000 lm each), CU 0.36, produce 518 lx (target 500); and 12 top-light fixtures on stage (4,000 lm each), CU 0.50, produce 240 lx (target 250). Performance mode: the audience area is reduced to 8 PAR fixtures and 65 lx; the performance area uses 12 front lights plus 8 side lights, CU 0.38, producing 912 lx over 32 m² (target 800–1,000); 8 backlights provide 108 lx on the cyclorama as background glow.
One common approach is deliberately rejected: conference mode should not achieve its illuminance target simply by dimming the lights. Dimming is used only for scene transitions; illuminance is determined by fixture quantity and beam distribution. Deep dimming can cause color-temperature drift (LED color shifts become obvious below 10% output), increased flicker depth, and reduced color-rendering index. Cameras may capture greenish faces or scan lines on screens. Therefore, the conference-mode specification of 4,000 K and Ra ≥ 90 is a single color temperature at full output, while the performance-mode range of 3,200–5,600 K is adjustable under dimming. These are specified separately in the acceptance schedule. There are 64 fixtures in total, with a connected load of 11.56 kW. Dimming uses DMX512 at 0–100%, 16-bit resolution. Circuits are configured as 12 × 16 A, with 20% spare capacity.

Figure D-06 | Lighting-illuminance calculation comparison: area illuminance, target lines, and fixture configurations in conference and performance modes.
Sound-insulation problems in school halls rarely originate in the wall itself; they more often occur at doors, windows, sleeves, and junctions. The partition wall between this hall and adjacent classrooms is modeled as 240 mm brickwork with plaster on both sides (surface density 512 kg/m², total thickness 280 mm). Its laboratory weighted sound reduction index is Rw 56 dB, Rw+C 55.2, and Rw+Ctr 53.4. One 1.5 × 2.1 m steel acoustic door in the rear wall (Rw 41) occupies only 3.15/90 = 3.5% of the wall area, but accounts for 69.5% of transmitted energy. It reduces the apparent wall rating from 56 to Rw,app 53 ( +C 51.6, +Ctr 49.3). This quantifies the principle that the weakest component controls the overall wall: improving the wall rating without treating the door will not improve the assembly.
The field value must be reduced further. A rigid junction is assigned a 5 dB flanking-transmission penalty, leaving a field R'w of only 48.0 dB, below the 50 dB target. Changing the junction to an elastic isolation pad reduces the penalty to 3 dB, giving R'w = 50.0 dB and meeting the target; DnT,w is 57.6 dB. A floating, structurally isolated floor could reach 52.5 dB. For the floor slab, the bare 120 mm cast-in-place slab has Ln,w 77.9 dB. Adding a 30 mm resilient layer and a 50 mm floating fine-aggregate concrete topping gives ΔLw 29.9 dB and a design Ln,w of 48.0 dB, below the 60 dB target.
The most easily overlooked detail is the wall-penetration sleeve. An area-weighted transmission estimate gives a combined τS of 4.68 × 10⁻⁴ for the 90 m² composite wall (including the door), corresponding to Rw,app 52.8 dB. If one φ100 sleeve is left unsealed (area 0.00785 m², τ ≈ 1), τS rises to 8.32 × 10⁻³ and the apparent wall rating falls to 40.3 dB. A fist-sized opening can cost 12.7 dB—effectively turning a 240 mm brick wall into a 100 mm aerated-concrete wall. For this reason, the project lists “mineral-wool filling and sealant at sleeves, sealing cable gaps, and elastic sealing where cable trays pass through walls” as separate concealed-work acceptance items, checked together with suspension-point verification. A 1.2 m sound-lock vestibule is also provided inside the acoustic door, and the two doors are not opened simultaneously.
Table 4 | Comparison of Sound-Insulation Assemblies: Five Solutions for the Same Target
Assembly | Base Rw (dB) | Composite Rw,app (dB) | Field R'w (dB) | Conclusion |
240 mm brick wall + steel acoustic door (rigid junction) | 56 | 53 | 48.0 | Does not meet target (−2.0) |
240 mm brick wall + steel acoustic door + resilient isolation pad | 56 | 53 | 50.0 | Meets target (adopted) |
Double-stud gypsum board + steel acoustic door | 52 | 50 | 45.0 | Does not meet target |
200 mm concrete wall + steel acoustic door | 59 | 54 | 49.0 | Does not meet target |
240 mm brick wall + solid-core composite door | 56 | 44 | 39.0 | Does not meet target |
Target: airborne sound insulation of at least 50 dB (Rw+C) between the hall and adjacent teaching rooms. Field values are estimated using junction K-factors and are not measured results.

Figure D-07 | Sound-insulation components and frequency characteristics: layer sequences, Rw curves, composite components, and assembly comparison.
Grouping the values in this chapter by who uses them downstream makes handover clearer. Geometry and construction data (926 m² developed area, surface-by-surface assemblies and absorption coefficients, and floor elevations by seating row) go into the architectural and interior-fit-out design-development drawings as the basis for material orders and setting out the steps. Equipment-position data (line-array suspension elevation of 4,200 mm and 6° down-tilt, lighting zones and suspension points, and control-room location) go into the audio/lighting layout drawings and must align with ceiling framing, cable trays, and access panels. Interface data (screen bottom at 950 mm, screen top at 4,888 mm, proscenium line, and sleeve-sealing details) go into the interface schedule and must pass concealed-work inspection before the interior finishes are closed.
The more important point is the chain of dependencies. A volume of 5.96 m³ per seat determines the scale of the absorption budget. The empty-room limit of 1.20 s pulls the mid-frequency setpoint down from 0.95 s to 0.85 s; that setpoint then determines the additional 126.3 m² of absorption and its distribution across four surfaces. Setting the viewing point 1.0 m above the stage determines row rises of 120–320 mm and a last-row elevation of 2.60 m, which in turn determines the 13.4 m last-row viewing distance, the minimum screen height of 2,985 mm, and the 41.0° first-row upward angle. The screen-to-proscenium proportion then limits the side screens to vertical strips only 1,500 mm wide. Changing any one link independently will cause downstream mismatches. This is why the design stage must calculate first, draw second, and brief the construction team afterward.
The maturity of an auditorium audio and lighting system is not measured by the length of its equipment list. It is measured by how long it takes to change events, how many people are needed, and whether errors can occur. This project focuses on repeatable scene operation, verifiable audio and lighting indicators, and maintainable operating procedures, resulting in six practices that can be reused directly.
Most annual auditorium activities fall into four categories: assemblies and ceremonies; open classes and lectures; artistic and club performances; and external exchanges and visitor reception. Each category has different requirements for lighting brightness and color temperature, PA gain structure, microphone-channel configuration, and source-signal status. During design development, the project broke these four scenarios into configurable parameter sets. Each set was verified during commissioning and saved as a preset for one-touch use during events. This converts on-the-spot operation, once dependent on the experience of a particular technician, into a standard procedure that any trained duty operator can reproduce.
The existing three-screen arrangement—a main screen and two side screens—creates an information hierarchy: the main screen carries the content, the side screens provide atmosphere and prompts, and the event-banner screen supports ceremony and announcements. The audio and lighting systems do not need to add another display; instead, fixture positions and sound levels are designed around the existing display conditions. In conference mode, stage-side light is reduced to avoid reflections on the large screen and overexposed faces. In performance mode, front light is balanced against background brightness, and audio presets are synchronized with image changes. Red-themed backgrounds for opening ceremonies and grade assemblies must also remain visually consistent with presentation slides under a unified color temperature. These details directly affect photography, video recording, and the quality of later promotional materials.
The overhead lighting array is the most eye-catching element in the photographs and one of the elements that requires the closest coordination with structural conditions during design development. Fixture positions must serve beam paths and illuminance targets; suspension points must be verified and accepted within the existing ceiling interface; power and dimming circuits require insulation protection and heat-dissipation planning; and adequate safety margins must be allowed for fixture dead loads and dynamic loads. Acceptance testing under WH/T 97-2022, dimmer performance verification under GB/T 14218-2018, and electrical construction quality acceptance under GB 50303-2015 provide the safety foundation for the visual result.
Feedback is one of the most common on-site problems in school auditoriums: a wireless microphone moves toward the front of the stage, the volume is raised, and a high-pitched squeal interrupts the event. Feedback cannot be controlled by a feedback suppressor alone. Four factors must be addressed together: speaker coverage angle, microphone pickup area, gain structure, and equalization presets. This project optimized loudspeaker coverage through sound-field testing so that more of the main PA energy falls on the audience rather than the stage. Feedback-suppression presets and channel gain allocation were then configured in the digital mixing console. Together with the stable absorption provided by the side-wall treatment and upholstered seats, the difference in listening conditions between an empty and full hall is reduced, so a full-house opening ceremony does not require major parameter changes. Professional practice also uses acoustic simulation during design to predict sound-pressure distribution, sound-field non-uniformity, and speech intelligibility, followed by verification against as-built measurements rather than relying on experience alone.
Some schools divide audio, lighting, and even display equipment into separate procurement packages to reduce apparent unit prices. In practice, costs are often shifted to integrated commissioning and ongoing maintenance. The comparison below reflects the actual operating logic of a school auditorium and can be used when evaluating proposals.
Comparison dimension | Separate procurement by different contractors | Integrated audio and lighting delivery |
Scene switching | Manually switch lights, adjust volume, and change signal sources separately; lengthy preparation before events | One-touch presets for assemblies, performances, and exchanges; repeatable parameters |
Signal paths | Inconsistent interface standards and level references can cause compatibility problems | Interfaces, levels, and signal flow planned together and verified one by one during commissioning |
Audio/lighting coordination | Illuminance and PA gain configured independently; images and sound may be out of sync | Illuminance, color temperature, volume, and source signals configured together for each scenario |
Safety responsibility | Suspension, electrical work, and dimming handled by different parties, with unclear boundaries | Suspension, insulation, and circuit protection checked item by item against one coordinated checklist |
Handover and training | Each contractor explains its own equipment; the school must combine the operating logic itself | Unified operating interface, one coordinated training program, and one complete set of drawings and documents |
Ongoing maintenance | Fault diagnosis may require several contractors to attend | One point of contact and faster fault isolation along the system signal path |
Primary and secondary school environments have three non-negotiable constraints. First, the venue is densely occupied and includes younger students, so lighting suspension, emergency power isolation, and electrical insulation need adequate safety margins. Second, the system is used frequently by operators who are often non-specialist support staff, so the interface must be intuitive and protected against accidental operation. Third, campus installation windows are limited, so cable routing and equipment suspension should avoid normal teaching hours wherever possible. The project therefore follows four stages: design development; phased supply and installation; integrated audio and lighting commissioning; and handover with operator training. Safety testing and document filing are completed before handover, not added after a problem occurs.

Figure 6 | Oblique full view of the auditorium audience area: seating zones, side-wall acoustic treatment, and wall-mounted loudspeaker coverage (on-site video frame).
The difficulty of campus procurement projects often lies not in the equipment itself, but in installation windows, overlapping trades, and responsibility boundaries. The following five areas required the most advance planning in this project and are common sources of problems in similar school auditorium audio and lighting projects.
Before and after a new campus opens, interior fit-out, mechanical and electrical, low-voltage, and furniture contractors often work in the same building at the same time. The project team conducted multiple site surveys before mobilization, coordinated with the school to confirm event requirements and building conditions, and prepared a customized supply and installation plan. During installation, weekends and school holidays were prioritized for cable routing and equipment suspension. Noisy or space-intensive tasks were scheduled outside teaching activities. A point-confirmation process was also established with the parties responsible for the interior-finish interfaces to prevent missing fixture or speaker suspension provisions from being discovered after the ceiling was closed. Concealed work must precede the finish layer; this sequence cannot be reversed.
Lighting circuits, audio cables, and control-signal cables must pass through walls and ceilings and reach the control room. Any omission may require demolition and rework after completion. This project made point verification, equipment suspension, and cable installation the first tasks after mobilization, with item-by-item acceptance completed before the interior interfaces were closed. Wall penetrations were sleeved and sealed with elastic materials to meet fire and electrical requirements while preventing gaps in the sound-insulation assembly. Ceiling profiles and the positions of fixtures, speakers, and access panels were aligned once in the design-development drawings to reduce site changes and secondary openings.
Passing individual equipment tests does not mean the integrated system will pass. The commissioning sequence is individual testing first, followed by integrated testing. Lighting checks cover fixture positions, beam paths, and dimming circuits. Audio checks cover sound-field performance and gain structure, while microphones and signal paths are verified one by one. After both systems pass, realistic scenarios such as assemblies, lectures, and performances are simulated for integrated testing. The team checks whether lighting fades according to the presets, audio channels switch correctly, and timing matches the existing display signals. Most compatibility issues emerge at this stage and must be resolved here.
Successful commissioning in an empty hall does not guarantee trouble-free full-house events. Before handover, the project simulated opening ceremonies and performances under full-house conditions, with multiple microphones and continuous scene changes. Wireless microphones were repeatedly moved to the front and sides of the stage to check channel gain headroom and feedback-suppression presets. Conference, performance, and ceremony lighting scenes were called up continuously to observe dimming consistency and circuit temperature rise. The team adjusted speaker coverage angles, channel equalization, and scene-switching timing accordingly, completing corrective work before handover rather than on event day. The value of testing lies in deliberately creating demanding conditions, not waiting for problems to occur.
Even the best system is of little value if the people receiving it do not know how to use it. At handover, the project provided on-site operating training for school support staff and teachers. Topics included daily power-up and shutdown procedures, selecting the four scene types, connecting wireless microphones and external equipment, identifying simple faults, and reporting issues. System drawings, equipment lists, operating instructions, and scene-preset descriptions were also handed over and filed as a complete project archive. For the school, these documents are often as valuable as the equipment itself during maintenance, upgrades, and staff transitions.

Figure 7 | Control-room view: the project team and school representatives commission the system and receive operating training around the digital mixing console (on-site photograph).
Chapter 5 discussed the challenges and methods. This chapter completes the record with photographs documenting the construction process. All images below were taken on site for the Auditorium Audio and Lighting System Procurement Project at Peiying Middle School (Science City Campus), Guangzhou. They are arranged by work sequence: material delivery; steelwork and suspension support; cable routing; ceiling closure and stepped-floor finishes; fixture and loudspeaker installation; concealed-work acceptance; and integrated commissioning and handover. They are actual site photographs, not design renderings. Some images include engineering-record watermarks and timestamps that correspond to specific construction milestones. The visible hard hats, reflective vests, fire extinguishers, hot-work supervision, and sign-off records for concealed ceiling framing provide direct evidence that safety and document filing were addressed before handover. The existing three-screen LED display, audience-area base, and main stage are venue facilities; this chapter records only the work and interface coordination related to the project's audio and lighting systems.
The first task after mobilization is not equipment installation, but verification of site conditions. Room length, width, and height; the seating rake; ceiling elevations and load-bearing points; the existing three-screen display and control-room locations; and power and signal routes must all be checked against the design-development drawings. Figure 8 records the storage of equipment and interior materials after delivery. Boxes are grouped by system and retain their original packaging and labels to support verification of models, quantities, and certificates while avoiding damage from secondary handling during finish construction. For campus projects, this stage also requires agreement with the school on the installation window, so noisy and space-intensive work can be kept outside teaching activities. Once positions are confirmed before the ceiling is closed, fixture locations, speaker suspension points, access panels, and wall penetrations can be aligned in one pass, reducing rework.

Figure 8 | Material delivery and unpacking inspection: equipment boxes and interior materials stacked by system, with original labels retained for item-by-item checking (on-site photograph, 2026-08-22).
All fixtures and loudspeakers are ultimately suspended from the structural support system, making the suspension substrate the first line of safety. Figures 9 and 10 record on-site steelwork. Workers wearing hard hats and reflective vests weld and secure components on the steel-grid structure. Fire extinguishers are positioned beside the work area and hot work is supervised, consistent with safe construction practices in a densely occupied school environment. At the same stage, ceiling framing, hangers, and maintenance walkways are checked and positioned, with load-bearing points reserved for later fixture suspension and cable trays. Welds, suspension points, corrosion protection, and grounding are inspected and documented before enclosure, avoiding discovery of inadequate structural conditions after fixtures are installed. Only after the support structure is sound can lighting effects and sound coverage be considered.

Figure 9 | Steel-structure welding: workers wearing hard hats and reflective vests, with a fire extinguisher and hot-work supervision in place (on-site photograph).

Figure 10 | Multiple trades working on the steel-grid structure above the stepped seating area: suspension supports and ceiling framing completed before ceiling closure (on-site photograph).
Audio cables, lighting power and dimming circuits, and control-signal cables must pass through ceilings and walls and connect to the control room. A single missing cable can require demolition and rework after completion. Figure 11 records ceiling cable-tray installation (engineering-record watermark dated 2026-07-27). Figure 12 shows trunking covers in the equipment room and floor cable-trunking organization (watermark dated 2026-08-20). Strong-current and low-voltage cables are routed in separate trays; spare cable length is retained for maintenance; cable ends are numbered and labeled; and wall penetrations are sleeved and sealed with elastic materials. These details affect electrical safety and fire protection and prevent sound-insulation assemblies from being compromised by gaps around penetrations. Rack wiring and signal-path labels are completed at the control-room end at the same time, keeping complex technology inside the racks and simple operation at the console.

Figure 11 | Ceiling cable-tray installation: cable trays, trunking, and cable routes laid out before ceiling closure (on-site photograph; engineering record dated 2026-07-27).

Figure 12 | Equipment-room trunking covers and floor cable-trunking organization: cables bundled, numbered, and provided with maintenance slack (on-site photograph; engineering record dated 2026-08-20).
Figure 13 shows the work at the finish stage. The stepped platform has taken shape row by row; cove lighting, downlight arrays, and access panels are in place; the vertically striped side-wall acoustic treatment is complete; and wall-mounted fill speakers have been installed. For the audio system, the side-wall treatment and upholstered seats provide stable absorption that directly affects reverberation time and speech intelligibility. For the lighting system, once the ceiling is closed, fixture positions, beam paths, and heat-dissipation conditions are fixed. This is why the project treated point verification, cable routing, and penetration sealing as first-round installation tasks and completed item-by-item acceptance with the interior works before enclosure, rather than waiting until the fixtures arrived to cut openings.

Figure 13 | Auditorium at the finish-construction stage: stepped platform, cove-lit ceiling, acoustic side walls, and wall-mounted fill speakers completed together (on-site photograph).
Figure 14 is a frontal view after installation in the stage area. A full row of professional fixtures and the stage truss are suspended overhead, while line-array speakers are mounted symmetrically on both sides. The scaffolding has not yet been removed, indicating that installation and initial adjustment are still underway. Figure 15 is a close-up of the line-array suspension. Chains, slings, and secondary safety measures are in place as workers adjust mounting height and down-tilt so that the main PA energy falls on the audience rather than the stage. This is the practical implementation of the earlier principle: calculate the sound field first, then determine speaker positions. The lighting system is checked for beam paths in both soft conference mode and performance mode, with insulation and heat dissipation of dimming circuits also verified. Suspension dead-load and dynamic-load margins, grounding, and insulation checks are documented in accordance with the acceptance requirements of WH/T 97-2022 and GB 50303-2015.

Figure 14 | Lighting array and stage truss installed above the stage, with line-array speakers suspended symmetrically on both sides (on-site photograph, installation and initial-adjustment stage).

Figure 15 | Line-array speaker suspension: chains and slings used to adjust mounting height, down-tilt, and coverage angle (on-site photograph).
Traceable records must be retained before concealed work is enclosed. Figure 16 shows the signboard record for concealed acceptance of the multifunctional hall ceiling framing. The participating parties jointly confirmed the work, signed, and photographed the record; the watermark gives the date as 2026-08-05. Such records are more persuasive for future maintenance, renovation, and responsibility allocation than photographs taken afterward. Integrated commissioning followed: individual equipment was tested first, then the systems were linked. Audio testing covered sound-field performance and gain structure; lighting testing covered fixture beam paths and dimming circuits. The team then simulated real scenarios such as assemblies, lectures, and performances. Figure 17 shows the project team and school representatives checking fixture positions, speaker coverage, and usage scenarios on site during closeout, while also conducting operator training and explaining the project archive. Only then was the system truly transferred to the school.

Figure 16 | Signboard record of concealed acceptance for ceiling framing: all project parties jointly confirmed and photographed the record for filing (on-site photograph, 2026-08-05).

Figure 17 | Final site verification and handover briefing: overhead lighting array, wall-mounted speakers, and stepped audience seating all in place (on-site photograph).
Viewed together with the empty-hall and full-house images in the surrounding chapters, these construction photographs form a complete evidence chain: the support structure and cabling determine safety; the finish layers determine acoustic conditions; equipment suspension determines beam paths and sound coverage; and integrated commissioning and training determine whether the school can use the system over the long term. For similar school auditorium projects, concealed-work records, test reports, training, and document filing should be listed as formal deliverables in the procurement requirements and signed off item by item.
Earlier chapters have shown the empty auditorium, audience-area sound reinforcement and acoustic treatment, the existing three-screen stage display, lighting effects, digital mixing console, and control-room training. A dedicated chapter has also recorded the construction process from material delivery to integrated commissioning and handover. This chapter adds scenes of full-house operation and live performances: opening ceremonies, grade assemblies, artistic performances, and routine teaching meetings, which demonstrate the audio and lighting systems under real operating loads. All images are on-site photographs or frames captured from on-site videos (Figures D-× are design-stage drawings, not renderings). Reverberation time, maximum sound pressure level, sound-field non-uniformity, illuminance, and other indicators remain subject to as-built acceptance measurements.

Figure 18 | Opening ceremony/grade assembly: stage screen, lectern, and a full audience of teachers and students; audio and lighting systems operating during a real event (on-site photograph).

Figure 19 | Routine teaching-meeting scenario: lectern sound reinforcement, presentation displayed on the large screen, and audience-area illuminance (on-site photograph).

Figure 20 | Live performance: students on stage, with the three-screen background, front lighting, and audience area all operating together (on-site video frame).
Taken together with the empty-hall images, these photographs reveal a clear design principle: the audience area must provide clear listening and comfortable seating; the stage must support visibility and performance; and the control room must make scene changes and handover straightforward. Empty-hall images show the construction and equipment, while full-house images verify performance under real loads. Neither is sufficient on its own as evidence of complete delivery. Consecutive opening-ceremony activities and artistic performances are the clearest demonstration that the audio and lighting presets have moved from commissioning records into actual use.
Q1: What is usually included in an auditorium audio and lighting procurement project?
A: The core scope has two parts: a sound reinforcement system (speakers, amplifiers, digital mixing console, microphones, feedback suppression and signal processing, cables, and connectors) and a professional lighting system (front lights, top lights, beam lights and PAR lights, dimming control, suspension, and cabling). Control and scene presets linking the two systems, necessary installation accessories, and operator training are also required. If the venue already has an LED screen, curtain, or stage facilities, these are generally existing conditions. The project only needs to reserve interfaces for signal and scene coordination rather than procure them again. The Peiying Middle School (Science City Campus) project followed this boundary to avoid including items belonging to other contract packages.
Q2: Why should a school auditorium have separate conference and performance lighting modes?
A: The optical objectives of the two scenarios are almost opposite. Meetings and open classes require even illuminance, consistent color temperature, and minimal glare for note-taking, viewing presentations, and recording. Performances need front light to separate people from the background, together with beam effects, color washes, and brightness changes to create rhythm. A single fixed lighting setup often results in glare during meetings and flat-looking performances. The dual-mode approach defines two sets of fixture positions and dimming parameters during design development, verifies each during commissioning, and saves them as scene presets for one-touch switching. This reduces preparation time and avoids dependence on a specialist operator being present.
Q3: If the venue already has a main screen and side screens, how should the audio and lighting systems connect to them?
A: First, define the scope clearly. Display equipment is existing infrastructure and should not be duplicated in the audio and lighting procurement, but signal and control interfaces must be reserved. Three tasks are essential: (1) define the relationship between lighting scenes and large-screen brightness in the design-development drawings to avoid overexposed faces or backgrounds overpowering the subject; (2) agree on the timing of audio presets and image changes in performance mode; and (3) reserve audio and signal channels for external laptops and playback devices. Including these items in an interface schedule and integrated-test cases is much more reliable than searching for adapters on event day.
Q4: What practical value does a line-array sound system offer in a school auditorium?
A: A line array offers controllable vertical coverage, concentrating more acoustic energy on the audience and reducing reflections and reverberation excitation from walls and ceilings. This helps avoid harsh sound in the front rows and weak sound in the rear. In speech-oriented school environments, it directly improves intelligibility and can reduce the likelihood of feedback when microphones are near the stage. A line array is not a cure-all, however. Mounting height, down-tilt, and coverage angle must be simulated against the room dimensions and checked together with the absorption provided by the side walls and upholstered seating. Otherwise, even expensive speakers may not perform as expected.
Q5: Feedback is common in auditorium sound systems. Where should troubleshooting begin?
A: Feedback is a positive-feedback loop formed by the microphone, amplifier, loudspeaker, room, and microphone. Treating only one point often addresses the symptom rather than the cause. A four-step check is recommended: (1) adjust speaker mounting angles and coverage to keep the main PA away from the stage microphone pickup area; (2) establish a proper gain structure so channel faders and master volume do not drive each other excessively; (3) configure feedback-suppression presets and channel equalization in the digital mixing console; and (4) reduce strong reflections through side- and rear-wall acoustic treatment. At acceptance, check acoustic gain and other indicators under GB 50371-2006 and conduct measurements under GB/T 4959-2011; this is more reliable than judging by ear.
Q6: How can lighting suspension and electrical safety be ensured in an auditorium?
A: Even lightweight fixtures are suspended above students and teachers, so safety must be addressed from the beginning. Four points are essential: verify suspension points against the existing structure and allow adequate dead-load and dynamic-load margins; provide insulation protection, heat-dissipation planning, and overload protection for power and dimming circuits; test fixtures and cabling under standards such as WH/T 97-2022 and verify dimmer performance under GB/T 14218-2018; and inspect electrical work under GB 55024-2022 and GB 50303-2015. Before handover, suspension, grounding, and insulation must be listed in the inspection checklist and documented. In densely occupied spaces, safety margins always take priority over lighting effects.
Q7: Which indicators should be tested when accepting an auditorium audio and lighting system?
A: Acceptance should cover three areas. For sound reinforcement, check maximum sound pressure level, transmission frequency response, sound-field non-uniformity, and acoustic gain under GB 50371-2006; measure under GB/T 4959-2011 and conduct acceptance under GB/T 28048-2011. For lighting, perform system acceptance tests under WH/T 97-2022 and check illuminance, color-temperature consistency, and dimmer performance. For electrical work, inspect cable insulation, grounding, and construction quality under GB 55024-2022 and GB 50303-2015. If the contract includes room-acoustic requirements, add measured reverberation time and speech-intelligibility criteria. All conclusions should be supported by measured data and records, not simply “it sounds fine” or “it looks bright enough.”
Q8: How should a school choose a professional audio and lighting system contractor?
A: Use three firm criteria: whether the contractor has complete delivery cases for comparable school auditoriums or lecture halls that can be inspected on site; whether it can provide integrated capabilities from design development through commissioning and training; and whether it understands school safety and teaching-schedule constraints. The Saijia project team offers advantages in survey response, coordination with installation windows, post-project inspections, and emergency site support. Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. is headquartered in Baiyun District, Guangzhou, and has long undertaken acoustic fit-out and stage lighting and sound projects for lecture halls, auditoriums, multifunctional halls, studios, and recording rooms. It can provide schools with consulting, site surveys, and case lists. Contact via WhatsApp: +1 3142036465 or Email: saijia.avl@gmail.com to request comparable project information or arrange a site visit.
Q9: We are a school in South America. What should we consider when purchasing auditorium and school-hall audio/lighting systems from China?
A: Pay attention to five milestones: (1) remote survey and design development—site drawings, photographs, or videos can be used to develop the scheme and equipment positions; (2) confirmation of the power supply standard—voltage and frequency differ across South America (Brazil: 127/220 V, 60 Hz; Colombia: 110 V, 60 Hz; Argentina and Chile: 220 V, 50 Hz; Peru: 220 V, 60 Hz), so equipment selection and power distribution must be checked item by item during design development; (3) factory power-on and integrated testing of the complete system before shipment to reduce delivery risks; (4) on-site installation guidance by an engineer or remote commissioning by video; and (5) inclusion of acceptance indicators and measurement methods in the contract for local verification. Contact via WhatsApp: +1 3142036465 or Email: saijia.avl@gmail.com. Communication hours accommodate South American time zones.
The following eight mistakes are based on frequent rework issues in school audio and lighting procurement. They are presented as one problem and one answer each and should be checked at project approval, tendering, and acceptance.
Mistake 1: A projector and a few speakers are all an auditorium needs.
A: A projector and speakers provide images and sound, but do not solve intelligibility, coverage uniformity, or scene switching. An auditorium has a large volume and multiple event types, so sound-field simulation, fixture layout, illuminance verification, and signal-path planning must follow applicable standards. Without these steps, the common results are poor audibility in the rear, visual discomfort in the front, and rewiring and readjustment before every event.
Mistake 2: Treat lighting as ordinary room lighting—as long as it is bright enough, it is fine.
A: General lighting focuses on uniformity and energy efficiency. Professional stage lighting must also address front-light modeling, color-temperature consistency, dimming curves, and performance rhythm. The fixture types, circuits, and control logic are different. An ordinary-lighting approach can cause glare in the audience and flat lighting on stage during meetings, lack of depth during performances, color casts in camera images, and damage to finished ceiling details when fixtures are added later.
Mistake 3: Hire the cheapest separate contractors for audio and lighting and simply connect the systems.
A: Lowering individual package prices often shifts costs to commissioning and maintenance: interface levels may not match, scene changes require manual operation, and fault diagnosis requires several contractors. School auditoriums need reliable operation throughout the year. The procurement requirements should identify one party responsible for integrated commissioning, unified training, and document filing, and this responsibility should be written into the contract rather than left to on-site coordination.
Mistake 4: Choose equipment by brand and specifications without sound-field simulation or equipment-position design.
A: The same equipment can sound very different depending on mounting height, down-tilt, and coverage angle. Speaker and lighting positions should be determined using room dimensions, seating capacity, and sightline analysis, then aligned with the existing interior interfaces in the design-development drawings. A specification sheet cannot replace a site survey or measurements before handover.
Mistake 5: Once fixtures are suspended and cables connected, there is no need to test demanding operating conditions repeatedly.
A: Risks are most likely under full-house conditions, with multiple microphones and continuous scene changes. Insufficient gain headroom, poor heat dissipation in dimming circuits, or overloaded suspension points may not be obvious during routine use, but can cause feedback, fixture dropouts, or circuit trips during an event. The correct approach is to simulate demanding conditions, inspect suspension, grounding, and insulation item by item, and retain records under the applicable acceptance procedures. Corrective work should be completed before handover.
Mistake 6: Accept the system by feel—sign off if “it sounds fine and looks bright enough.”
A: Audio, lighting, and electrical systems all have objective measurement methods. The four sound-reinforcement characteristics, reverberation time, background noise, illuminance and color temperature, cable insulation, and grounding can all be measured under the relevant national and industry standards. Acceptance should obtain test records, equipment lists, system drawings, and scene-preset instructions, which will also support future maintenance and staff handovers.
Mistake 7: Treat handover as the end of the project, without operator training or document filing.
A: School operators are often non-specialist support staff, and staff turnover can be high. Without a unified interface, scene-preset instructions, and practical training, the system may soon be taken over by manual operation, presets may be abandoned, and operating errors may increase. Training, drawings, equipment lists, operating instructions, and fault-reporting procedures must be listed as handover deliverables and signed off item by item.
Mistake 8: For cross-border procurement, compare only equipment prices and ignore power standards, shipping, and local delivery.
A: Power standards differ across South American countries, so fixture drivers, amplifier power supplies, and power-distribution designs must be adapted item by item. Ocean freight takes time, and equipment sensitive to shock or moisture needs factory power-on testing and reinforced packaging. Local installation capabilities vary, so the contract should define installation guidance on arrival, remote commissioning, acceptance criteria, and emergency response to avoid a situation where “the equipment has arrived, but the system is not operational.” Power standards, shipping responsibilities, installation guidance, and WhatsApp emergency contact arrangements should all be included in the purchase contract.
Auditorium audio and lighting systems span building acoustics, sound reinforcement, stage lighting, electrical engineering, and campus safety. Standards must therefore be referenced as a coordinated set. The table below lists national and industry standards commonly used for similar procurement projects. Schools can use it when preparing requirements, reviewing design-development drawings, and organizing completion acceptance. For this project, the actual test items and acceptance values are governed by the contract and completion-acceptance records.
Standard number | Standard title | Applicable system |
GB/T 50356-2005 | Code for Architectural Acoustics Design of Theatres, Cinemas and Multipurpose Halls | Architectural acoustics |
GB 50118-2010 | Code for Design of Sound Insulation of Civil Buildings | Architectural acoustics |
GB 50099-2011 | Code for Design of Schools | School buildings |
JGJ 57-2016 | Code for Design of Theatre Buildings (Section 6.4 Stage Lighting; Section 6.5 Stage Sound) | General |
GB 50371-2006 | Code for Design of Sound Reinforcement Systems in Halls | Sound reinforcement |
GB/T 4959-2011 | Methods of Measurement for Sound Reinforcement Characteristics in Halls | Sound reinforcement |
GB/T 28048-2011 | Code for Acceptance of Sound Reinforcement Systems in Halls and Sports Venues | Sound reinforcement |
WH/T 25-2007 | Guidelines for Sound Reinforcement System Engineering in Theatres and Other Performance Venues | Sound reinforcement |
WH/T 97-2022 | Code for Acceptance Testing of Stage Lighting Systems | Lighting |
WH/T 60-2013 | General Technical Conditions for LED Stage Luminaires | Lighting |
WH/T 26-2007 | Photometric Testing and Marking of Stage Luminaires | Lighting |
GB/T 14218-2018 | Performance Parameters and Test Methods for Electronic Dimming Equipment | Lighting |
GB 50034-2013 | Standard for Lighting Design of Buildings | Lighting |
GB 55024-2022 | General Code for Building Electrical and Intelligent Systems (Mandatory Engineering Construction Code) | Electrical |
GB 50303-2015 | Code for Acceptance of Construction Quality of Building Electrical Engineering | Electrical |
GB 50016-2014 (2018 edition) | Code for Fire Protection Design of Buildings | Fire safety |
The longest possible standards list is not necessarily the best one. What matters is identifying during design which clauses must appear in the drawings, and during acceptance which indicators must be supported by measured records. For example, the four sound-reinforcement characteristics correspond to GB 50371-2006 and GB/T 4959-2011; lighting-system acceptance corresponds to WH/T 97-2022, dimmer performance to GB/T 14218-2018, and electrical safety to GB 55024-2022 and GB 50303-2015. If the contract includes room-acoustic requirements, reverberation-time calculations, sound-field simulation, and speech-transmission indicators should also be included in the acceptance schedule. Listing standard numbers in tender documents and acceptance forms is far more useful than making a general statement in promotional copy that the project “complies with national standards.”
Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. undertakes projects worldwide for school auditoriums, lecture halls, multifunctional halls, studios, recording rooms, and other assembly venues. Its services include audio and lighting system procurement, installation, and commissioning, as well as acoustic fit-out, sound reinforcement, video display, and centralized control systems. The company provides rapid site surveys, design development, coordination with installation windows, and post-handover inspections. South America is a key overseas service market.
For schools, the practical value of a local project team is reflected at three stages. During project planning, the team can survey the site and prepare a feasible system scope and procurement list based on building conditions. During implementation, it can coordinate installation windows with the general contractor and interior-fit-out team to reduce disruption to teaching. After handover, it can reinspect the system before events and provide refresher training when personnel change. In addition to new campuses, the company also undertakes upgrades to existing auditorium audio systems, lighting renovations, acoustic treatment, and supplementary operator training. If you are preparing requirements, comparing proposals, or planning completion acceptance, you are welcome to request comparable school-project case lists, standards cross-reference tables, or a site-survey appointment.
Looking back at the Auditorium Audio and Lighting System Procurement Project at Peiying Middle School (Science City Campus), Guangzhou—from equipment supply and installation, through sound-field and beam-path commissioning, to opening ceremonies, grade assemblies, and consecutive artistic performances—the real proof is not any single piece of equipment. It is the ability of sound reinforcement and professional lighting to work together under one scene logic. The PA remains clear with a full audience; the lighting knows when to soften and when to intensify; signal timing is coordinated with the existing large screens; and any trained operator in the control room can call up a scene with one touch. Ultimately, the value of a school auditorium is measured by the quality and reliability of the events it supports.
If your school is planning a new auditorium or renovating an existing hall, we recommend including four items in the requirements as early as possible: the scene list, indicator definitions, acceptance criteria, and training/document handover. One more question during planning can prevent one more round of rework later. For design consultation, site surveys, or comparable project information, please contact Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd.
Primary Regulatory Standards: GB/T 50356-2005, GB 50371-2006, GB/T 4959-2011, GB/T 28048-2011, WH/T 97-2022, GB/T 14218-2018, GB 55024-2022, and GB 50303-2015.
Contact Us: Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. | WhatsApp: +1 3142036465 | Email: saijia.avl@gmail.com | Address: Room 615, Building 3, No. 135 Huangyuan Road, Baiyun District, Guangzhou.
Overseas Service Areas
Key Region: South America
Countries: Brazil, Argentina, Colombia, Chile, Peru, and Venezuela.
Guangzhou Saijia Acoustic & Lighting Engineering Co., Ltd. provides comprehensive solutions for school auditoriums, lecture halls, conference halls, cultural centers, and multi-functional venues across South America. Our services encompass system design, equipment supply, installation, commissioning, and final project handover. We offer remote design refinement, localized project coordination, and technical documentation provided in multiple languages.
For the calculation process, parameter definitions, and drawings from the design phase, please refer to the attached "Design Calculation Report."